GBT Site Survey & Construction


Procedure.
Now, we will discuss about GBT Site Survey &
Construction Procedure
Survey Tools
Survey tools are same for RTT & GBT sites;
 White Paper, Scale (30cm), Pencil, etc,. to draw the rough
layout
 Measuring tape – Steel tape or Cloth tape

 Compass

 Tower Details like


 Height
 Weight
 Base Width
 No of Legs (3 legged tower OR 4 legged tower)

 Shelter Details like External dimensions, No of pedestals, c/c distance of


pedestals, Shelter Weight
 DG Bed Size, DG Weight

 Earth pit size, No. of pits & c/c distances (INDIA)


Now, we will discuss about GBT Site Survey &
Construction Procedure
Survey Tools
Survey tools are same for RTT & GBT sites;
 White Paper, Scale (30cm), Pencil, etc,. to draw the rough
layout
 Measuring tape – Steel tape or Cloth tape

 Compass

 Tower Details like


 Height
 Weight
 Base Width
 No of Legs (3 legged tower OR 4 legged tower)

 Shelter Details like External dimensions, No of pedestals, c/c distance of


pedestals, Shelter Weight
 DG Bed Size, DG Weight

 Earth pit size, No. of pits & c/c distances (INDIA)


SITE SURVEY – GBT

SURVEY PROCEDURE / CHECKS

(INDIA)
SITE SURVEY – GBT

Before going to the survey, we should know the following dimensions:


Tower Base Width & Excavation Width,
Shelter Size
DG Size

With the above details we can find out whether the given size of the site
is suitable or not to arrange the all above equipments.

(INDIA)
SITE SURVEY – GBT
Tower Excavation Width

If foundation drawing is available, excavation width can be know from that drawing

If foundation drawing is NOT available: take excavation width = 2 x Tower Base width

3.2

Excavation Line
40 m 6.4 = 2 x 3.2
Tower

This is only for survey purpose; during execution we have to follow as per
foundation drawing only.
PREPARATION OF LAYOUT AT SITE Kota – 40m, Near Petrol Pump, Main Road, Nellore Dt.

PROCEDURE / CHECKS N
Street road
1. Write Site Name, Tower Ht., Site 20m
Address at the top of the page.
1.5
1.2 1.5
3.3 3.5 1.5
4.0
2. Draw the boundary line with 1.5
3.2 DG EP
dimensions. Make sure that, 0o Should
3. Indicate the NORTH direction. be placed upward2 of your 0.5 x 0.5
x 1.5
4. Mark the adjacent roads, surrounding 40 m page
structures and its distances. Tower

Green Field
5. Mark the site level w.r.t. the road level EP

Green Field
0.5 x 0.5
6. Mark the proposed area of tower, DG & 15m 15m
Shelter 1.5
EP EP
7. Mark all dimensions w.r.t. the
0.5 x 0.5
ELECTROTEK(INDIA)
Shelter 0.5 x 0.5
boundary as shown
2.5x3.2
8. Mark the cable tray rooting 2.5
Security
9. Mark the proposed Earth Pits Room
GATE
10. Mark the Security room and gate 3x3
11. Mark the nearest Elec. Pole / 20m
Transformer to the site Electric Pole
Main Road
12. Write your name, Employee ID No.,
Date & Sign
+ 0.5 m w.r.t. the road level
13. Take the Owner sign and h
Rajes
customer site engineer sign P
P Rajesh
401501
14. This Rough layout should be Owner Customer
03.03.06
sent to Design department to
Kota – 40m, Near Petrol Pump, Main Road, Nellore Dt.
SOIL TEST
Street road N
20m
To design the foundation, we require
soil parameters like SBC, Density, 1.5
1.2 1.5
3.3 3.5 1.5
4.0
1.5
Angle of repose etc., DG
2 x 1.5
Soil sample to be collected within
the proposed area of the tower

