Beruflich Dokumente
Kultur Dokumente
A Done
Build B
B Done
Build C
C Done
On time!
Build D
Ship
Project Management
How is it different?
Limited time frame
Narrow focus, specific objectives
Less bureaucratic
Why is it used?
Specialneeds
Pressures for new or improves products or services
Project Management
What are the Key Metrics
Time
Cost
Performance objectives
Organizational alternatives
Manage within functional unit
Assign acoordinator
Use a matrix organization with a project leader
Project Management
What are the tools?
Work breakdown structure
Network diagram
Gantt charts
Risk management
Planning and Scheduling
Gantt Chart MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Locate new
facilities
Interview staff
Move in/startup
Key Decisions
Deciding which projects to implement
Selecting a project manager
Selecting a project team
Planning and designing the project
Managing and controlling project resources
Deciding if and when a project should be
terminated
Work Breakdown Structure
Project X
Level 1
Level 2
Level 3
Level 4
PERT and CPM
PERT: Program Evaluation and
Review Technique
CPM: Critical Path Method
S 5 7
Hire and
Interview
train
3 4
Network Conventions
a
b
c a
c
b
a c
a c
b Dummy
activity
b d
Time Estimates
Deterministic
Time estimates that are fairly certain
Probabilistic
Estimates of times that allow for variation
Example 1
6 weeks
Deterministic 4
time estimates
3 weeks
8 weeks 2
11 weeks Move
in
1 5 6
1 week
4 weeks
9 weeks
3
Example 1 Solution
Critical Path
Used to determine
Expected project duration
Slack time
Critical path
Probabilistic Time Estimates
Optimistic time
Time required under optimal conditions
Pessimistic time
Time required under worst conditions
Most likely time
Most probable length of time that will be required
Probabilistic Estimates
to tm te tp
te = t o + 4t m +t p
6
te = expected time
to = optimistic time
tm = most likely time
tp = pessimistic time
Variance
2 (t
= p o– t ) 2
36
2 = variance
to = optimistic time
tp = pessimistic time
Example 5
2-4-6
b
4-6-8
h
Path Probabilities
d-e-f
Weeks
16.0
1.00
g-h-i
13.5 Weeks
Advantages of PERT
Forces managers to organize
Provides graphic display of activities
Identifies
4
Critical activities
2
Slack activities
1 5 6
3
Limitations of PERT
Important activities may be omitted
Precedence relationships may not be
correct 4
a fudge factor
1 5 6
May focus solely
on critical path 142 weeks
3
Technology for Managing Projects
Computer aided design (CAD)
Groupware (Lotus Notes)
Project management software
CA Super Project
Harvard Total Manager
MS Project
Time Line
Project Risk Management
Risk: occurrence of events that have undesirable
consequences
Delays
Increased costs