Beruflich Dokumente
Kultur Dokumente
Note:
At an age of 5 days, the slab was able to support its self weight plus construction load
(Alvarado YA, et al. An experimental study into the evolution of loads on shores and slabs during construction of multi-
storey buildings using partial striking , 2009)
The post head with shoring jack prevents the early aged concrete to deflect when Plasform /
phenolic, joist, waler and scaffold are remove.
Next Floor Level 3
Casting of level 2 t = 9 days (rebar & formwork column)
t = 8 days t = 10 days (pouring column)
t = 11 days (strip beam sides)
Next Floor Level 3
Clearing of level 2 t = 13 days (install plasform & scaffold)
t = 12 days t = 14 days (install rebar & mep)
t = 15 days (install rebar & mep)
Casting of level 3 Next Floor Level 4
t = 17 days (rebar & formwork column)
t = 16 days t = 18 days (pouring column)
t = 19 days (strip beam sides)
Next Floor Level 4
Clearing of level 3 t = 21 days (install plasform / phenolic)
t = 20 days t = 22 days (install rebar & mep)
t = 23 days (install rebar & mep)
Advantages
• Plasform is expensive for initial cost however cheaper in the long run compared to Phenolic
• Post head with shoring jack is cheaper than Scaffold with u-head, base jack and aluma beams
• Can achieve 8 days cycle per floor
Dis - Advantages
• Need coordination and approval of structural designer
• Workers-Subcon not familiar with the method (Learning Curve Period)
• Proper and strict implementation at site, especially the stripping and transfer of formwork.