Beruflich Dokumente
Kultur Dokumente
BUILDING
LOT 1 & 2 BLOCK S-159 NO. 60 EUGENIO LOPEZ DRIVE CORNER
SAMAR AVENUE QUEZON CITY
COORDINATION
MEETING No. 148
AUGUST 16, 2019
S TAT U S O F W I R E
REPLACEMENT
S TAT U S O F W I R E R E P L A C E M E N T
10.0 XLPE HVSG to metering pole 1 25-Jul 25-Jul 4 4 25-Jul 25-Jul 26-Jul 4 Building Energization
STATUS OF
INSTALLATION OF
LIGHTING FIXTURES
S T AT U S O F I N S T A L L AT I O N O F L I G H T I N G F I X T U R E S
PROJECT : CBCP
LOCATION: #60 E. LOPEZ DRV., COR. SAMAR AVE., QUEZON CITY
SUBJECT : STATUS OF INSTALLATION OF LIGHTING FIXTURES
DATE: as of August 16, 2019
LEGEND : - DONE/COMPLETED
- WITH ACCOMPLISHMENT
TESTED
UNIT/LEVEL INSTALLED TERMINATED
(wire)
BASEMENT 2 138/158 105/158 105/158
BASEMENT 1 140/158 73/158 73/158
LOWER GROUND 118/174 18/174 18/174
UPPER GROUND FLOOR 608/772 608/772 608/772
SECOND FLOOR 158/466 139/466 139/466
THIRD FLOOR 76/383 24/383 24/393
FOURTH FLOOR 494/746 124/746 124/746
FIFTH FLOOR 4/263 0/263 0/245
SIXTH FLOOR 33/58 0/58 0/58
TOTAL 1769/3170 1091/3170 1091/3170
STATUS OF
INSTALLATION OF
DEVICES (FDAS)
STATUS OF INSTALLATION OF DEVICES (FDAS)
FDAS
ADDRESSABLE FIREMAN'S
UNIT/LEVEL SMOKE STROBE HEAT DUCT MANUAL PULL ANNUNCIATOR
BEAM SMOKE TELEPHONE
DETECTOR LIGHT DETECTOR DETECTOR STATION PANEL
DETECTOR JACK
BASEMENT 2 7/7 0/4 - - - 0/4 0/1 1/5
BASEMENT 1 0/6 0/4 - - - 0/4 0/1 1/4
LOWER GROUND 0/13 0/3 - - - 0/3 0/1 0/4
UPPER GROUND FLOOR 50/54 18/18 - - - 7/9 0/1 0/3
SECOND FLOOR 59/74 6/12 - - - 5/5 0/1 0/1
THIRD FLOOR 51/64 12/15 - 0/4 - 5/5 0/1 0/3
FOURTH FLOOR 77/77 8/12 - - - 0/4 0/1 0/3
FIFTH FLOOR 0/33 0/8 0/4 - 0/2 0/3 0/1 0/3
SIXTH FLOOR 0/35 0/5 - - - 0/4 - 0/2
TOTAL 244/363 44/81 0/4 0/4 0/2 17/41 0/8 2/28
PREPARED BY:
GREEN BUILDING
REQUIREMENTS
GREEN BUILDING REQUIREMENTS
WORLD URBAN
CONCERNS
M AT E R I A L S B Y O T H E R T R A D E S N E E D E D T O B E C L E A R E D P R I O R T O F I N I S H I N G
AND PUNCHLIST WORKS
W I L - A N , P O W E R C O R E A N D S P U R W AY
CONCERNS
M AT E R I A L S B Y O T H E R T R A D E S N E E D E D T O B E C L E A R E D P R I O R T O F I N I S H I N G
AND PUNCHLIST WORKS
O S M M AT E R I A L
CONCERNS
M AT E R I A L S B Y O T H E R T R A D E S N E E D E D T O B E C L E A R E D P R I O R T O F I N I S H I N G
AND PUNCHLIST WORKS
MAGNA PRIME
CONCERNS
M AT E R I A L S B Y O T H E R T R A D E S N E E D E D T O B E C L E A R E D P R I O R T O F I N I S H I N G
AND PUNCHLIST WORKS
FRESH AIR
FAF-1 (X3)
WELL
Start:08/21/19
End:08/22/19
No. of Days:2
EXHAUST
EF-6 (X3)
AIRWELL
Start:08/21/19
End:08/22/19
No. of Days:2
LPB1-B DPLG LVSB
PARKING JF1 (X14)
Start:08/21/19
End:08/22/19
No. of Days:2
UTILITY
EF-1 (X2)
ROOMS 1&2
Start:08/21/19
End:08/22/19
No. of Days:2
ELECTRICITY –
TOILET TEF-4 (X2)
COOLING -
Start:08/21/19 Start: Start:8/10/2019 Start:
- DONE End:08/22/19 End:TESTED End:8/17/2019 End:TESTED
- DELAYED No. of Days:2 No. of Days: No. of Days:7 No. of Days:
- AHEAD
- TARGET NEXT WEEK
BASEMENT 01
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
- DONE
- DELAYED
- AHEAD
- TARGET NEXT WEEK
LOWER GROUND FLOOR
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
Fan Coil Unit, VRF Type
BOOKSTORE AND
FCU-102
COFFEE SHOP
