CONSTRUCCION PUENTE CARROZABLE RUMICHACA Y ACCESOS, DISTRITO DE AYACUCHO Y JESUS NAZARENO, PROVINCIA DE HUAMANGA - AYACUCHO S/ 17,903.48 S/ 449,671.08 S/ 223,100.80 S/ 320,094.58 S/ 392,500.97 S/ 425,581.12 S/ 380,679.33 S/ 2,209,531.36 S/ 534,761.99 S/ 534,761.99 S/ 2,744,293.35
MEJORAMIENTO DE LA VÍA DE ACCESO S/ 17,903.48 S/ 367,612.82 S/ 128,985.25 S/ - S/ - S/ - S/ - S/ 514,501.55 S/ 59,958.08 S/ 59,958.08 S/ 574,459.63
OBRAS PRELIMINARES S/ 17,903.48 S/ 39,387.66 S/ - S/ - S/ - S/ - S/ - S/ 57,291.14 S/ - S/ - S/ 57,291.14
EXPLANACIONES S/ - S/ 326,816.26 S/ 123,600.06 S/ - S/ - S/ - S/ - S/ 450,416.32 S/ 5,406.93 S/ 5,406.93 S/ 455,823.25
CORTE EN MATERIAL SUELTO S/ - S/ 27,527.28 S/ - S/ - S/ - S/ - S/ - S/ 27,527.28 S/ - S/ - S/ 27,527.28
CORTE EN ROCA FIJA S/ - S/ 39,775.52 S/ 11,965.00 S/ - S/ - S/ - S/ - S/ 51,740.52 S/ - S/ - S/ 51,740.52
CORTE EN ROCA SUELTA S/ - S/ 193,788.92 S/ - S/ - S/ - S/ - S/ - S/ 193,788.92 S/ - S/ - S/ 193,788.92
DESQUINCHE EN ROCA FIJA S/ - S/ 10,459.10 S/ - S/ - S/ - S/ - S/ - S/ 10,459.10 S/ - S/ - S/ 10,459.10
DESQUINCHE EN ROCA SUELTA S/ - S/ 21,718.62 S/ 9,872.10 S/ - S/ - S/ - S/ - S/ 31,590.72 S/ - S/ - S/ 31,590.72
CONFORMACIÓN DE TERRAPLENES S/ - S/ - S/ 74,478.22 S/ - S/ - S/ - S/ - S/ 74,478.22 S/ - S/ - S/ 74,478.22
ELIMINACION DE MATERIAL EXCEDENTE S/ - S/ 33,546.82 S/ 27,284.74 S/ - S/ - S/ - S/ - S/ 60,831.56 S/ - S/ - S/ 60,831.56
PERFILADO Y COMPACTADO DE SUBRASANTE S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 5,406.93 S/ 5,406.93 S/ 5,406.93
CUNETAS S/ - S/ 1,408.90 S/ 5,385.19 S/ - S/ - S/ - S/ - S/ 6,794.09 S/ - S/ - S/ 6,794.09
CONFORMACIÓN DE CUNETAS EN MATERIAL SUELTO S/ - S/ - S/ 559.10 S/ - S/ - S/ - S/ - S/ 559.10 S/ - S/ - S/ 559.10
CONFORMACIÓN DE CUNETAS EN ROCA FIJA S/ - S/ 1,408.90 S/ - S/ - S/ - S/ - S/ - S/ 1,408.90 S/ - S/ - S/ 1,408.90
CONFORMACIÓN DE CUNETAS EN ROCA SUELTA S/ - S/ - S/ 4,826.09 S/ - S/ - S/ - S/ - S/ 4,826.09 S/ - S/ - S/ 4,826.09
PAVIMENTOS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 54,551.15 S/ 54,551.15 S/ 54,551.15
EXTENDIDO, REGADO Y COMPACTADO DE AFIRMADO E=0.20M S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 54,551.15 S/ 54,551.15 S/ 54,551.15
CONSTRUCCION DEL PUENTE CARROZABLE RUMICHACA S/ - S/ 82,058.26 S/ 94,115.55 S/ 320,094.58 S/ 379,711.13 S/ 275,938.64 S/ 380,679.33 S/ 1,532,597.49 S/ 448,550.16 S/ 448,550.16 S/ 1,981,147.65
SUBESTRUCTURA DEL PUENTE S/ - S/ 82,058.26 S/ 94,115.55 S/ 320,094.58 S/ 72,564.41 S/ - S/ - S/ 568,832.80 S/ - S/ - S/ 568,832.80
EXCAVACION PARA ESTRIBOS EN TERRENO NORMAL S/ - S/ 14,005.72 S/ - S/ - S/ - S/ - S/ - S/ 14,005.72 S/ - S/ - S/ 14,005.72
EXCAVACION PARA ESTRIBOS BAJO AGUA S/ - S/ 38,997.36 S/ 1,585.26 S/ - S/ - S/ - S/ - S/ 40,582.62 S/ - S/ - S/ 40,582.62
