Development Permission shall be not be required for alterations and minor works except
those buildings in precincts and natural features listed by the Heritage Conservation
Committee.
The following alterations shall have to conform to the Development Control Regulations.
1. Repairing doors and windows in the same location including change in size.
4. Rebuilding an existing wall, repairing the
wall including plastering the wall.
7. Changing or repairing flooring at any floor 10. Constructing a new toilet block within the
or height. This only includes wood, stone and Building.
metal flooring and does not included RCC 11. Internal partitions within the Building.
flooring .
12. Constructing a parapet, railing,
8. Reducing or increasing the height of the compound wall or wire fencing .
plinth and constructing new steps within the
13. Construction of a water tank or wash area
Building‐unit.
in open area of the Building‐unit or terrace for
residential use only.
14. Construction of Water Closets as required by
the Health Department.
15. Constructing and repairing weather
protection.
16. Installing metal grill in verandah or
courtyard.
Notes :
1. It shall be necessary to ascertain that the work carried out is as per the regulations
and if found in violation, legal action may be taken.
2. Prior to deciding not to take any action on the above mentioned works, a review will
be required if this construction does not pose any danger or due to this construction
there is no danger to other parts.
3. If the construction is falling under Road line, then an agreement or deposit
according to Corporation Act, clause 201 (5).
SCHEDULE-2 : MANDATORY DESIGN AND SPECIFICATIONS
A. SCRUTINY FEES
1. For buildings(for categories D1 to D6 only)
a) For Residential Buildings with
Height upto 25mts – Rs.10 per sq.mt of built area of all floors
minimum scrutiny fees Rs. 1000
b) For Residential Buildings
Height more than 25mts and Non Residential building – Rs. 15 per sq.mt of built area of all
floors
minimum scrutiny fees Rs.1000
• For Buildings (For categoryD7(A), D7(B), and D8)
a) For Residential Buildings
Rs.5 per sq.mt of built area of all floors
minimum scrutiny fees Rs.500
b) For Residential Buildings
Height more than 25mts and Non Residential Building – Rs.10 per sq.mt of built area of all
floors
minimum scrutiny fees Rs. 750.
1. Amenities fee for different categories of development area per sq.mt of total built up
area for proposed development.
1 D1, D2 300
2 D4 150
3 D3, D5, D6, D7(A) 100
4 D7(B), D8 50
5 D9 50
2. 50% of above fees shall be levied on total built up area for proposed development of
educational institutions, charitable trusts, government and semi government building.
SCHEDULE 5: FORMAT FOR SUBMISSION OF DOCUMENTS, DRAWINGS AND SPECIFICATIONS
shall be free of
any scratches or
corrections –
small, initiated
corrections shall
be permitted
3. Colours and Notations to be followed for all Drawings and Documents
N Item Site Plan Building
o. Plan
Financial penalty –
Financial penalty – TEN TIMES THE REVISED
FIFTEEN TIMES THE SCRUTINY DEVELOPMENT PERMISSION
FEES FEES
Financial penalty –
Financial penalty –
FIVE TIMES THE DEVELOPMENT
TWICE TIMES THE
PERMISSION FEES
DEVELOPMENT PERMISSION
FEES
SCHEDULE 7: Minimum Qualification, Experience and Document Requirements for
Being Considered for Registering with the Competent Authority as Persons on
Record
(The following are the minimum qualifications and experience requirements for all persons to be
considered for registering with the Competent Authority as Persons on Record.)
o The Architect must hold a valid registration with the Council of Architecture, India, issued as per the
provisions of the Architects Act, 1972 or Bachelors Degree in Architecture / Diploma in Architecture
Equivalent to B.Arch; and
o The Architect must have a minimum of two years of experience in a practice of architecture.
o Preparation & planning of all types of lay‐outs & submission drawings and to submit certificate of
supervision, progress report & certificate of completion for all types of buildings in accordance to the
provisions of building regulations.
o Supervision & execution of construction work as per specifications & drawings prepared by
authorised registered structural designer & engineer.
Engineer on Record (EOR)
o A Masters Degree in Civil Engineering, a Bachelors Degree in Civil Engineering or Building construction or
its equivalent qualification recognized by the All India Board of Technical Education, or, a Diploma in Civil
Engineering or Diploma in Building Construction recognized by State Board of Technical Examination of
any State of India or Associate Membership (Civil Engineering ) of the Institute of Engineers, India (AMIE
o The Engineer having Bachelors degree or its equivalent qualification must have minimum of two
year s of experience and Diploma holder/or AMIE must have minimum of five years of experience
in professional work.
o Preparation & planning of all types of lay‐outs except special structures / Special Buildings and to submit
certificate of supervision & completion for all types of buildings. Provided person having qualification of a
Diploma in Civil Engineering shall be permitted for low rise buildings only
o Supervision & execution of construction work as per specifications & drawings prepared by
authorised registered structural designer & engineer.
o He/she can prepare & submit structural details & calculations for buildings of load bearing
structures.
Structural Engineer on Record (SEOR)
*Note: Minimum years of experience of preparing structural designs, detailed drawings and specifications. (after attaining the
degree/ Diploma) , Person holding Higher grade license can also work for Lower Grade Work
Clerk of Works on Record (COWOR)
4.3.2 Fees
Development Permission Revalidation Fees for revalidating a Development Permission
shall be determined by the competent authority.
For revalidating a lapsed Development Permission, penalty charges shall be applicable.
1000/-
• For Mining, Quarrying and Brick kiln operation.
1. Form No. 9
2. Receipt of payment of all relevant I am the Owner/Developer of the plot and wish to undertake construction of the proposed
building on the Building‐unit.
scrutiny fees or any other charges
The Development Permission has been granted to me by the Competent Authority vide Letter
No. dated . The Development Permission that was issued on
(date) by the Competent Authority shall lapse on .
(date) due to
I shall be responsible for ensuring that the building complies with the General Development
Control Regulations. I request that the Revalidated Development Permission be granted to
me.
Failure to comply with the above requirements may result in revocation of the Development
Permission.