Beruflich Dokumente
Kultur Dokumente
Role of PMA
DISCOM wise IPDS Financial Progress & Physical Progress: System
Strengthening
Status of other IPDS / RAPDRP projects
Issues
• Projects of Rs. 30,085 Cr approved (ST&D, IT, ERP and Smart Metering)
• Total GOI Grant released Rs 6,658 Cr (28%)
• Rs 27,625 Cr for System Strengthening (ST&D) in 546 circles (3630 towns) :
Physical Progress 46%
% Physical
Survey
Milestone Name Unit Sanction Award WIP Completion progress
Complete
achieved
ERP NA
Smart Metering NA
RT-Das NA
GIS Substation NA
Status of Arunachal-PD
Reconciled BOQ - Pending
Pending Issues
Financial progress
Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt first Dt last Grant %
Amount (Rs Cr) 691 588 Sep-16 645 Jul-17 634 92 Sep-17 June-18 151 26
Circles 19 19 15 79
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 10 13 6 6 0 14%
Substations Capacity enhancement &
No. 64 36 34 5 0 18%
Additional Transformers
Over-head HT (33 & 11KV) Km 659 616 602 167 9 22%
Lines LT (440 V) Km 538 211 209 57 11 23%
Cables Aerial Bunch /UG Km 1,450 2,322 2,311 906 72 28%
Distribution Transformers No. 726 596 596 167 33 27%
Smart/ Prepaid No. 3,760 2,553 1,068 0 0 4%
Meters
Consumer-System No. 55,030 68,179 66,782 0 0 10%
Solar Panels KWp 488 0 0 0 0
ERP NA
Smart Metering NA
Pending Issues
Financial progress
Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 1102 663 Sep-16 942 Jul-16 942 85 Jan-17 Sep-18 171 26
Circles 7 7 5 71
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 35 35 32 26 6 53%
Substations Capacity enhancement &
No. 32 33 33 18 10 51%
Additional Transformers
Over-head HT (33 & 11KV) Km 1,323 1,366 968 570 353 38%
Lines LT (440 V) Km 915 914 665 281 222 32%
Cables Aerial Bunch / UG Km 4,120 2,722 2,424 1,565 1,457 58%
Distribution Transformers No. 2,529 2,999 2,718 1,591 1,260 52%
Smart/ Prepaid No. 2,918 0 0 0 0
Meters
Consumer-System No. 115,016 127,540 116,016 116,016 116,016 91%
Solar Panels KWp 936 936 398 280 279 31%
Pending Issues
Financial progress
Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 1118 673 Sep-16 1062 Jul-16 1062 95 Jan-17 Mar-17 185 27
Circles 9 9 9 100
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 27 27 22 20 6 37%
Substations Capacity enhancement &
No. 76 77 77 50 38 62%
Additional Transformers
Over-head HT (33 & 11KV) Km 1,365 1,260 899 577 115 33%
Lines LT (440 V) Km 1,018 1,019 535 189 18 15%
Cables Aerial Bunch / UG Km 3,700 3,375 2,820 1,718 862 44%
Distribution Transformers No. 1,334 1,393 1,393 778 531 53%
Smart/ Prepaid No. 2,370 1,048,324 167 0 0 0%
Meters
Consumer-System No. 125,410 136,146 93,492 93,492 93,492 69%
Solar Panels KWp 669 733 733 592 483 77%
Pending Issues
Pending Issues
• Progress of IPDS ~ 3%
DHBVNL
Financial progress
Departmental + Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 311 187 Sep-16 289 Sep-16 289 93 Mar-17 June-18 53 28
Circles 9 9 5 56
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 4 4 4 4 1 44%
Sub stations Capacity enhancement &
No. 5 5 5 5 5 100%
Additional Transformers
Over-head HT (33 & 11KV) Km 454 454 454 85 42 25%
Lines LT (440 V) Km
Cables Aerial Bunch / UG Km 932 932 932 154 37 21%
Distribution Transformers No. 694 694 694 330 267 50%
Smart/ Prepaid No.
