Summary Report of this week activity

Sano Project 42 MW
2019/07/18
JuwiShizen Energy
Filling work at North
area, using 2 unit
bulldozer capacity 20T
and backhoe 0.45m3 and
some crawler trucks.
Filling work at North
area and slope shaping
work, inclination slope
around 27º.
Deforestation and
rooting work at
central area, this area
will be filling area.
Box culvert installation at the
approach road(North area
entrance).
Installing reinforce bar for drainage tower at
the retention pond No.6 (minami koku)
Slope shaping for
vegetation sheet at the
entrance of approach
road Naka koku