CORPORATION LIMITED
PRESENTATION BEFORE MD ON Dated 31st May’2019
AUTHORITY ENGINEER
EPC CONTRACTOR
1
SL No Details Page No
1 Location Map 3
2 Project Administrative Details 4
3 Project Technical Details 5-6
4 Project Milestones 7
5 Payment Milestones 8
6 Bifurcation Of Project Cost As Per Schedule-H 9
7 Project Status As Per Physical Progress 10
8 List of Manpower 11-12
9 List of Machinery 13
10 Site Status 14-19
11 Other Status of Project 20
12 Deployment Schedule 21
13 Material Stock Details 22
14 Critical Issues 23
15 Details of Safety Signboards installed at Site 24
16 Site Photographs 25-30
Rainwater Harvesting
37.19% 41.74%
Major Bridge (length> 60m) works and
19.65%
ROB/RUB/elelevated sections/Flyover
inclduing vaiducts,if any
9
R-BLOCK - DIGHA 6-LANE
Physical Progress
10.10%
89.900%
2 Loader 1
3 Grader 2
5 Dumper 45
6 Water Tanker 6
7 Transit Mixer 8
8 Soil Compactor 4
9 Trailer 2
10 Dozer 2
Commissioning in
11 Concrete Batching Plant 1
progress
12 Weigh Bridge 1
R-BLOCK
13 - REDIGHA
PANEL CASTING 6-LANE
TOTAL 2
YARD 617 COMPLETED 14
R-BLOCK - DIGHA 6-LANE 15
SL. CHAINAGE
SIDE LENGTH REMARKS
No. FROM TO
16 DRAIN
1 0+800 0+940 LHS 140 PCC of Storm water Drain
2 0+800 0+940 LHS 140 Raft Of Storm water Drain
3 0+800 0+820 LHS 20 Wall Of Storm water Drain
4 1+030 1+130 LHS 100 PCC of Storm water Drain
5 1+030 1+130 LHS 100 Raft Of Storm water Drain
6 1+030 1+050 LHS 20 Wall Of Storm water Drain
7 4+390 4+460 LHS 70 PCC Of Utility Duct Done
8 4+650 4+920 LHS 270 PCC of Storm water Drain
TOTAL 860
1 3+000 3+180 RHS 180 PCC of Storm water Drain
2 3+000 3+080 RHS 80 Raft of Storm water Drain
3 3+000 3+040 RHS 40 Wall of Storm water Drain
4 4+350 4+920 RHS 570 PCC Of Utility Duct Done
5 4+350 4+920 RHS 570 Raft Of Utility Duct Done
6 4+350 4+530 RHS 180 Wall Of Utility Duct Done
7 4+610 4+710 RHS 100 Wall Of Utility Duct Done
8 4+750 4+920 RHS 170 PCC of Storm water Drain
9 4+750 4+800 RHS 50 Raft Of Storm water Drain
TOTAL 1940
2 4+680 4+800 LHS 120.00 Emb Top Completed 2 0+780 0+800 LSR 20.00 Emb in Progress
3 4+980 5+160 LHS 180.00 Emb Top Completed 3 0+940 0+960 LSR 20.00 Emb in Progress
4 4+350 4+800 LHS 450.00 Emb Top Completed 4 2+250 2+500 LSR 250.00 Emb in Progress
5 4+800 4+950 LHS 150.00 Emb Top Completed 5 2+540 2+900 LSR 360.00 Emb in Progress
1 4+350 4+950 RSR 600.00 Emb Top Completed 7 4+980 5+160 LSR 180.00 Emb in Progress
Total 1170
1 0+700 0+940 LSR 240.00 SG Top Completed 1 0+700 0+940 LSR 240.00 GSB Top Completed
2 4+680 4+800 LSR 120.00 SG Top Completed 2 4+350 4+800 LSR 450.00 GSB Top Completed
4 4+980 5+160 LSR 180.00 SG Top Completed 1 2+600 2+870 RSR 270.00 GSB Top Completed
5 4+350 4+800 LSR 450.00 SG Top Completed 2 4+350 4+950 RSR 600.00 GSB Top Completed
Total 870
20
R-BLOCK - DIGHA 6-LANE
Tree Cutting : 360 Nos. out of 585 Nos.
Encroachment Removal
From R-Block to Shivpuri (km 0 to 2.5, In Progress)
From Digha towards Rajiv Nagar (km 6.3 to 5.5 In Progress)
3 nos of temples to be removed.
21
R-BLOCK - DIGHA 6-LANE
Day Schedule
04 No Excavator at site
02 No Excavator at Ghat for uplifting of sand.
01 No Excavator at Dumping Yard .
01 No Dozer at site for grading of Sand.
01 No Dozer at Dumping Yard
04 No JCB at site.
02 No JCB at Dumping Yard.
02 No Grader at site for grading.
02 No Soil Compactor for compaction of Bed.
03 No Water Tanker for watering of Bed.
35 No Tipper for loading and unloading of Debris and Sand.
Night Schedule
04 No Excavator at site
02 No Excavator at Ghat for uplifting of sand.
01 No Excavator at Dumping Yard .
01 No Dozer at Dumping Yard
01 No JCB at Site.
02 No JCB at Dumping Yard.
01 No Grader at site for grading of Bed.
02 No Soil Compactor at site for compaction of Bed.
22
R-BLOCK - DIGHA 6-LANE
MATERIALS STOCK DETAILS
SL NO ITEMS UNIT QUANTITY IN STOCK REMARKS
4 GSB MT 26550.1
5 DUST MT 1581.98
6 SAND MT 35087.172
7 CEMENT MT 249
8 BITUMEN MT Nill
9 STEEL MT 110.598