Meters
Consumer-System No. 37,246 37,246 37,246 2,000 0 13%
Solar Panels KWp 103 103 103 0 0 10%
Overall Physical progress – 21 %
Circle wise Completion Plan
Discom Total Completed Nov- 18 Dec-18 Jan-19 Feb-19 Mar-19
DHBVNL 9 1 1 3 22
Expected Completion
Circle Name In Progress (%) Bottleneck in completion
Month
HISAR/HISAR/DHBV HT, ABC, Consumer Meter,
33.28 Mar-19
N Solar Panel
JIND/HISAR/DHBVN 38.19 Mar-19 S/S, HT Lines, Solar Panel
NARNAUL/Delhi/DH
67.74 Feb-19 ABC, Solar Panel
BVN
Palwal/Delhi/DHBVN 34.91 Mar-19 HT, Consumer Meter
SIRSA/HISAR/DHBVN 64.37 Jan-19 Consumer Meter, ABC
18 / 18 Towns Completed.
Part-A (IT) TPIEA Verification under progress
Closure Report Pending
Part-A (SCADA) NA
Part-B NA
ERP NA
Smart Metering NA
GIS Substation NA
Status of DHBVNL
Reconciled BOQ : Submitted
Pending Issues
• Progress of IPDS ~ 21 %
• Award of IT Phase- II
• Verification of R-APDRP Part A (IT)
UHBVNL
Financial progress
Departmental + Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 79 48 Sep-16 73 Mar-17 73 92 Sep-17 Apr-18 13 27
Circles 9 9 8 89
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No.
Sub stations Capacity enhancement &
No.
Additional Transformers
Over-head HT (33 & 11KV) Km 37 37 37 32 0 59%
Lines LT (440 V) Km 1 1 1 1 0 60%
Cables Aerial Bunch / UG Km 426 426 426 168 5 32%
Distribution Transformers No. 333 333 333 123 0 32%
Smart/ Prepaid No.
Meters
Consumer-System No. 3,700 3,700 3,700 0 0 10%
Solar Panels KWp 320 320 320 315 50 82%
Overall Physical progress – 29 %
Circle wise Completion Plan
Discom Total Completed Nov- 18 Dec-18 Jan-19 Feb-19 Mar-19
UHBVNL 9 2 2 1 26
Expected Completion
Circle Name In Progress (%) Bottleneck in completion
Month
AMBALA 38.32 Feb-19 DT, AB Cable, LT Lines
JHAJJAR 74.06 Jan-19 ABC
KAITHAL 51.55 Jan-19 ABC, DT
ABC, UGC, DT, Consumer
KURUKSHETRA 26.01 Mar-19
Meter
YAMUNA NAGAR 32.78 Feb-19 ABC, DT
18 / 18 Towns Completed.
Part-A (IT) TPIEA Verification under progress
Closure Report Pending
Part-A (SCADA) NA
Part-B NA
ERP NA
Smart Metering NA
Pending Issues
• Progress of IPDS ~ 29 %
• Verification of R-APDRP Part A (IT)
HPSEBL
Financial progress Departmental+ Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 111 94 Sep-16 111 Oct-16 111 100 Sep-17 Dec-17 28 30
Circles 12 12 12 100
Physical progress
%
Awarded Survey
Qty Work in Physical
Milestone Name Unit Sanction Qty Complet Completion
Dept. Progress progress
Turnkey ed
achieved
New Substation No. 2 - 2 1 1 0 13%
Sub stations Capacity enhancement &
Additional Transformers
Over-head HT (33 & 11KV) Km 105 9 96 70 70 0 22%
Lines 48 48 1
LT (440 V) Km 104 10 94 15%
Pending Issues
• Progress of IPDS ~ 11%
• Award of IT Phase- II
• R-APDRP Part-A IT & Part B Closure
JKPDD
Financial progress
Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 447 380 Sep-16 434 Oct-17 433 97 Feb-18 Oct-18 38 10
Circles 12 12 12 100
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 21 16 9 3 0 8%
Sub
Capacity enhancement &
stations No. 66 41 7 1 0 2%
Additional Transformers
Over-head HT (33 & 11KV) Km 723 474 91 14 0 3%
Lines LT (440 V) Km 500 256 1 0 0 0%
Cables Aerial Bunch / UG Km 2,581 1,694 190 28 0 2%
Distribution Transformers No. 1,689 485 76 0 0 2%
Smart/ Prepaid No. 460 0 0 0 0
Meters
Consumer-System No. 133,451 5,630 155 0 0 0%
Solar Panels KWp 565 155 0 0 0 0%
ERP NA
Smart Metering NA
Pending Issues
• Award of IT Phase- II and ERP
• Award of SCADA and completion of Part B in all 30 towns
• Closure of Part-A IT
JBVNL
Financial progress
Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 755 455 Sep-16 755 Sep-16 755 100 Jun-17 Sep-17 133 29
Circles 15 15 15 100
Physical progress
%
Revised Awarded Survey Work in Physical
Milestone Name Unit Completion
Sanction Quantity Completed Progress progress
achieved
New Substation No. 26 26 26 26 0 52%
Sub stations Capacity enhancement &
No. 50 50 50 35 1 46%
Additional Transformers
Over-head HT (33 & 11KV) Km 711 711 711 256 12 31%
Lines LT (440 V) Km
Cables Aerial Bunch / UG Km 2,652 2,652 2,652 1,589 119 45%
Distribution Transformers No. 1,665 1,665 1,665 976 329 48%
Smart/ Prepaid No.