Green Field
Soil report should be sent to design

Green Field
department to design the foundation15m 15m
1.5 Soil sample
The following are the different collected areas
types of foundations depends Shelter
upon the soil conditions 2.5x3.2
2.5
Security
Isolated Foundation Room
GATE
Raft Foundation 3x3
20m
Pile Foundation Electric Pole
Main Road
Rock-Anchor Foundation

+ 0.5 m w.r.t. the road level


h
Rajes
P
P Rajesh

ELECTROTEK(INDIA) Owner Customer


401501
03.03.06
CONSTRUCTION PROCEDURE (Raft Foundation)
Site Cleaning
Marking
Excavation
Levelling of excavated pit
Laying of PCC
Bar-bending
Shuttering
Raft Concreting
1st lift column concreting
Tie beam concreting
Template Fixing
Final concreting
Backfilling with proper compaction
INDIA)
Marking At site
Street road N

Carry the CAD layout and foundation


drawing 1.5
1.2 1.5
3.3 3.5 4.0

Mark the distances from the


boundary
Mark the Excavation line with the 6
help of Foundation Drawing

Green Field
Ex.: 6 m is the width of the

Green Field
excavation
Check the diagonal distances
6
6 +6
2 2
= 8.485 m

Main Road

+ 0.5 m w.r.t. the road level


Excavation

Excavation with JCB is recommended

In case of lose soil, proper


shoring should be provided to
prevent soil collapse. Motor for de-
Supports to prevent watering
the soil
In case of seepage, de-watering collapse
should be done

ELECTROTEK(INDIA)

Seepage of water
Excavation

Excavation with JCB is recommended

In case of lose soil, proper


shoring should be provided to
prevent soil collapse.
In case of seepage, de-watering
should be done

Levelling

Proper levelling should be done to


maintain uniform foundation depth

Check the depth of foundation at all


corners as per drawing
PCC (Plain Cement Concrete)

Volumes per Cu M
Grade of Proportion Ballast Sand Cement (cum)
Concrete (cum) (cum)

M10 1:3:6 0.9 0.45 0.15 4.5bags


1:4:8 0.92 0.46 0.115 3.45bags
1:5:10 0.95 0.475 0.095 2.85bags

Generally used mix

PCC – Thickness should be as


per drawing
Bar bending – Shuttering – Concreting

PCC

After laying the PCC, mark the column Check the c/c distances and diagonal
positions to place the column distances
reinforcement.
Bar bending – Shuttering – Concreting
Bottom
reinforcement in
two way direction

Cover Blocks b/w the PCC


and bottom reinf.
Bar bending – Shuttering – Concreting
Column reinf.

Place the column reif. exactly on


marked portion of PCC

Side view
Bar bending – Shuttering – Concreting

Place the column reif. exactly on


marked portion of PCC

Tie the ‘L’ bends of the column


reinf. to the bottom steel

Side view
Bar bending – Shuttering – Concreting
Stirrups at the top of the
column reifn.
Column Stirrups

Stirrups at the bottom of


the column reifn.

Set
First arrange the stirrups at top and
bottom of the column reinf.
Bar bending – Shuttering – Concreting

Arrangement of chairs to support


the top reif.

Chairs
Bar bending – Shuttering – Concreting

Top reinf. of the raft

Stirrups
Bar bending – Shuttering – Concreting

If chairs are not provided properly at regular


intervals, top rainf. may sag as shown
Bar bending – Shuttering – Concreting

Raft Shuttering

Now it is ready for Raft


Concreting
Bar bending – Shuttering – Concreting

Checks before Raft Concreting

Check the size of the raft reinf. and


spacing as per drawing or not
Check the size of the column reinf.
and no. of bars as per drawing or not
Check the c/c dist. and
diagonal dist. of column
reinf. As per drawing or not
Check the raft width and
depth as per drawing or not
Check for shuttering gaps

Mixing of concrete should be machine mix


Grade of concrete should be M20 (as per drawing) as discussed in RTT
While concreting, vibrators should be used for compacting the concrete
Bar bending – Shuttering – Concreting