Start:08/19/19
End:08/24/19 LPBC DPA
No. of Days:6
FCU-C145 (x4)
Start:08/19/19
MULTIPURPOSE
End:08/24/19 LPMR DPA
ELECTRICITY – RM. 01
No. of Days:6
COOLING - Panel LVSB
FCU-C145 (x4)
- DONE Start:08/19/19 Start: Start:
- DELAYED End:08/24/19 End:TESTED End:
No. of Days:6 No. of Days: No. of Days:
- AHEAD
ACCU-103 (X2) Panel PME6F DPMEB
- TARGET NEXT WEEK Start:08/19/19 Start:08/07/19 Start: Start:
End:08/24/19 End:08/18/19 End: End:TESTED
UPPER GROUND FLOOR No. of Days:6 No. of Days:12 No. of Days: No. of Days:
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
Fan Coil Unit, VRF Type
MULTIPURPOSE
FCU-C104 (x2) LPMR DPA
RM. 02
Start:08/19/19 Start: Start:
Panel LVSB
End:08/24/19 End: End:TESTED
No. of Days:6 No. of Days: No. of Days:
ACCU-104 Panel PME6F DPMEB
Start:08/19/19 Start:08/07/19 Start: Start:
End:08/24/19 End:08/18/19 End:TESTED End:TESTED
No. of Days:6 No. of Days:12 No. of Days: No. of Days:
YOUTH, ADMIN
OFFICE AND AV FCU-W101 (x3)
EQUIP STO. RM.
Start:08/19/19 LPUG DPA
End:08/24/19
No. of Days:6 Panel LVSB
VIP LOUNGE FCU-W102 (x2)
PLAY/GATHERIN
FCU-C203
G AREA
Start:08/19/19
End:08/24/19 Panel LPSS2 Panel DPA
No. of Days:6
CLASSROOM 204-
FCU-S203 (x6) LPSS2 DPA
206
BOARD ROOM
AND CHOIR & AV FCU-C402 (x4) LPPOF DPB
RM.
Panel LVSB
Start:08/19/19 Start:08/12/19 Start:
End:08/24/19 End:08/13/19 End:TESTED
No. of Days:6 No. of Days:2 No. of Days:
ACCU 409 PME6F
Start:08/19/19 Start:08/07/19 Start:
End:08/24/19 End:08/18/19 End:TESTED
No. of Days:6 No. of Days:12 No. of Days:
MEETING RM
1&2 AND FCU-W450 (x2) LP4FB
DISCIPLESHIP
Start:08/19/19 Start:08/12/19
End:08/24/19 End:08/13/19
No. of Days:6 No. of Days:2
MEETING RM
1&2 AND FCU-W450 (x6) DPB
DISCIPLESHIP
Panel LVSB
Start:08/19/19
End:08/24/19 LPPOF
No. of Days:6
ELECTRICITY –
COOLING - PRAYER ROOM
FCU-W401 (x3)
AND OFFICES
COOLING TOWERS
CHWP-1 (X3)
Start:08/16/19
End:08/17/19 PME6FC DPMEWH LVSB
No. of Days:2
ELECTRICITY –
COOLING - COWP-1 (X3)
Start:08/16/19 Start:08/07/19 Start: Start:
- DONE End:08/17/19 End:08/14/19 End:TESTED End:TESTED
- DELAYED No. of Days:2 No. of Days:8 No. of Days: No. of Days:
- AHEAD Catch-up: Aug.20
- TARGET NEXT WEEK
ROOF DECK
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
FIRE PROTECTION
FP-01
Start:08/19/19
End:08/20/19 PFP ATS LVSB
No. of Days:2
JP-01
Start:08/19/19 Start:08/17/19
End:08/20/19 End:08/18/19
No. of Days:2 No. of Days:2
PLUMBING WORKS
CPS PUMPS
(triplex)
Start:08/16/19
End:08/17/19
No. of Days:2 PSE DPMEA
T E S T I N G O F L I G H T I N G F I X T U R E S AT B A S E M E N T 0 1
PROGRESS PHOTOS
ELECTRICAL WORKS
T E S T I N G O F L I G H T I N G F I X T U R E S AT L G F
PROGRESS PHOTOS
ELECTRICAL WORKS
I N S TA L L AT I O N A N D T E S T I N G O F L I G H T I N G F I X T U R E S AT
UGF - TOILET
PROGRESS PHOTOS
ELECTRICAL WORKS
I N S TA L L E D C E I L I N G B O A R D S AT 3 R D F L O O R - C W H
PROGRESS PHOTOS
CIVIL WORKS
I N S TA L L E D R O L L - U P D O O R S A L O N G E . L O P E Z A N D
S A M A R AV E .
PROGRESS PHOTOS
CIVIL WORKS
F I N I S H E D S T E P S G O I N G T O S TA G E AT 3 R D F L O O R - C W H
PROGRESS PHOTOS
E X T E R I O R V I E W O F T H E B U I L D I N G A L O N G S A M A R AV E .
PROGRESS PHOTOS