EXCAVACION PARA ESTRIBOS EN ROCA SUELTA S/ - S/ 29,055.18 S/ - S/ - S/ - S/ - S/ - S/ 29,055.18 S/ - S/ - S/ 29,055.18
DESQUINCHE EN ROCA SUELTA S/ - S/ - S/ 6,029.02 S/ - S/ - S/ - S/ - S/ 6,029.02 S/ - S/ - S/ 6,029.02
RELLENO CON MATERIAL PROPIO S/ - S/ - S/ - S/ - S/ 18,683.08 S/ - S/ - S/ 18,683.08 S/ - S/ - S/ 18,683.08
ELIMINACION DE MATERIAL EXCEDENTE S/ - S/ - S/ - S/ - S/ 23,576.83 S/ - S/ - S/ 23,576.83 S/ - S/ - S/ 23,576.83
SOLADO PARA ZAPATAS, f'c=100 KG/CM2-BAJO AGUA S/ - S/ - S/ 6,675.27 S/ - S/ - S/ - S/ - S/ 6,675.27 S/ - S/ - S/ 6,675.27
CONCRETO F'C=210 KG/CM2 BAJO AGUA S/ - S/ - S/ - S/ 140,400.30 S/ - S/ - S/ - S/ 140,400.30 S/ - S/ - S/ 140,400.30
ENCOFRADO Y DESENCOFRADO-ESTRIBOS (BAJO AGUA) S/ - S/ - S/ 1,579.94 S/ 28,726.15 S/ 4,165.29 S/ - S/ - S/ 34,471.38 S/ - S/ - S/ 34,471.38
CONCRETO F'C=210 KG/CM2 EN SECO S/ - S/ - S/ - S/ 33,100.28 S/ 18,821.73 S/ - S/ - S/ 51,922.01 S/ - S/ - S/ 51,922.01
ENCOFRADO Y DESENCOFRADO-ESTRIBOS S/ - S/ - S/ - S/ 15,160.03 S/ 3,356.04 S/ - S/ - S/ 18,516.07 S/ - S/ - S/ 18,516.07
ENCOFRADO Y DESENCOFRADO CARA VISTA EN SECO S/ - S/ - S/ - S/ 8,259.17 S/ 1,828.36 S/ - S/ - S/ 10,087.53 S/ - S/ - S/ 10,087.53
ACERO DE REFUERZO FY=4200KG/CM2-ESTRIBOS S/ - S/ - S/ 78,246.06 S/ 88,997.43 S/ - S/ - S/ - S/ 167,243.49 S/ - S/ - S/ 167,243.49
CURADO DE CONCRETO S/ - S/ - S/ - S/ 5,451.22 S/ 2,133.08 S/ - S/ - S/ 7,584.30 S/ - S/ - S/ 7,584.30
SUPERESTRUCTURA S/ - S/ - S/ - S/ - S/ 264,944.77 S/ 268,262.52 S/ 51,944.98 S/ 585,152.27 S/ 20,618.80 S/ 20,618.80 S/ 605,771.07
LOSAS MACIZAS Y VEREDAS S/ - S/ - S/ - S/ - S/ - S/ 3,264.88 S/ 51,944.98 S/ 55,209.86 S/ 20,618.80 S/ 20,618.80 S/ 75,828.66
LOSAS MACIZAS Y VEREDAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
CONCRETO F'C=280 KG/CM2 EN LOSA S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 19,029.32 S/ 19,029.32 S/ 19,029.32
ENCOFRADO Y DESENCOFRADO- LOSA S/ - S/ - S/ - S/ - S/ - S/ 3,264.88 S/ 6,408.85 S/ 9,673.73 S/ - S/ - S/ 9,673.73
ACERO DE REFUERZO FY=4200KG/CM2 - LOSA Y VEREDAS S/ - S/ - S/ - S/ - S/ - S/ - S/ 40,841.09 S/ 40,841.09 S/ - S/ - S/ 40,841.09
CONCRETO F'C=280 KG/CM2 EN VEREDAS S/ - S/ - S/ - S/ - S/ - S/ - S/ 2,595.58 S/ 2,595.58 S/ 1,249.72 S/ 1,249.72 S/ 3,845.30
ENCOFRADO Y DESENCOFRADO- VEREDAS S/ - S/ - S/ - S/ - S/ - S/ - S/ 940.40 S/ 940.40 S/ 83.17 S/ 83.17 S/ 1,023.57
CURADO DE CONCRETO S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,159.06 S/ 1,159.06 S/ 256.59 S/ 256.59 S/ 1,415.65
VIGAS METÁLICAS S/ - S/ - S/ - S/ - S/ 264,944.77 S/ 264,997.64 S/ - S/ 529,942.41 S/ - S/ - S/ 529,942.41
FABRICACION DE VIGAS METALICAS Y DIAFRAGMAS S/ - S/ - S/ - S/ - S/ 243,819.32 S/ 180,791.20 S/ - S/ 424,610.52 S/ - S/ - S/ 424,610.52
LANZAMIENTO Y MONTAJE S/ - S/ - S/ - S/ - S/ - S/ 11,705.80 S/ - S/ 11,705.80 S/ - S/ - S/ 11,705.80
PINTADO Y ARENADO S/ - S/ - S/ - S/ - S/ - S/ 33,059.67 S/ - S/ 33,059.67 S/ - S/ - S/ 33,059.67