After Raft Concrete


Picture at site

Aggregate should be immersed in


the concrete as shown to develop
the bond for column concrete
Bar bending – Shuttering – Concreting

Side shuttering can be removed after


24hr. from the concreting

Arrange the column shuttering for


first lift concreting

Curing should be done properly for


the minimum period of 7 days
Bar bending – Shuttering – Concreting

Before first lift concreting:

Again check the c/c distance and


diagonal distance of the column
shuttering

Check the column sizes as per


the drawing or not
Bar bending – Shuttering – Concreting

After Concreting

Shuttering can be removed Aggregate should be immersed in


12hr. after concreting the concrete as shown to develop
the bond for 2nd lift column concrete
Bar bending – Shuttering – Concreting Tie beam
shuttering
Tie beam & 2nd lift column

2nd lift column


shuttering
Bar bending – Shuttering – Concreting

Tie beam reinforcement

Position of T B Bars

Tie Beam C.S.


Bar Bending
Bar bending – Shuttering – Concreting
Tie beam reinf.
Arrange the tie beam reinf.

Check the alignment of the


All corners should be in a columns by pulling the
straight line thread from one end to other
Bar bending – Shuttering – Concreting

Template fixing

Recall the procedure which we have discussed in RTT site


Template & Foundation bolts fixing

Measures before fixing the template on foundation

Fix the template on ground

Check the c/c distance at all sides as per drawing


(In this example c/c distance is 2.1 m )

Check the diagonal distance in both ways


Bar bending – Shuttering – Concreting

Template fixing

Procedure for
water level
checking
Alignment & Fixing of Anchor Bolts
Side View

Isometric View

Top View
Bar bending – Shuttering – Concreting

Template fixing

Procedure for water level


checking
Bar bending – Shuttering – Concreting

Template fixing In the same way check at


all corners as shown
Procedure for water level
checking
Bar bending – Shuttering – Concreting

Template fixing

Top level should be


same for all fn. bolts
Bar bending – Shuttering – Concreting
Now it is ready for final concreting
Checks before Final Concreting

Check all dimensions are per drawing or not.


i.e. Tie beam size, column size and tie beam
distance from the top of the column etc.,
Check the tie beam reinf. Size and no. of bar Tie Beam C.S.
at top and bottom as per drawing or not
Check all foundation bolt thread portion is
covered to protect while concreting
All the threaded portion of the fn. Bolts
should be applied by Greece and covered
with polythene cover
Bar bending – Shuttering – Concreting
Now it is ready for final concreting
After Concreting
Bar bending – Shuttering – Concreting

Site shuttering can be removed after


24hr. (except tie beam bottom
shuttering)

Template can be removed after 12 hr.


from the concreting period

Tie beam bottom shuttering can be


removed after 5 to 7 days

Curing should be done min. of 14 days


Back filling

Back filling should be done with


proper compaction up to the above
ground level to allow settlement in
future
Excavation in Hard Rock

If we found hard rock for small


depth, it has to be removed to reach
the complete foundation depth
Excavation in Hard Rock

If we found hard rock for small


depth, it has to be removed to reach
the complete foundation depth
Anchoring Rod

If we found hard rock nearer to the Chemical Grouting


below ground level, we have to go
for the Anchor Foundation

Level the rock surface

Drilling

Anchorage
Excavation in Hard Rock

If we found hard rock for small


depth, it has to be removed to reach
the complete foundation depth

If we found hard rock nearer to the


below ground level, we have to go
for the Anchor Foundation

Level the rock surface

Drilling

Anchorage

Raft and Columns


Pile Foundation

If the bearing capacity is low in the


given area, piles are required

Boring
Pile Foundation

If the bearing capacity is low in the


given area, piles are required

Boring

Reinforcement & Piling

Pile Cap & Column

Pile Concreting should


be of M25 mix (1:1:2)