Beruflich Dokumente
Kultur Dokumente
Application is function of :
Good weather
Reasonable water currents
Sufficient bearing capacity for riverbed/seabed
Immersed Tunneling
Application is function of :
Good weather,
Reasonable water currents
Sufficient bearing capacity for riverbed/seabed
Tunnel Boring
Excavation is done by tunnel without structural
Tunnel Boring Machines support.
(TBM's).
Used for tunneling under
Involves digging a tube-like bodies of water.
passage through the earth.
Capital intensive with high
Long tunnels construction. mobilization costs.
Diameter:
1 – 14.4 m(Hard Rock TBM)
1 – 19.25 m (Soft Ground TBM)
TBM
Earth
Pressure Slurry Shield Open Face
Shielded Open type
Balance (SS) Type
(EPB)
Hard Rock TBMs
Shielded TBM:
Used with fractured rock, erecting
concrete segments to support
unstable tunnel walls behind the
machine.
Could be single-shielded or double-
shielded
Soft Ground TBMs
Earth Pressure Balance (EPB):
Mixes excavated soil, foaming
agents, water and polymers in
the working chamber behind
cutter head. The muck pressure is
controlled by the pressure wall.
Screw conveyor takes the mud
out of the machine as the
machine moves forward.
Commonly used to
cross tunnel beneath railways
Underground structure & tunnels
Drill & Blast Method
Merits: Drawbacks:
Waste materials generated Safety risks for workers.
would be less. Fumes and gases generated
Disturbance to local traffic & from detonating explosives
environmental impacts are toxic
would be much reduced Noise pollution generated
Blasting significantly reduce from blasting
the duration of vibration Blasting fracture the rock
around the tunnels/
uncontrolled rockslides/falling
debris
Sequential Excavation Method
New Austrian Tunneling Method ( NATM)
Used with dry soil where roads are used for excavation
Sequential Excavation Method
Support element is shotcreting, providing interlocking &
continuous support to the ground
Duration 20 years
Boston Big Dig, Boston, USA
I-90: Ted Williams Tunnel
Temporary rails
TBM conveys
transport
earth soil Lowering TBMs
Concrete TBM excavates
outside for in the Shafts
sections to TBM
disposal
head
Process
TBM places
continues until
pre-cast
both TBMs TBM disposal
concrete slabs
reach meeting
for tunnel lining
point
Case Study 2: Method Evaluation
The channel between the UK and France is well known for unstable
weather conditions and extreme currents. Hence, using the
immersed tunneling technique would have been difficult and of
very high risks.
The box jacking method was unsuitable for usage in case of such a
long tunnel.
The type of TBM’s could have been altered to use only two multi-
mode TBM’s to take into account the possible variation in ground
conditions instead of having five different TBM’s and disposing some
of them.
Conclusion
The most governing factor of choice is the soil conditions