Beruflich Dokumente
Kultur Dokumente
1 Port Qasim Coal Project 1,320 Port Qasim, Karachi, Sindh CPEC 30th June 2018
2 Sahiwal Coal Power Project 1,320 Qadarabad, Sahiwal CPEC 25th Dec 2017
3 HUBCO Coal based Power Project 1,320 Hub, Balochistan CPEC Mar-2020
5 Lucky Coal Power Project 660 Port Qasim, Karachi, Sindh Non-CPEC Dec-2020
6 Siddiqsons Coal Power Project 350 Port Qasim, Karachi, Sindh Non-CPEC Oct-2020
7 Engro Thar Coal Power Project 660 Thar Block - II, Sindh CPEC 3rd June 2019
8 Shanghai Electric Coal Power Project 1,320 Thar Block - I, Sindh CPEC Aug-2020
9 HUB Power Project Thar Block-II 330 Thar Block - II, Sindh CPEC Jan-2020
10 Thal NOVA Power Project, Thar Block-II 330 Thar Block - II, Sindh CPEC Jan-2020
11 Oracle Coal Power Project 1320 Thar Block-VI, Sindh CPEC Mar-2021
1. Land Acquisition 2 No. Grounding Electrodes 110 Acres each at Lahore and Matiari
3 No. Repeater Stations 1 Acre each
Central Warehouse Approx. 1 Acre
2. RoW for T/L 886 km 413.8 km cleared
3. Land Route for 5 km each approx. Route finalized.
Drainages
4. NOCs 13 8 obtained
5. Design Review OE: M/s. Hatch, M/s. Barqaab C/S and T/L Preliminary Designs approved;
Foundation Design under process
6. FATs/Testing NTDC and OE 3 Tower Types done, 3 Remaining
7. Stability Studies Base Cases for Studies 90% done
A Typical Converter Station Layout
Lahore to Bahawalnagar Line Route showing Cities
19
Bahawalnagar to Khanpur
20
Khanpur to Sukkur
21
Sukkur to Matiari
Khanpur to Sukkur
22
Security Control System (SCS)
For the outage of both Poles (i.e., HVDC link is down either due to converter station or due to
transmission lines).
The whole power has to flow through HVAC network which is stability constrained to a limit of 3,200
MW.
As of March 2021 the line flows are expected to be 4,227 MW from South towards Mid-Country.
In case of both poles out age(either due to converter or due to transmission lines), 4,000 MW will
transfer on the HVAC network.
Whereas its stable transfer limit is 3,200 MW, Hence 4,227 – 3,200 = 1,027 MW need to be cross-
tripped from South side, simultaneously with Bipole outage.
continued
Such Controllers shall be installed in the converter & power stations by PMLTC.
PSP NTDC is in the process of study, to enhance the HVAC network capacity by using FACTS devices
(like Series Compensation).
HVDC Cross Border Projects Conceived
Cross Border Proposed HVDC Links
The import of 1,000 MW from Zahidan, Iran to Quetta
◦ Environmental Aspects