Beruflich Dokumente
Kultur Dokumente
Ltd.
Submitted By:
Debasis Senapati
Madhura Modi
Hilak Patel
Priya Agarwal
Pulokesh Ghosh
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
TIMELINES
Nov 2005
Shortlisting of two
bidders GMR-Frapot
and Reliance-ASA by
bid evaluation
committee
Sept 2005
Five consortiums April 2006
submitted bid for DIAL entered into
Delhi and Six for operations,
Mumbai management and
Jan 2006 development
agreement (OMDA)
Mandate was
with Airport
awarded to GMR led
Authority of India
consortium to
(AAI)
modernize the Delhi
Airport after a
competitive bidding
process
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
Project Brief
STAKEHOLDERS
Delhi International Airport Private Limited (DIAL) is a joint venture
consortium of GMR Group (54%), Airports Authority of India (26%), and DIAL
Fraport & Eraman Malaysia (10% each). GMR is the lead member of the
consortium; Fraport AG is the airport operator in Frankfurt Airport,
Germany, Eraman Malaysia - the retail advisors 10%
10%
54%
DIAL entered in to an Operations, Management and Development 26%
Agreement (OMDA) on April 4, 2006 with the Airport Authority of India
(AAI). The initial term of the concession was for 30 years extendable by a
further period of 30 years.
On 3rd July, 2009, a new world class integrated passenger terminal GMR AAI Farport AG Eraman Malasia
(Terminal 3) was commissioned. The first phase of the airport was designed
and capable to handle 60 million passengers per annum (mppa). In • DIAL is a Joint Venture formed to operate,
subsequent stages, the airport will be further developed with an ultimate manage and develop the IGI Airport
design capacity of 100 million passengers per annum • GMR is the lead member of the
consortium
As per ACI, ASQ rating IGI ranked No.2 next to Incheon Airport (South • Fraport AG is the airport operator
Korea) in its group Airports ranging up to 35 million Passenger movements • Eraman Malaysia is the retail advisor.
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
• Public-private partnership arrangements have existed throughout history, but have become
significantly more popular across the globe since the 1980s as governments attempt to
obtain some benefits from the private sector without having to make the full privatization
jump
• Due to limited funding and increasing constraints, many government agencies are looking into different models of public-
private partnership (P3) as a means of maintaining updated infrastructures without having to make large investments. There
are many different types of public-private partnerships to fit various construction, operation, ownership, and revenue-
generating scenarios.
• These models operate on different conditions on the private sector regarding type of project (for example, a road or a prison),
level of investment, ownership control, risk sharing, technical collaboration, duration of the project, financing mode, tax
treatment, management of cash flows etc.
• Some Examples: From 1990 to 2009, almost 1,400 PPP arrangements were signed just in the European Union (EU),
representing a capital value of about €260 billion. Since 2008 – the onset of the global financial crisis – the EU estimates that
PPP deals in the trading bloc have declined by over 40%.
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
• The private component of the partnership operates and Build-Own- • the public partner builds, possesses, and operates the
Operation and maintains the project, while the public agency acts as the Operate- project for a limited time, then the facility is transferred,
Maintenance owner of the project. Transfer P3s free of charge and including ownership, to the public
P3s • Examples of these contracts include bridges and tollways. agency.
Advantages Disadvantages
•Better infrastructure solutions than an initiative that is •Every public-private partnership involves risks for the
wholly public or wholly private. Each participant does what private participant, who reasonably expects to be
it does best. compensated for accepting those risks. This can increase
government costs.
Regulatory initiatives
• The GoI has a progressive financial support system for PPP projects. Some of the key initiatives include
India Infrastructure Project Development Fund (IIPDF), Viability Gap Funding (VGF), resources for annuities/
National P P P policy (2011) and Draft P P P Rules (2012) availability-based payments, long-tenor lending, re-financing facility, infrastructure debt funds, etc. The GoI
In the light of growing PPP trends and policy/institutional intervention, the GoI had felt the need to have a broad will provide legislative and policy support to develop equity, debt, hybrid structures and appropriate credit
policy framework in place. The Ministry of Finance drafted a National PPP policy for soliciting suggestions in 2011. enhancement structures.
Subsequently, it came out with a comprehensive set of draft PPP rules in 2012. The draft policy proposes to focus
• The GoI is expected to undertake capacity building interventions to develop organizational and individual
on assisting Central and State Government agencies and private investors by: capacities for the purpose of identification, procurement and managing of PPPs.
