Beruflich Dokumente
Kultur Dokumente
POWER PLANT IN
PAMPANGA
THE TEAM
TA G A L A HONTIVEROS PA G S I B I G A N
SHAIRAH D AV E F R A N C I S L AW RE NC E
LEADER
D AY R I T LORIA
DANIEL MARQUIS CANE
Power Demand
According to the 2016-2040 Power Development Plan, despite the
country’s global risks and uncertainties due to natural calamities
such as Sendong (2011), Pablo (2012) and Yolanda (2013) the
power consumption of Filipinos still grew by 19.14% with an AAGR
of 4.49% during the year 2011-2015
The Client
Pampanga II Electric Cooperative, Inc. commonly known as
PELCO II is one of the 14 electric cooperatives in Region III and
was registered and incorporated on April 23, 1979, the date of its
first energization is November 15, 1979.
Power Demand
The Distribution Development Plan 2016-2025 published by
Department of Energy, includes a projection for the peak demand
for each electric company including PELCO II.
2015 76.3
1
2016 85.3
3
2017 88.1
8
2018 94.0
7
2019 100.
1
2020 106.22
2021 11 2 . 3 8
Power Demand
C A PA C I T Y O F T H E P L A N T PROJECTION
In determining the capacity of the power plant to be designed, the The proponents used the projected peak demand of PELCO II for
proponents considered the projected peak demand for PELCO II in the year 2022, because the proponents considered the time
the year 2022 and the peak load of PELCO II as of March 31, 2018 required for the construction of the power plants
D E T E R M I N I N G T H E C A PA C I T Y C O M P U T AT I O N
To determine the capacity of the power plant the proponents 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝑡ℎ𝑒 𝑃𝑙𝑎𝑛𝑡 = 𝑃𝑟𝑜𝑗𝑒𝑐𝑡𝑒𝑑 𝑃𝑒𝑎𝑘 𝐷𝑒𝑚𝑎𝑛𝑑 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝑃𝑒𝑎𝑘 𝐿𝑜𝑎𝑑
deducted the actual current peak load of PELCO II to the
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝑡ℎ𝑒 𝑃𝑙𝑎𝑛𝑡 = 118.55 𝑀𝑊 − 91.937𝑀𝑊
projected peak demand of PELCO II for the year 2022 with
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝑡ℎ𝑒 𝑃𝑙𝑎𝑛𝑡 = 26.613 𝑀𝑊 ≈ 𝟐𝟕 𝑴𝑾
accordance to the DOE’s projection.
Objectives
GENERAL OBJECTIVE
SPECIFIC OBJECTIVES
Computations for: The proponents didn’t include Computations for: The proponents didn’t include
• Diesel generator set the plant layout for the diesel • Solar Modules the plant layout for the solar
• Thermal efficiencies, heat power plant • Land Area power plant
rates • Capital Cost, O&M cost
• Cooling system • Rate of Return
• Machine Foundation
• Capital Cost, O&M cost
• Rate of Return
Scope Delimitation
Computations for: The proponents didn’t include
• Steam turbine/s the plant layout for the coal-
• Boiler/s fired power plant, the
• Cooling system/s computations for pulverizer,
• Machine Foundation scrubber, and filters.
• Capital Cost, O&M cost
• Rate of Return
Power Plants
DIESEL POWER PLANT
FA C T O R S C O N S I D E R E D
Power Plants
COAL-FIRED POWER PLANT
The proponents considered coal-fired power plant as an alternative
design since according to the Department of Energy, the coal
reserves in the Philippines amounts to a total of 2,386,700,000
tons. In addition, as stated by IEA Clean Coal Centre, there is
potentially up to 270 billion tons of coal resources in the
Philippines.
FA C T O R S C O N S I D E R E D
Power Plants
SOLAR POWER PLANT
The proponents considered solar power plant as an alternative
Pampanga is known for its 22 MW Solar Power Plant in Clark, also
design since based on NREL, the potential photovoltaic electricity
it is famous for its potential for Solar Power Plant.
production in Pampanga is 4 to 4.5 kWh/kWp.
Constraints Economical
offs
Environmental Societal Health & Safety Manufacturability Sustainability Total
Economical - 0 1 1 1 1 4
Environmental 1 - 1 1 1 1 5
Societal 0 0 - 0 1 0 1
Manufacturability 0 0 0 0 - 0 0
Sustainability 0 0 1 0 1 - 2
Total: 15
Constraint
offs Rank Weight (%)