Meters
Consumer-System No. 82,333 82,333 82,333 38,416 21,846 44%
Solar Panels KWp 324 324 324 0 0 10%
Smart Metering NA
RT-Das NA
GIS Substation NA
Status of JBVNL
Reconciled BOQ : Submitted
Pending Issues
ERP NA
Smart Metering NA
GIS Substation NA
Status of MSPDCL
Reconciled BOQ : Submitted
Pending Issues
• Installation of Billboards
• Award of IT Phase- II
• R-APDRP Part B Closure
• Part-A IT Closure
MePDCL
Financial progress
Partial Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 62 53 Sep-16 61 Mar-17 61 99 Dec-17 Mar-18 15 28
Circles 6 6 6 100
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 6 6 5 5 0 21%
Sub stations Capacity enhancement &
No. 2 2 2 1 0 18%
Additional Transformers
Over-head HT (33 & 11KV) Km 92 92 92 4 0 12%
Lines LT (440 V) Km 60 60 60 0 0 10%
Cables Aerial Bunch / UG Km
Distribution Transformers No. 53 53 53 0 0 10%
Smart/ Prepaid No. 6,400 6,400 6,400 0 0 10%
Meters
Consumer-System No. 10 10 10 0 0 10%
Solar Panels KWp 210 210 210 0 0 10%
Smart Metering NA
Pending Issues
• Progress of IPDS ~ 12 %
• Operationalisation of Customer Care Centre for all Go-Live towns
• Completion of Part B towns
• Part-A IT Closure
Mizoram-PD
Financial progress
Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 90 76 Sep-16 73 Jan-17 47 52 Mar-17 Mar-17 15 20
Circles 1 1 0 0
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 2 2 2 1 0 35%
Sub stations Capacity enhancement &
No. 1 1 0 0 0 0%
Additional Transformers
Over-head HT (33 & 11KV) Km 139 132 132 62 0 41%
Lines LT (440 V) Km 118 130 130 66 66 56%
Cables Aerial Bunch / UG Km 115 90 90 26 19 33%
Distribution Transformers No. 50 51 51 10 3 25%
Smart/ Prepaid No.
Meters
Consumer-System No. 9,082 3,924 0 0 0 0%
Solar Panels KWp 21 21 21 9 6 43%
ERP NA
Smart Metering NA
GIS Substation NA
Status of Mizoram-PD
Reconciled BOQ : Pending
Pending Issues
• Progress of IPDS ~ 34 %
• Award of IT Phase - II
• Verification of R-APDRP Part A (IT)
• R-APDRP Part-B Completion
Nagaland-PD
Financial progress
Partial Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 119 102 Sep-16 44 Mar-17 44 37 Aug-17 Aug-17 17 17
Circles 2 0 0 0
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 1 0 0 0 0
Sub stations Capacity enhancement &
No. 1 0 0 0 0
Additional Transformers
Over-head HT (33 & 11KV) Km 116 32 32 1 0 12%
Lines LT (440 V) Km 79 18 12 10 3 41%
Cables Aerial Bunch / UG Km
Distribution Transformers No. 98 38 25 10 7 27%
Smart/ Prepaid No. 19,900 0 0 0 0
Meters
Consumer-System No. 44,865 59,689 43,169 37,034 8,614 44%
Solar Panels KWp 20 0 0 0 0
IT Phase II
Approved cost: 2.29 , NIT not floated
Smart Metering NA
RT-Das NA
GIS Substation NA
Status of Nagaland-PD
Reconciled BOQ : Pending
Pending Issues
• Award of IT Phase- II & ERP
• Verification of IT project
OPTCL
Smart Metering NA
GIS Substation NA
Status of OPTCL
Reconciled BOQ : Pending
Pending Issues
• Award of IT Phase- II
• Completion of IT /SCADA project
• R-APDRP Part B Closure for all 12 towns
PSPCL
Financial progress
Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 332 200 Sep-16 332 May-17 332 100 Oct-17 Nov-17 58 29
Circles 20 20 20 100
Physical progress
%
Revised Awarded Survey Work in Physical
Milestone Name Unit Completion
Sanction Quantity Completed Progress progress
achieved
New Substation No.