APOYO FIJO S/ - S/ - S/ - S/ - S/ - S/ 7,059.36 S/ - S/ 7,059.36 S/ - S/ - S/ 7,059.36
APOYO MOVIL S/ - S/ - S/ - S/ - S/ - S/ 7,059.36 S/ - S/ 7,059.36 S/ - S/ - S/ 7,059.36
CONTROL DE CALIDAD DE VIGAS S/ - S/ - S/ - S/ - S/ - S/ 25,322.25 S/ - S/ 25,322.25 S/ - S/ - S/ 25,322.25
TRASPORTE DE VIGA METALICA S/ - S/ - S/ - S/ - S/ 21,125.45 S/ - S/ - S/ 21,125.45 S/ - S/ - S/ 21,125.45
LOSA DE APROXIMACION S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 14,415.01 S/ 14,415.01 S/ 14,415.01
CONCRETO F'C=210KG/CM2 EN LOSAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 6,356.07 S/ 6,356.07 S/ 6,356.07
CONCRETO F'C=175 KG/CM2 EN VEREDAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,275.31 S/ 1,275.31 S/ 1,275.31
ACERO DE REFUERZO FY=4200KG/CM2 - LOSA Y VEREDAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 6,783.63 S/ 6,783.63 S/ 6,783.63
MUROS DE CONTENCION DE RELLENO S/ - S/ - S/ - S/ - S/ 42,201.95 S/ 7,676.12 S/ 323,548.35 S/ 373,426.42 S/ 343,383.16 S/ 343,383.16 S/ 716,809.58
EXCAVACION PARA MUROS DE CONTENCION EN TERRENO NORMAL S/ - S/ - S/ - S/ - S/ - S/ 7,676.12 S/ 10,519.12 S/ 18,195.24 S/ - S/ - S/ 18,195.24
RELLENO CON MATERIAL PROPIO SELECCIONADO EN ACCESO A PUENTE S/ - S/ - S/ - S/ - S/ 42,201.95 S/ - S/ - S/ 42,201.95 S/ - S/ - S/ 42,201.95
SOLADO PARA ZAPATAS, f'c=100 KG/CM2 S/ - S/ - S/ - S/ - S/ - S/ - S/ 21,633.88 S/ 21,633.88 S/ - S/ - S/ 21,633.88
CONCRETO F'C=175 KG/CM2 EN MUROS Y PISO S/ - S/ - S/ - S/ - S/ - S/ - S/ 7,547.60 S/ 7,547.60 S/ 294,356.38 S/ 294,356.38 S/ 301,903.98
ENCOFRADO Y DESENCOF MUROS REFORZADOS S/ - S/ - S/ - S/ - S/ - S/ - S/ 15,387.10 S/ 15,387.10 S/ 41,867.22 S/ 41,867.22 S/ 57,254.32
ACERO EN MUROS REFORZADOS GRADO 60 S/ - S/ - S/ - S/ - S/ - S/ - S/ 268,460.65 S/ 268,460.65 S/ - S/ - S/ 268,460.65
CURADO DE CONCRETO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 7,159.56 S/ 7,159.56 S/ 7,159.56
BARANDAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 46,471.04 S/ 46,471.04 S/ 46,471.04
BARANDA METALICA EN PUENTE S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 14,267.00 S/ 14,267.00 S/ 14,267.00
BARANDA METALICA EN ACCESOS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 22,256.52 S/ 22,256.52 S/ 22,256.52
COLUMNETA DE CONCRETO PREFABRICADA DE 0.15X0.15m S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 9,947.52 S/ 9,947.52 S/ 9,947.52
PINTURA S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,755.81 S/ 1,755.81 S/ 1,755.81
PINTURA S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ -
PINTURA EN CONCRETO S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 375.20 S/ 375.20 S/ 375.20
PINTURA EN BARANDAS METALICAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,380.61 S/ 1,380.61 S/ 1,380.61