Environmental 1st 50
Economical 2nd 33
Percent Weight
17%
50%
33%
2 Slightly Satisfied The constraints for the specific options were slightly satisfied. Ranges
from 18% - 33%
3 Moderately Satisfied The constraints for the specific options were moderately satisfied.
Ranges from 34% - 50%
4 Satisfied The constraints for the specific options were satisfied. Ranges from 51%
- 66%
5 Very Satisfied The constraints for the specific options were very satisfied. Ranges from
67% - 83%
6 Extremely Satisfied The constraints for the specific options were extremely satisfied. Ranges
from 84% - 100%
R AT I N G D E S C R I P T I O N
Constraints & Trade-
Constraints
Power Plant Type
Specific constraints
offs
DM5415-06
Diesel Power Plant
16CM32C SST150
Coal Power Plant
SST100
Solar Power Plant
Mono-crystalline Poly-crystalline
Environmental
Water consumption, 33,102.1149 22,387.0922 557.6926 722.7241 No water consumption No water consumption
Liters/(MW-hour) (Computed) (Computed) (Computed) (Computed)
Safety
20 20 15 15
Particulate Matter (PM) in
(International Council on (International Council on (Assessment of Coal-Fired (Assessment of Coal-Fired No PM Emission No PM Emission
𝜇g/m3
Combustion Engines) Combustion Engines) Boiler Air Emissions) Boiler Air Emissions)
© 2018 Slidefabric.com All rights reserved. S L I D E 23
ANALYSIS OF DESIGN OPTIONS
Noise Emission
17% Coal 1 & 2 (95 dBA)
X1 Diesel 1 & 2 (93 dBA)
51% 90 dBA
100% Solar 1 & 2 (0 dBA)
𝑋1 − 17% 93 − 95
=
51% − 17% 90 − 95
𝑋1 = 30.6 %
SENSITIVITY
POSSIBLE ARRANGEMENTS ANALYSIS
Percent Weight 50% 33% 17%
SENSITIVITY
F O R T H E 1 ST A R R A N G E M E N T
SENSITIVITY
F O R T H E 1 ST A R R A N G E M E N T
2 Coal 2
69 68
62 64
3 Solar 2 61
51
4 Diesel 1
5 Solar 1
6 Coal 1
1st
SENSITIVITY
F O R T H E 2 ND A R R A N G E M E N T
Land Use 6 6 4 4 1 1
Environmental 1 2 6 6 6 6
Water Consumption
Operational &
Economical 1 2 3 3 6 6
Maintenance Cost
6 6 4 4 1 2
Return of Investment
SENSITIVITY
F O R T H E 2 ND A R R A N G E M E N T
3 Coal 1 72
68 68 69
3 Coal 2 64
58
5 Diesel 2
6 Diesel 1
2nd
SENSITIVITY
F O R T H E 3 RD A R R A N G E M E N T
Land Use 6 6 4 4 1 1
Environmental 1 2 6 6 6 6
Water Consumption
Operational &
1 2 3 3 6 6
Economical Maintenance Cost
6 6 4 4 1 2
Return of Investment
SENSITIVITY
F O R T H E 3 RD A R R A N G E M E N T
3 Coal 2
6 Solar 1
3rd
SENSITIVITY
F O R T H E 4 TH A R R A N G E M E N T
Power Plant Type ANALYSIS
Diesel Power Plant Coal Power Plant Solar Power Plant
Land Use 6 6 4 4 1 1
Environmental 1 2 6 6 6 6
Water Consumption
Operational &
1 2 3 3 6 6
Economical Maintenance Cost
6 6 4 4 1 2
Return of Investment
SENSITIVITY
F O R T H E 4 TH A R R A N G E M E N T
Rank Design Option
ANALYSIS
1 Solar 2
4TH ARRANGEMENT
Diesel 1 Diesel 2 Coal 1 Coal 2 Solar 1 Solar 2
2 Solar 1
3 Coal 1
3 Coal 2 71
67 65
63
5 Diesel 2 56 56
6 Diesel 1
4th
SENSITIVITY
F O R T H E 5 TH A R R A N G E M E N T
Power Plant Type ANALYSIS
Diesel Power Plant Coal Power Plant Solar Power Plant
Land Use 6 6 4 4 1 1
Environmental 1 2 6 6 6 6
Water Consumption
Operational &
1 2 3 3 6 6
Economical Maintenance Cost
6 6 4 4 1 2
Return of Investment
SENSITIVITY
F O R T H E 5 TH A R R A N G E M E N T
3 Coal 1 79
76
3 Coal 2
60 61 61
5 Diesel 2 56
6 Diesel 1
5th
SENSITIVITY
F O R T H E 6 TH A R R A N G E M E N T
Land Use 6 6 4 4 1 1
Environmental 1 2 6 6 6 6
Water Consumption
Operational &
1 2 3 3 6 6
Economical Maintenance Cost
6 6 4 4 1 2
Return of Investment
SENSITIVITY
F O R T H E 6 TH A R R A N G E M E N T
Rank Design Option
ANALYSIS
6TH ARRANGEMENT
1 Solar 1
Diesel 1 Diesel 2 Coal 1 Coal 2 Solar 1 Solar 2
1 Solar 2
3 Diesel 2 75 75
4 Diesel 1 62
59
56 56
5 Coal 1
5 Coal 2
6th
SENSITIVITY
FOR THE ALL OF THE ARRANGEMENT
ANALYSIS All Arrangements
80
70
60
50
40
30
20
10
0
1st 2nd 3rd 4th 5th 6th