FLEXIBLE PAVEMENT

METHOD
START

SUB GRADE PREPARATION - CBR 5%


BY MOTOR GRADER/VIBRO ROLLER

DETAIL B AGGREGAT BASE CLASS B thick 30 cm


WIDENING BY MOTOR GRADER/VIBRO ROLLER

AGGREGAT BASE CLASS A thick 27.5 cm


BY MOTOR GRADER/VIBRO ROLLER

PRIME COAT
BY COMPRESSOR/ASPHALT SPRAYER
ASPHALT CONCRETE SURFACE COURSE t=40 A C t=40
ASPHALT CONCRETE BINDER COURSE t=60 A T B t=40
ASPHALT TREATED BASE thick = 10 cm
ASPHALT TREATED BASE t=100 BY DT/ASPHALT FINISHER/TANDEM ROLLER/PNEUMATIC TYRED ROLLER
AGGREGAT BASE CLASS-A t=275

AGGREGAT BASE CLASS-B t=300


TACK COAT
BY COMPRESSOR/ASPHALT SPRAYER

SUBGRADE CBR 5 % EXISTING PAVEMENT


( OVERLAY ) ASPHALT CONCRETE BINDER thick = 6,0 cm
BY DT/ASPHALT FINISHER/TANDEM ROLLER/PNEUMATIC TYRED ROLLER

TACK COAT
BY COMPRESSOR/ASPHALT SPRAYER

ASPHALT CONCRETE SURFACE thick 4,0 cm


BY DT/ASPHALT FINISHER/TANDEM ROLLER/PNEUMATIC TYRED ROLLER

FINISH
SUB GRADE PREPARATION

1. HAULING SUBGRADE MATERIAL FROM 2. DUMPING SUBGRADE MATERIAL FROM DUMP TRUCK
BORROW AREA GOING TO PROJECT (IF NECESSARY)
LOCATION BY DUMP TRUCK (IF NECESSARY)

4. -SPRAY THE WATER APPLIED TO SURFACE


BY WATER TANK TRUCK
3. SPREADING MATERIAL BY MOTOR GRADER -COMPACTING (THICKNESS AT LEAST 20 CM PER LAYER
BY VIBRO ROLLER, TO KEEP CBR 5%
WATER TANK TRUCK

20CM
AGGREGAT BASE B ~ 20 CM THICKNESS
LAYERS

1. DUMPING THE AGGREGAT BASE A MATERIAL FROM 2. UNLOAD AGGREGATE MATERIAL FROM DUMP TRUCK
BORROW AREA GOING TO PROJECT LOCATION BY
DUMP TRUCK

3. SPREADING BY MOTOR GRADER 4. COMPACTING AGGREGAT BASE A BY VIBRO ROLLER


AGGREGATE BASE A ~ 20 CM THICKNESS
LAYERS

1. HAULING AGGREGATE BASE A MATERIAL FROM BORROW


AREA GOING TO PROJECT LOCATION BY DUMP TRUCK 2. DUMP AGGREGATE MATERIAL BY DUMP TRUCK

3. SPREADING BY MOTOR GRADER 4. COMPACTING AGGREGATE BASE A BY VIBRO ROLLER


1. PRIME COAT

2. ASPHALT TREATED BASE 10 CM 3. SPREADING THE HOT ASPHALTIC MIX TURES BY ASPHALT FINISHER

4. FIRST COMPACTING BY TANDEM ROLLER, MIDDLE COMPACTING BY


PNEUMATIC TYRE ROLLER AND FINAL COMPACTING BY TANDEM ROLLER
1. THE PRIME COAT APPLIED TO SURFACE OF THE BASE COARSE BY ALSO
ASPHALT SPRAYER, BEFORE THAT CLEAN THE SURFACE BY COMPRESSOR
2. ALOCATE THE HOT ASPHALTIC MIXTURES (ASPHALT TREATED BASE BY
DUMP TRUCK) INTO ASPHALT FINISHER
- THE ASPHALT TEMPERATURE IS NOT LESS THAN 120ºC

3 4A 4B 4C
1 2
1

WIDENING ROAD
FLEXIBLE PAVEMENT
3. TACK COAT 3. SPREADING THE HOT ASPHALTIC MIX TURES BY ASPHALT FINISHER

4. FIRST COMPACTING BY TANDEM ROLLER, MIDDLE COMPACTING BY


4. ASPHALT CONCRETE BINDER 6.0 CM PNEUMATIC TYRE ROLLER AND FINAL COMPACTING BY TANDEM ROLLER ALSO

1. THE TACK COAT APPLIED TO SURFACE OF THE ASPHALT TREATED BASE BY


ASPHALT SPRAYER, BEFORE THAT CLEAN THE SURFACE BY COMPRESSOR
2. ALOCATE THE HOT ASPHALTIC MIXTURES (ASPHALT CONCRETE BINDER BY - THE ASPHALT TEMPERATURE IS NOT LESS THAN 120ºC
DUMP TRUCK) INTO ASPHALT FINISHER
3 4A 4B 4C
1 2
1
WIDENING ROAD FLEXIBLE PAVEMENT

5. TACK COAT

6. ASPHALT CONCRETE SURFACE 4.0 CM


3. SPREADING THE HOT ASPHALTIC MIX TURES BY ASPHALT FINISHER
4. FIRST COMPACTING BY TANDEM ROLLER, MIDDLE COMPACTING BY
1. THE TACK COAT APPLIED TO SURFACE OF THE ASPHALT CONCRETE BINDER BY
PNEUMATIC TYRE ROLLER AND FINAL COMPACTING BY TANDEM ROLLER
ASPHALT SPRAYER, BEFORE THAT CLEAN THE SURFACE BY COMPRESSOR ALSO
2. ALOCATE THE HOT ASPHALTIC MIXTURES (ASPHALT CONCRETE SURFACE BY
DUMP TRUCK) INTO ASPHALT FINISHER
- THE ASPHALT TEMPERATURE IS NOT LESS THAN 120ºC

2 3 4A 4B 4C
1
1