Beruflich Dokumente
Kultur Dokumente
Guided By:
Mrs. B. PANDYA
Mr. A. SINGH
Department Interface
Functions
• Regulation of the quality of raw materials,
packing materials (wooden drum), In process
checks and Final testing of finished cables.
• Handling customer Inspections & preparation
of inspection reports and documents.
• Hold all non-conforming products prior to
dispatch.
• Maintains BIS License.
Standards
For 1.1 kv LT power & control cables, we have
following BIS License:
TESTS COVERED:
• Routine Test
• Type Test
• Acceptance Test
• Optional Test
Routine Test
These type of tests made by the manufacturers on all finish cable
lengths to demonstrate the integrity of cable.
SIGNIFICANCE :-
A cable is considered flame retardant if it is tested ,is ignited but extinguishes
again when the external heat supply ceases and the spread of the fire does not
exceed the given maximum value.
REQUIREMENTS :-
The length of the test specimen shall be 850 mm in a finished condition.
Burning time of ethanol in min. , t = K + D / 5
where K = 1 for c/s area <= 2.5 sq.mm
K = 2 for c/s area > 2.5 sq.mm
D = external dia. Of test specimen
Quantity of ethanol = 20 * t ml
GUIDED BY:
Mr. P.N. SINGH
Mr. A. PATIL
Functions Of Department
• Periodic Maintenance of every machine on the shop
floor.
• Attending Breakdowns
• Making job orders, indents & preserving maintenance
records.
• Maintenance of Electrical Sub – Station, Utilities.
• Development Activities to improve the Plant
Productivity.
Preventive Maintenance
• Yearly preventive maintenance schedule is prepared for
all machines.
• As per yearly schedule, monthly preventive schedule is
made.
• As per the schedule & availability of machine,
Department attends to the machines & undertakes
activities listed in PM checklist.
• Necessary machine modifications are done in
consultation with respective HOD’s.
• Records of inspections carried out by external agencies
are maintained in Engineering Department.
Breakdown Maintenance
• In case of any machine breakdown, the concerned dept.
informs the Engineering Dept.
• The Dept. analyzes the nature of breakdown & takes
necessary action.
• The required spare parts are taken from the stores.
• Incase the spare parts are not available, the Dept. prepares
the Indent & forward it to the materials Dept.
• At the same time if possible the Dept. provide the
temporary arrangement to start the machine.
• Necessary entries regarding the breakdown are made in
Log book.
Utilities
• HOT WATER GENERATOR • COMPRESSOR
OUT PUT : 400000 IR1(100 Psi)
KCAL/HR IR2(125 Psi)
MAX. TEMP. :1400C IR3(125Psi)
ELGI(250 Psi)
FUEL :HSD
Ensure
• water circulation pump
• proper battery connection
• optimum engine oil level
• diesel line valve in open condition
• switch in idle position
• proper coolant water level
• proper water level in cooling tank
DG Set Troubleshooting
1- 90 mm , 400 A 27- CAPACITOR, 250 A
2- 42 ARM ,200 A 28- DT ,250 A
1-
3- LIGHTING .200 A 29- FURNACE, 32 B, 250 A
4- 6+1 ,200 A 30- 120 mm, 400A
5- DG ROOM ,400 A 31- HEAVY REW 3 , 250 A
6- 80 mm, 200 A 32- 61 B, 400 A
7- STRIP REW, 200A 33- 42 B NEW, 250 A
8- LIGHTING, 200 A 34- 6+1 TUB, 250 A
9- 72 B ARM, 200A
10- 24 B,200 A
11- 3+1, 200 A
12- TEST HOUSE, HWG, 200A
13- 4+1, 200 A
14- 37 B, 200 A
15- 19 B,WATER PUMP, 200 A
16- CAPACITOR, 200 A
17- 11 DIE RBD, 800 A
18- 150 mm, 600A
19- 9 DIE Al, 400 A
20- 9 DIE CU, 630 A
21- CAPACITOR,250 A
22- 150 mm MIXTURE, 250 A
23- EOT CRANE 15T, 250 A
24- 17 DIE CU, 250 A
25- CHILLING, 250 A
26- 60 mm, 250 A