• Undertaking PPP projects through streamlined processes and principles • The PPP Cell in the Department of Economic Affairs will have professionals who provide technical support to the
• Ensuring the adoption of value-for-money approach through optimization of risk-return allocation in project ministries and other authorities developing PPPs.
structuring Financial initiatives
• Attaining adequate public oversight and monitoring of PPP projects • Bank loans to earning-based PPP infrastructure projects under concession agreements are to be treated as
• Developing governance structures to facilitate competitiveness, fairness and transparency secured advances. This is expected to boost infrastructure financing, particularly for BOT roads projects and
power sector projects. 3
Prominent features of the policy
• ECB norms have been relaxed to help infrastructure companies raise more funds from overseas markets 4
• The GoI plans to formalize PPPs as preferred implementation models. It has laid down strong procedures to
procure a PPP project. In order to instill transparency in the PPP process, it will publish separate mandatory • Infrastructure companies are allowed to raise bridge finance from overseas market under the automatic
disclosures and fair practices, set up a dedicated dispute resolution mechanism, develop new market-based route. Earlier, the companies were required to seek permission from the RBI in order to raise bridge finance.
products (e.g., pre-bid rating) and explore possibilities of setting up a web-based PPP market place.
• ECB limit has been increased for NBFC-IFCs (non-banking finance companies classified as infrastructure
• The PPP process should comprise four phases: finance companies) under the automatic route from 5 0 to 7 5 of their owned funds, and hedging
requirement for currency risk has been reduced from 1 0 0 of their exposure to 7 5 .
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
All risks associated The intricacies and Risk associated with All the risks Operational factors
with the overall involvement of govt. increase in costs due associated during related to financing,
project start and and political risks to some unforeseen the construction future agreements,
operational planning associated with it circumstances and phase such as land sharing of revenue
how to avoid them acquisition etc. etc.
Project Risk Political Risk Cost Overrun Risk Construction Risk Operational Risk
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
Project Risk Political Risk Construction Risk Cost Overrun Risk Operational Risk
Project Risk
As per EIL final report, the estimated area required and permitted as per Financial Closure was 470179 m^2. However, the
area constructed by DIAL was 553887 m^2
The difference in area is 83708m2 which accounts for 17.18% of the overall size
EIL accepted 98% of the constructed land and had not approved the 2% of the total area meant for the following purpose:
o 8652 m2 is for the food court and retail area at CIP, Office and Hotel level
o 1914 m2 in the mezzanine level is meant for plant rooms, DIAL BHIS control room, Transfer area for passengers and
stores
AAI have submitted the area to be considered for the following reason:
o Food Court will increase the commercial activities in the passenger Terminal Building (PTB), which will enhance
passenger facilitation and also fetch additional revenue
o Even though the plant and control rooms may not have commercial potential, they would increase the operational
efficiency and convenience of passengers
Also due to this expansion, all other items estimated in the initial cost increase proportionately
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
Project Risk Political Risk Construction Risk Cost Overrun Risk Operational Risk
Political Risk
There was no political risk as such, however conflict of interest between the centre and the state govt
Risk of change in govt and modification in contract or PPP laws at later date
Construction Risk:
This type of risk includes matters related to land encroachment, procurement of additional land if required, removal of
obstruction to ensure safety and efficiency and providing utilities
An agreement was signed between state govt. and DIAL for such services, known as State Govt. Support Agreement (SGSA)
SGSA also provided help in procuring various clearances required to implement the project as mentioned in OMDA
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
Project Risk Political Risk Construction Risk Cost Overrun Risk Operational Risk
Cost Overrun Risk
DIAL had taken the following cost overrun mitigation risk measures for the project:
Benchmarking: Engaging Jacobs to carry out the benchmarking exercise in compliance with the Schedule 21 of OMDA
(Operations, Management and Development Agreement)
o The report was however submitted in Feb 2009, when selection of many contracts had already been accomplished
Incentivization: To control costs, the contractors usually sign “sharing of pain-gain” agreement, where penalties are built
into contracts by adjusting contractor’s fee depending upon target and actual costs. However, no such relevant clause was
mentioned in the agreement
Dis-incentivization: This is another method where contractors are disincentivized to increase costs by capping their fees at
a fixed absolute level rather than a percentage of base out; in DIAL case it was the latter
Engaging external Project Management Consultant (PMC): Parsons Brinckerhoff International Inc was engaged by DIAL as
the PMC.
