Critical Jobs of MRSS

( Year 2018 -19 )

Department- EPS
Area- MRSS-1 and 21671bxjxf
At MRSS2- 120 MVA ,Tr-2 LV neutral bus bar was not matching with neutral bushing
palm connector resulting of oil leakage from bottom of bushing. Therefore as a step of
modification we connected these two with 4 - 12x 40 sq mm Cu flexible adequate for 56 KA for
3 sec STR. 120

Copyright © 2010 Jindal Steel & Power Ltd.


At MRSS2- RTV-570 Coating application at Air cored
reactor SVC- Oct 2018
Cleaning job of outer surface of reactors

3 Copyright © 2010 Jindal Steel & Power Ltd.


Reactors 2nd, 3rd, 4th and 5th Harmonic reactors at a glance
after final RTV coat

Copyright © 2010 Jindal Steel & Power Ltd.


2nd Harmonic resistance boxes bottom plate and support
insulator coating where we usually phased max no of
flashovers and tracking.

Copyright © 2010 Jindal Steel & Power Ltd.


Technical data sheet of Si-Coat RTV 570TM

 Dielectric strength- 735.5 Volts/mil (290.5 KV/Cm) Alstom 149


 Surface resistivity- 2.2x1015 ohm-in (5.5X1015 Ohm-Cm) Alstom 249
 Temp Stability- -40 to +480*F (-40 to +250 *C)
 Water repellency angle- 120 degree
 Dry Arc resistance- track- 180 sec; burn out- 450 sec
 Dissipation factor- @100 Hz- 0.01; @ 100 KHz -0.0057 Alstom d150
 Thermal expansion coefficient – 0.24x 10- 4 Cm/Cm*C
 Application Temp range- 5 to 60 *C ( ambient); 5-130 *C (substrate)
 Drying time- a) Skin –over time -15 Mints
b) Track free time- 30 Mints
c) Cure through- 6 hrs.
d) Fully physical Characteristics- 7 Days
 Method of application- Airless spray, brush or dip

Ref- Copyright 2004,CSL Silicones inc.

Copyright © 2010 Jindal Steel & Power Ltd.


Delta VT repairing in Jan 2019- Faulty VT removal
and found carbon and mud accumulation at Bottom of tank

Copyright © 2010 Jindal Steel & Power Ltd.


HV leads repairing, 4 no's 33 KV bushing changed and
bottom plate of one PT damaged so replaced with new one
thus made it ready for use.

Copyright © 2010 Jindal Steel & Power Ltd.


TRW, March 2019- SAF spare transformer 12 no of epoxy bus bar
bushings changed with spare one, old selector, diverter and chamber changed with
new one. Its HV winding resistance are deviated in two (4 & 20) taps suspect
dough in step resistance so its job is in progress.

Copyright © 2010 Jindal Steel & Power Ltd.


MRSS-1,Feb 2019- Though core, frame and body/tank brought out to the top of
tank and get shorted in a box. This has done to restrict high potential induced in core resulting of
partial discharge and eventually may damaged the winding and If core is grounded, this voltage safely
discharge to ground. In the event of charging transformer potential difference induced between upper
and bottom portion of tank resulting high discharge/spark, which get nullified completely by using
this earth links. – Electricity Today Magazine- James white.

Copyright © 2010 Jindal Steel & Power Ltd.


MRSS-1,March 2019- 220 KV bay-8, B-Phase CVT oil
leakage arrested from its level indicator without taking shutdown.

Copyright © 2010 Jindal Steel & Power Ltd.


MRSS-1, Bay-15 Transformer, March 2019- We repeatedly found the problem
of oil spillage when oil temp rises up to 46*C, after wards we taken S/D and lowered the conservator
and found air cell is open from its two supporting hooks and oil inside the cell. This might be the
reason of creating back pressure of oil spillage through Y-phase HV bushing when temp rises.

Copyright © 2010 Jindal Steel & Power Ltd.


MRSS-1, Bay-09 Transformer, March 2019- Oil leakage problem
attended from top windows and B-Phase tyrak.
Result- Oil leakage reduced from 5.5 Ltrs to 50 mLtrs/day.

Copyright © 2010 Jindal Steel & Power Ltd.


MRSS-1, Feb 2019- As a compliances of TPM-JH activities at plant some
painting and writing work carried out at Transformer M boxes, earth pits and GI
structures.

Copyright © 2010 Jindal Steel & Power Ltd.


MRSS-2, Feb 2019-Nominclature work inside transformer
Marshaling boxes.

Copyright © 2010 Jindal Steel & Power Ltd.


MRSS-1, JLDC, Feb 2019- Saving through Minimizing Import
from CSPDCL-Earlier we control Kwh and KVA by monitoring only Active Power Export/Import
through Power monitor system, but now we monitoring and controlling KVAH also along with Kwh
and KVA.
Result- i) We have saved Rs.150000 Lakhs (approx.) saved in 15 days.
ii) Earlier Import KVAh was 100000 units approx. now it comes to 80000 units .

After Graphical illustration

Copyright © 2010 Jindal Steel & Power Ltd.


MRSS-1, JLDC, Jan 2019- Power quality Monitor (PQID) Software
Installation .
 Installation and configuration of PQ Manager PQ vision software .
 PQID Modem health assessment
 Establishing communication between PC ,Modem and terminal (device).
 Evaluation of event record by simulating faults.

Copyright © 2010 Jindal Steel & Power Ltd.


MRSS-2, I/D Board, March 2019- CB Tulip contact changed and
bus inspected for it’s abnormal sound

Before After Bus bar


Copyright © 2010 Jindal Steel & Power Ltd.
CSEB yard, March 2019- SF6 filling at 245 KV, Y-Phase CB pole at
Ckt-II

Before After
Copyright © 2010 Jindal Steel & Power Ltd.
Thank you

End of .ppt

FROM EPS-MRSS TEAM