Drilling Update 25 May 2019


Summary Drilling
South Block 1

Progress Drilling 69% in area SouthBlock 1


block 2-2E, Finish 32 holes/ plan 10 holes,
actual depth 2320.64m/plan 1054.36m

Progress drilling may 2019, in line PR2E000,


CD01020 & CD01060, 12 holes, 849.40 meters

Update 25 May 2019


Section
LineCD01060
Avarge Dip 25-30 degree, in line CD01060 seam
target seam 7000-seam 8900
Actual seam 7000-seam8700
Recommended for spase 200 for seam 7000
avarage more than 1.00-1.5 meters

CD0106042C

LineCD01060

Update 25 May 2019


Section
LineCD01020
Recommended for spase 200 for seam 7000
avarage more than 1.00-1.5 meters

LineCD01020

Update 25 May 2019


Section
Line PR2E000
Avarge Dip 35 degree, in line PR2E000 seam target
seam 7000-seam 8900
Actual seam 7000-seam8700
Recommended for continue spase 200 for seam
5600 avarage more than 1.00-1.5 meters (actual
core recovery just 65%
)and seam 6800 avarage more than 1.00-1.5
meters

S6800

PR2E00037C

S5600
Line PR2E000

PR2E00035C

Update 25 May 2019


Summary Drilling
Underground Drilling
At 2019 plan 10 holes (2 stage)
Stage I ( january- march) = 5 holes (3 time
redrill) total depth 2269.05m
Stage II cut off 25 may = 1 holes total depth
221.70metrs, on progress 2 hole again, seam
target seam quality seam 3000, geotech
sample and hidrology )

Progress Drilling 69% in area SouthBlock 1,


Finish 6 holes/ plan 4 holes, actual depth
2490.75m/plan 1129.25m

Estimasi finish end off july because afyer finish


drilling we want get data hydrology by
pumping test)

Update 25 May 2019


Cortech 500 (02) hole DH1902
Intruction Drilling

Intruction
Hole DH1902 disposal estimate 0-22 meters make casing more than 22
meter (until safety drilling )
Start corring 252-307 meters
Geotech sample 30 meter above seam 3000 and 20 meters under s3000

Actual S3800
Hole DH1902 disposal estimate 0-22
make casing until original lithology
Start corring 160- 221meters
Get Coal Seam 3800 (176.80-178.00)
and seam 3000 (206.70 – 211.59)

S3000

S3800
S3000

S3000

Update 25 May 2019


Cortech 500 (02) hole DH1902 Activity Drilling

Coal S3000 Bottom Coal


Top Coal S3000 S3000

Drilling Activity
Descripsi and packing sample
Sample corring
for geotech

Drilling progress
Casing in hole

Coal S38000

Update 25 May 2019


General Issue

1. EID Holiday for driling 29 May – 1 June 2019


2. Induksi crew renovate container 27 may 2019, and start continue renovate
3. Recommendation for continue drilling sapce 200 for seam target seam 7000, seam 6800 and seam 5600 (need
sugestion)
4. After lebaran continue drilling in SB1 block 2e-block 2 and support underground drilling
5. We always late for resurvey because we must waiting progress from geologi TCM first

Update 25 May2019