o The scope included giving cost control advice, warning for variance and assessment of implication on cost for design
changes
o KPMG when reviewed three cost monitoring reports provided by the PMC didn’t find any comparison between a
package’s original and final cost estimate or the analysis for cost escalation or corrective action that would be taken in
the future
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
Project Risk Political Risk Construction Risk Cost Overrun Risk Operational Risk
Cost Overrun Risk
Implications:
The original project cost approved by DIAL and communicated to AAI was 8975 crore
Final project cost adopted by Airports Economic Regulatory Authority (AERA) was 12502.86 crore (43.25% higher)
The financial gap was met by levy of Development Fees which was 27.32 per cent of the total capital outlay
OMDA didn’t predict earlier about charging this DF from passengers since the entire funding was supposed to be done through debt and
equity only
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
Project Risk Political Risk Construction Risk Cost Overrun Risk Operational Risk
Operational Risk
Right of First Refusal: State Support Agreement (SSA) provided the ROFA to DIAL with regard to any other airport being
planned within the distance of 150 km radius.
o DIAL can win the bid through a competitive bidding process. If unsuccessful, if its bid is within 10% of most
competitive bid, it would be allowed to match it and win
o Validity given: 30 years
Clarity in definition of Aeronautical and non-aeronautical services: It differed between AERA Act and OMDA, thus
affecting the calculation of targeted revenue for tariff fixation
Maintaining Debt to Equity Ratio: DIAL submitted a proposal to maintain a D/E ratio of at least 2:1. Further they were
restricted to raise fresh equity as this will result in dilution of the shareholding of AAI/AAI nominees
High Risk Premium: EIL commented that the risk premium considered by the principal contractor was high due to high risk
of the project, and it was totally borne by JVC leading to further increased costs
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
• Following Analysis were done by the National Council of Applied Economic Research and published in
March 2017 report
• Direct economic impacts are the financial and employment changes for all the existing establishments
whose activities are linked to the airport such as airport employees, freight companies, retailers,
facilitators of movement of passengers and cargo etc.
• Input-output (I-O) framework has been considered as an appropriate approach to provide an assessment
of the multiplier effects
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
Profile of passengers travelling in terms of gender and their occupation in IGI Airport through a survey conducted
among 3500 travellers
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
• By 2020, the overall economic impact of Delhi Airport is expected to be Rs 909.5 billion, which will be 0.7
per cent of the National GDP and 22.2 per cent of Delhi’s GDP.
• Delhi airport’s operations contributed Rs 294.7 billion (0.45 per cent) and the construction sector
contributed INR 68.23 billion (0.104 per cent) to the national GDP (in 2009–10)
• In terms of economic performance, a major portion of Delhi airport’s revenue comes from non-aeronautical
services (44.8 per cent) followed by aeronautical services (36.4 per cent) and the remaining portions of
revenue comes from services like cargo, CPD and other income.
Project Transaction Risk Social Economic Details of
Introduction PPP Financials Conclusion
Overview Document Management Impact Impact Financing
Operations Phase
Gross Value Added Employme
Output (INR Bn) nt % GDP %Employment Value Added Employment
Operations
Total Impact 491.2 294.7 1577.7 0.45 0.34
Induced Impact 291 174.6 1061.6 0.27 0.23
Direct Impact
Direct and Indirect 200.2 120.1 516.1 0.18 0.11 Direct Impact Indirect Impact
Indirect Impact
Induced Impact
Direct Impact 71.5 42.9 64.974 0.07 0.01 Induced Impact
Airport Transport 49.28 29.57 33.956
Airport Services 22.22 13.33 30.118
Indirect 128.7 77.2 451.126 0.12 0.10
I-O table multiples 2.8 0.722
Conclusion
DIAL was first of its kind project taken in brownfield airfield project and it has been declared 2nd best airport in its category and has won many
awards
As it was first of its kind modalities of project were not exhaustive and CAG has reported that government/passengers suffered at cost of
promoters
The total cost overrun of project was 42% of total project cost but project was completed in time
The promoters of led by GMR has got extremely good deal and long term rating of DIAL is AA-/stable which is excellent for this kind of project
Currently many new airports are being built using the same model. The design Approach model was a great success
Recommendations
Contracting in PPP projects should be rigorously defined so that none of contracting party faces undue loss or gain
The clause of Right to first refusal should be decided keeping in find future revenue streams and in way that it doesn’t thwart
competition
In terms of bid evaluation weightage allocation to higher non-aeronautical revenue share needs to be revisited for future bids (AAI
made 30% revenue loss due to this)