Sub stations Capacity enhancement &
No.
Additional Transformers
Over-head HT (33 & 11KV) Km 505 505 505 202 46 36%
Lines LT (440 V) Km 51 51 51 5 2 16%
Cables Aerial Bunch / UG Km 413 413 413 46 0 16%
Distribution Transformers No. 1,616 1,616 1,616 780 288 44%
Smart/ Prepaid No. 547 547 547 0 0 10%
Meters
Consumer-System No. 21,190 21,190 21,190 0 0 10%
Solar Panels KWp 380 380 380 0 0 10%
Overall Physical progress – 28 %
GIS Substation NA
Status of PSPCL
Reconciled BOQ : Submitted
Pending Issues
Financial progress
Turnkey + Departmental
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 425 256 Sep-16 425 Aug-16 393 92 Apr-17 Feb-18 70 27
Circles 12 12 11 92
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 58 59 59 47 20 60%
Sub stations Capacity enhancement &
No. 67 66 66 47 46 74%
Additional Transformers
Over-head HT (33 & 11KV) Km 872 648 648 203 111 33%
Lines LT (440 V) Km 581 75 75 9 8 20%
Cables Aerial Bunch /UG Km 904 311 311 191 112 55%
Distribution Transformers No. 1,135 1,070 1,070 255 161 28%
Smart/ Prepaid No. 2,091 300 300 0 0 10%
Meters
Consumer-System No. 145,483 144,001 144,001 143,973 50,646 74%
Solar Panels KWp 337 398 398 0 0 10%
Overall Physical progress – 34%
Circle wise Completion Plan
Discom Total Completed Nov- 18 Dec-18 Jan-19 Feb-19 Mar-19
AjVVNL 12 2 59
Expected Completion Bottleneck in
Circle Name In Progress (%)
Month completion
BANSWARA 59.8 Feb-19 Solar, Prepaid Meter
Consumer Meter, Solar
DUNGARPUR 55.68 Feb-19
Panel
29 / 29 Towns Completed.
Part-A (IT) TPIEA Verification Pending
Closure Report Pending
1 /1 Town Completed.
Part-A (SCADA) TPIEA Verification Pending
Financial Closure pending
29 / 29 Towns Completed.
Part-B
0 / 29 Towns Closed.
IT Phase II Approved cost: 10.90 , NIT not floated
GIS Substation NA
Status of AjVVNL
Reconciled BOQ : Pending
Pending Issues
Financial progress
Turnkey + Departmental
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 509 307 Sep-16 509 Aug-16 507 99 Feb-17 Sep-18 87 28
Circles 13 13 13 100
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 49 43 43 34 18 68%
Sub stations Capacity enhancement &
No. 84 108 108 64 50 59%
Additional Transformers
Over-head HT (33 & 11KV) Km 499 167 167 85 42 45%
Lines LT (440 V) Km 180 85 82 16 3 17%
Cables Aerial Bunch /UG Km 1,214 1,318 1,318 770 584 58%
Distribution Transformers No. 720 677 677 449 263 59%
Smart/ Prepaid No. 8,648 1,051 1,051 0 0 10%
Meters
Consumer-System No. 48,082 27,447 27,447 597 589 12%
Solar Panels KWp 91 58 58 0 0 10%
Overall Physical progress – 55%
Circle wise Completion Plan
Discom Total Completed Nov- 18 Dec-18 Jan-19 Feb-19 Mar-19
JaVVNL 13 2 3 1 63
Expected Completion Bottleneck in
Circle Name In Progress (%)
Month completion
BUNDI CIRCLE 54.79 Jan-19 S/S, LT, Solar Panel
Cap. enhancement of Xr,
DAUSA CIRCLE 70.3 Dec-18
Solar Panel
JHALWAR CIRCLE 58.39 Jan-19 HT, LT, DT, Solar Panel
KOTA CIRCLE 68.73 Dec-18 DT, Solar Panel
SAWAI MADHOPUR
58.8 Jan-19 HT, DT, Solar Panel
CIRCLE
TONK CIRCLE 58.64 Feb-19 Ht, Solar Panel
27 / 27 Towns Completed.
