Beruflich Dokumente
Kultur Dokumente
MANAGEMENT
GROUP V BSA-1A
INTRODUCTION
• A project may be defined as a series of
related jobs usually directed towards
some major output and requiring a
significant period of time to perform.
• Project management can be defined
as planning, directing, and controlling
resources (people, equipment, material)
to meet the technical, cost, and time
constraints of the project.
INTRODUCTION
Network models are used in the
scheduling of large complex projects
that consist of many interrelated
activities (jobs, operations). All the
activities take specific time and mostly
require some resources for their
completion that often correspond with
specific cost.
INTRODUCTION
Each activity has a start point and a
finish point (points in time) that are
known as events. Since the activities
are performed in a certain sequence,
the final network must respect this
restriction. In following text we will deal
with the networks where arcs
correspond to the activities and nodes
correspond to the events.
Activity A Activity B
Design a Car Make a
Prototype
2 3
1
Activity B
1 2
Make a Prototype
Activity C
Computer
presentation
4
1 2
Activity D
Prototype
Presentation
Activity C 4
Computer
presentation
Fig. 3.17 Three Activities
Activity Activity Description Immediate
Predecessors
A Design a Car None
B Make a Prototype A
C Computer Presentation A
D Prototype Presentation B, C
E Prototype Test B
1. Songs Selection.
2. Mastering.
3. Promotion Material Elaborating.
4. Customers’ Analysis.
5. Promotion Material Production.
6. Make CD Copies.
7. Customers Selection.
8. Data to Printing House.
9. Promotion Material to Printing House.
10. Laser Print.
11. Mailing.
ACTIVITY Activity description Durati Immediate
on predecesso
rs
A Song selection 15 None
B Mastering 8 A
C Promotion material elaborating 6 A
D Customers analysis 7 A
E Promotion material production 4 C,D
F Promotion material to printing 5 E
house
G Customers selection 3 D
H Make CD Copies 12 B, D
I Data to printing house 3 G
J Laser Print 9 F, I
K Mailing 8 H, J
Tab. 3.5 Christmas Compilation Project
SOLUTION
1. Construct the
network
The earliest event time for a node is the earliest time at which
all the preceding activities have been completed. The earliest
event time for completing a project is the earliest time of the
last event.
The latest event time for a node is the latest time at which the
event can occur without delaying the determined completion
time of the project. The latest event time for completing a
project can be set in the planning process or can be considered
as the earliest event time for completing a project
FORWARD PASS
4. = 31 – 3 = 28.
5. = 31 – 5 = 26.
6. = 26 – 4 = 22.
7. = 40 – 12 = 28.
8. Computing the latest event time of the node 3 is not as easy as the previous
computations. depends not only on one successive latest event times, but even
on three of them (those events correspond to the nodes 4, 5 and 7). Therefore the
latest event time must be computed according to the following formula:
Where
… total float of the activity (i, j),
… latest event time of the node j that is the finish node of the activity
(i,j),
… earliest event time of the node i that is the start node of the activity
(i, j),
… duration of the activity (i, j)
* Total floats of critical activities are zeroes.
*Total floats of noncritical activities are positive.
Fig. 3.22 CPM – Backward Pass
CRITICAL ACTIVITIES
NONCRITICAL ACTIVITIES
Total floats give three possibilities of delay of each
noncritical activity:
= pessimistic estimate of duration – the longest time that the activity (i,
j) could take (when everything goes wrong),
= most likely estimate of duration – the time that would occur most
often (if the activity (i, j) were repeated under exactly the same
conditions many times), or the time estimated by experts.
PERT (Program Evaluation Review
Technique)
If we consider the β probabilistic distribution of
activity time (Figure 3.24), the expected completion
time of the activity (i, j) can be then computed as a
weighted average of the three time estimates using the
following formula:
In
addition it is possible to calculate the standard deviation for
each activity:
What
is the probability of project
completion within a desired time ? The
normal distribution N (M, σ) can be
transformed into the standard normal
distribution N (0, 1) using the following
formula
What is the completion time in which
2.
the project will be finished with a
desired probability p?
= M + .
TO ILLUSTRATE PERT, WE MODIFY EXAMPLE 3.6 BY
INTRODUCING THREE DURATION ESTIMATES FOR EACH ACTIVITY
SOLUTION
1.
Construct the network
The considered change, of course, does not affect the
network representing the original project in terms of the
interrelations between all the activities (Figure 3.19).
2. Determine the expected completion time for each
activity
All the expected completion times are computed using
Equation 3.4. For example, the weighted average for the
activity A (1,2) is:
3. Event analysis - This phase is identical with
the computation in Example 3.6. In each step, of
course, we use instead of . Although Figure 3.22
shows the results of the computation, it is necessary
to consider probabilistic feature of the project.
4. Activity analysis-
Using formulas (3.6) and (3.7) we get the expected duration and the
variance (standard deviation) of duration of the project:
M = 15 + 7 + 4 + 5 + 9 + 8 = 48,
= (8/6 + (4/6 + (8/6 + (10/6 + (4/6 = 9,
= 3.
Let us suppose that the management of the company wants to find the
probabilities of the project completion within 45 days (i.e. until December 9)
and within 54 days (i.e. until December 20). First we compute transformed
values of standard normal variables :
,
THANK
YOU
In the table of the standard normal distribution N (0, 1) we look up the distribution values
corresponding to the required probabilities:
= 0.1587 ,
.
Hence, the probability with which the project will have been finished by December 9 is
0.1587. The probability of finishing the project by December 20 is 0.9772.
As mentioned above, the management, of course, might solve the opposite question: to find
the date by which the project will have been finished, e.g. with a reliability of 95%. For this
purpose, we must look up the value corresponding to the probability p = 0.95. The value
found in the table is = 1.645. Introducing this value into Equation 3.9 we get:
= 48 + 1.645(3) = 52.935 .
If we round the result, we can take 53 days as the duration of the project corresponding to the
desired probability. Thus, the project will have been finished (with the reliability of 95%) by
December 19.