VARIOS S/ - S/ - S/ - S/ - S/ - S/ - S/ 5,186.00 S/ 5,186.00 S/ 17,931.48 S/ 17,931.48 S/ 23,117.48
TUBO DE DRENAJE EN LOSA CON TUBO PVC Ø=3" S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,129.57 S/ 1,129.57 S/ 1,129.57
TUBERIA PVC Ø6"EN VEREDAS S/ - S/ - S/ - S/ - S/ - S/ - S/ 5,186.00 S/ 5,186.00 S/ - S/ - S/ 5,186.00
JUNTA DE DILATACIÓN ASFALTICA Y METALICA S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 5,959.94 S/ 5,959.94 S/ 5,959.94
CARPETA ASFALTICA EN FRIO e=5CM S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 10,841.97 S/ 10,841.97 S/ 10,841.97
SEÑALIZACION S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 3,974.86 S/ 3,974.86 S/ 3,974.86
SEÑAL PREVENTIVA S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,863.74 S/ 1,863.74 S/ 1,863.74
SEÑAL DE INFORMACION GENERAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,482.72 S/ 1,482.72 S/ 1,482.72
CIMENTACION Y MONTAJE DE SEÑALES S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 628.40 S/ 628.40 S/ 628.40
DEFENSA RIBERENA EN EL CAUCE DEL RIO S/ - S/ - S/ - S/ - S/ 12,789.84 S/ 149,642.48 S/ - S/ 162,432.32 S/ - S/ - S/ 162,432.32
TRAZO Y REPLANTEO S/ - S/ - S/ - S/ - S/ 3,444.00 S/ - S/ - S/ 3,444.00 S/ - S/ - S/ 3,444.00
PREPARACION DE TERRENO C/MAQUINARIA S/ - S/ - S/ - S/ - S/ 1,579.20 S/ - S/ - S/ 1,579.20 S/ - S/ - S/ 1,579.20
EXTRACCCION, ACOPIO Y TRASLADO DE PIEDRA DE Ø6"@ Ø8" S/ - S/ - S/ - S/ - S/ 7,766.64 S/ 9,985.68 S/ - S/ 17,752.32 S/ - S/ - S/ 17,752.32
GAVION HEXAGONAL TIPO COLCHON DE 4.00x2.00x0.30 S/ - S/ - S/ - S/ - S/ - S/ 27,274.40 S/ - S/ 27,274.40 S/ - S/ - S/ 27,274.40
GAVION HEXAGONAL TIPO CAJA DE 4.00x1.00x1.00 S/ - S/ - S/ - S/ - S/ - S/ 112,382.40 S/ - S/ 112,382.40 S/ - S/ - S/ 112,382.40
MITIGACIÓN AMBIENTAL S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 26,253.75 S/ 26,253.75 S/ 26,253.75
LIMPIEZA FINAL DE OBRA S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 1,327.50 S/ 1,327.50 S/ 1,327.50
RESTAURACIÓN DE CANTERAS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 19,500.00 S/ 19,500.00 S/ 19,500.00
PLANTADO DE ÁRBOLES BORDE CAUCE S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 3,320.00 S/ 3,320.00 S/ 3,320.00
RECUPERACIÓN DE BOTADEROS S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ - S/ 2,106.25 S/ 2,106.25 S/ 2,106.25
Total general S/ 17,903.48 S/ 449,671.08 S/ 223,100.80 S/ 320,094.58 S/ 392,500.97 S/ 425,581.12 S/ 380,679.33 S/ 2,209,531.36 S/ 534,761.99 S/ 534,761.99 S/ 2,744,293.35
Etiqueta de
Nombre del recurso Tipo COSTO
material
TOPOGRAFO Trabajo HH S/17.70/hora
ESPECIALISTA EN RADIOLOGÍA Trabajo HH S/25.00/hora
OPERARIO Trabajo HH S/16.48/hora
OFICIAL Trabajo HH S/13.86/hora
PEON Trabajo HH S/12.40/hora
CARTEL DE OBRA DE 3.60 X 2.40 M(inc. transporte e instalación) Material und S/805.08
PERNOS Material pza S/29.68
PLACAS RADIOGRÁFICAS Material und S/233.05