Part-A (IT) TPIEA Verification Pending
Closure Report Pending
Part-A (SCADA) 0 /2 Town Completed.
23 / 23 Towns Completed.
Part-B
0 / 23 Towns Closed.
IT Phase II
NA
ERP Approved cost : 21.52 ,NIT Date: 11-May-18, Not Awarded
RT-Das NA
Pending Issues
• R-APDRP Part A (IT) & Part B Closure
• Completion of SCADA
• Award of ERP
JoVVNL
Financial progress
Turnkey + Departmental
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 415 250 Sep-16 415 Aug-16 415 100 Jan-17 Mar-17 72 28
Circles 10 10 9 90
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 44 45 45 30 8 44%
Sub stations Capacity enhancement &
No. 54 51 51 35 33 71%
Additional Transformers
Over-head HT (33 & 11KV) Km 528 305 305 145 60 44%
Lines LT (440 V) Km 560 81 81 27 9 35%
Cables Aerial Bunch /UG Km 633 839 839 450 166 51%
Distribution Transformers No. 848 872 872 434 385 53%
Smart/ Prepaid No. 4,493 200 200 200 200 100%
Meters
Consumer-System No. 103,876 5,185 5,185 4,900 4,900 95%
Solar Panels KWp 44 0 0 0 0
Pending Issues
• R-APDRP Part A (IT) & Part B Closure
• Award of IT Ph II, ERP & Smart Metering
Sikkim-PD
Financial progress
Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 101 86 Jul-17 28 Jan-18 20 20 Jun-18 Jun-18 1 1.2
Circles 6 6 1 17
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 1 0 0 0 0
Sub
Capacity enhancement &
stations No. 3 0 0 0 0
Additional Transformers
Over-head HT (33 & 11KV) Km 35 0 0 0 0
Lines LT (440 V) Km 29 0 0 0 0
Cables Aerial Bunch / Under Ground Km 122 0 0 0 0
Distribution Transformers No. 25 0 0 0 0
Smart/ Prepaid No. 26,713 4,440 4,440 0 0 10%
Meters
Consumer-System No. 7,606 440 440 0 0 10%
Solar Panels KWp 36 345 345 0 0 10%
Overall Physical progress – 2 %
Circle wise Completion Plan
Discom Total Completed Nov- 18 Dec-18 Jan-19 Feb-19 Mar-19
Sikkim-PD 6 71
2 / 2 Towns Completed.
Part-A (IT) TPIEA Verified
Closure Report Submitted
2 / 2 Towns Completed.
Part-B
2/ 2 Towns Closed.
IT Phase II NA
ERP NA
Smart Metering NA
RT-Das NA
Pending Issues
• Progress of IPDS ~ 2 % for
• Only 20% work awarded.
TSECL
Financial progress
Partial Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 122 104 Sep-16 80 Feb-17 71 58 Feb-17 Jul-18 17 16
Circles 9 6 0 0
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 1 1 1 0 0 10%
Sub
Capacity enhancement &
stations No.
Additional Transformers
Over-head HT (33 & 11KV) Km 47 45 45 40 0 70%
Lines LT (440 V) Km 11 11 11 11 0 80%
Cables Aerial Bunch / Under Ground Km 201 230 206 197 0 68%
Distribution Transformers No. 202 202 202 150 0 38%
Smart/ Prepaid No. 2,855 0 0 0 0
Meters
Consumer-System No. 25,388 25,388 0 0 0 0%
Solar Panels KWp 31 31 31 31 31 100%
Overall Physical progress – 56%
Circle wise Completion Plan
Discom Total Completed Nov- 18 Dec-18 Jan-19 Feb-19 Mar-19
TSECL 9 74
16 / 16 Towns Completed.
Part-A (IT) TPIEA Verification under progress
Closure Report Pending
16 /16 Towns Completed.
Part-B
11 / 16 Towns Closed.
