Level 1 Level 4
Level 5
Supplier PPAP Expectations
Level 3 – Continued
Data collection requires supplier to –
• Complete a 300 pc. production run.
• Ensure process capability of 1.67 Ppk on
features deemed key or critical on drawing
(N=50 pcs. sampling).
• 100% Layout verification of all dimensions
and drawing notes (ballooned drawing).
• Submit 3 sample parts* tagged to layouts.
• Material certifications for all components.
• Gage R&R (repeatability & reproducibility).
• Other JTEKT requirements per SQAM
* Multi-Cavity tooling requires samples from each cavity.
Supplier PPAP Expectations
Level 4 – Continued
Data collection requires supplier to –
• Complete a 50 pc. production run.
• Ensure process capability as deemed by
the customer. (i.e.: 1.67 Ppk or as noted)
• 100% Layout verification of all dimensions
and drawing notes (ballooned drawing).
• Submit 3 sample parts* tagged to layout.
• Material certifications for all components.
Ref: FSQM-017
Supplier PPAP Expectations
Remember
PPAP Document package is to ship WITH the
tagged PPAP sample parts.
In a well packed box that is labeled with the
JTEKT sample parts label.
GOOD EXAMPLE
Supplier PPAP Expectations
Successful PPAP
submission
relies on YOU!
KNOW THE JTEKT SQAM!!!!
Ship the PPAP samples AND paperwork package TOGETHER!
Label PPAP shipment properly to ensure receipt (use FSQM-013).
Don’t forget IMDS, it’s required for final PPAP approval on all levels.
Use a checklist (FSQM-080) to ensure all requirements are addressed.
Use early shipments (ITO, TTO, OTOP) to prepare for PPAP.
Include plans for Safe Launch to ensure Zero Defects for 90 days.
Thank You!
Pre-Production Part Requirements