IT Phase II
NA
ERP Approved cost : 18,NIT not floated
Smart Metering NA
RT-Das NA
GIS Substation NA
Status of TSECL
Reconciled BOQ : Submitted
Pending Issues
• 5 Part B Towns to be closed
• Award of ERP
• R-APDRP Part A (IT) Verification and Closure
DVVNL
Financial progress
Partial Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs. Cr.) 814 490 Sep-16 814 Jan-16 814 100 Jun-16 Sept-18 375 77
Circles 17 17 16 94
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 19 19 17 17 12 79%
Sub stations Capacity enhancement &
No. 34 28 27 27 26 95%
Additional Transformers
Over-head HT (33 & 11KV) Km 1,347 1,542 1,099 847 813 56%
Lines LT (440 V) Km 1,020 1,534 1,477 1,368 1,351 89%
Cables Aerial Bunch / UG Km 2,270 2,187 2,103 833 742 43%
Distribution Transformers No. 1,850 2,291 2,145 1,764 1,617 76%
Smart/ Prepaid No. 22,684 0 0 0 0
Meters
Consumer-System No. 128,353 238,392 238,293 178,795 142,994 71%
Solar Panels KWp 246 4,575 3,940 3,220 2,990 70%
Smart Metering NA
GIS Substation NA
Status of DVVNL
Reconciled BOQ : Pending
Pending Issues
• Award of ERP
• Verification of R-APDRP Part A (IT)
Smart Metering NA
RT-Das NA
GIS Substation NA
Status of KESCO
Reconciled BOQ : Pending
Pending Issues
Smart Metering NA
GIS Substation NA
Status of MVVNL
Reconciled BOQ : Pending
Pending Issues
• Award of ERP
• Verification & Closure of R-APDRP Part A (IT)
Smart Metering NA
GIS Substation NA
Status of PaVVNL
Reconciled BOQ : Pending
Pending Issues
• Award of ERP
• Verification & Closure of R-APDRP Part A (IT)
Smart Metering NA
Pending Issues
• Award of ERP
• Verification & Closure of R-APDRP Part A (IT)
Financial progress
Turnkey
Sanctioned NIT floated Awarded Disbursed
Project Grant Date Value Date Value % Dt. first Dt. last Grant %
Amount (Rs Cr) 600 511 Sep-16 243 Jul-16 239 40 May-17 Oct-18 50 10
Circles 11 10 9 82
Physical progress
%
Awarded Survey Work in Physical
Milestone Name Unit Sanction Completion
Quantity Completed Progress progress
achieved
New Substation No. 1 1 1 0 0 10%
Sub
Capacity enhancement &
stations No. 41 38 38 24 19 62%
Additional Transformers
Over-head HT (33 & 11KV) Km 268 205 205 163 73 69%
Lines LT (440 V) Km
Cables Aerial Bunch / Under Ground Km 1,141 762 761 601 478 75%
Distribution Transformers No. 286 252 252 235 100 81%
Smart/ Prepaid No. 350 158 158 0 0 10%
Meters
Consumer-System No. 29,541 18,863 18,863 12,000 3,536 49%
Solar Panels KWp 2,918 2,918 153 148 148 5%
Overall Physical progress – 28 %
Circle wise Completion Plan
Discom Total Completed Nov- 18 Dec-18 Jan-19 Feb-19 Mar-19
UPCL 11 2 1 2 97
Expected Completion Bottleneck in
Circle Name In Progress (%)
Month completion
EDC HALDWANI 68.42 Jan-19 S/S, HT, Solar Panel
EDC RANIKHET 93.49 Jan-19 ABC
EDC RURAL DEHRADUN 64.44 Feb-19 HT, Prepaid Meter
Cap enhancement of Xr,
EDC SRINAGAR GARHWAL 62.08 Mar-19
DT, Consumer Meter
Cap enhancement of Xr,
EDC TEHRI 64.55 Mar-19 Prepaid Meter,
Consumer Meter
31 / 31 Towns Completed.
Part-A (IT) TPIEA Verified
Closure Report under progress
1 /1 Town Completed.
Part-A (SCADA) TPIEA Verification under progress
Financial Closure pending
31 / 31 Towns Completed.
Part-B
0 / 31 Towns Closed.
IT Phase II Approved cost: 11.90 , NIT Date:16-May-17 , Award Date:4-Jan-2018
Smart Metering NA
Pending Issues
• Closure of Part B Towns
• Award of ERP
• R-APDRP Part A (IT) & SCADA Closure
DPL
Pending Issues
WBSEDCL
Smart Metering NA
RT-Das NA
Pending Issues
• Progress of IPDS ~ 37 %
• Completion of SCADA in 1/3 towns [Kolkata]