A PROPOSED CHURCH

BUILDING
LOT 1 & 2 BLOCK S-159 NO. 60 EUGENIO LOPEZ DRIVE CORNER
SAMAR AVENUE QUEZON CITY

COORDINATION
MEETING No. 148
AUGUST 16, 2019
S TAT U S O F W I R E
REPLACEMENT
S TAT U S O F W I R E R E P L A C E M E N T

PROJECT : CBCP - DONE


LOCATION: #60 E. LOPEZ. DRV., COR. SAMAR AVE., QUEZON CITY - NEXT WEEK'S TARGET
SUBJECT : SCHEDULE FOR WIRE REPLACEMENT - DONE/AHEAD
- DELAYED
PULL - OUT OF DAMAGED WIRES CABLE PULLING OF NEW WIRES
PANEL/
ITEM ROUTE TERMINATION REMARKS
DESCRIPTION DURATION START COMPLETION MANPOWER DURATION START COMPLETION
& TESTING
MANPOWER

Transformer Room (UGF) to EE


1.0 DPMEWH 5 17-Jul 21-Jul 20 12 24-Jul 3-Aug 4-Aug 20
Room A (3F)
Building electricity supply will
Pump Room (B2) to Transformer
2.0 DPMEA 5 19-Jul 23-Jul 10 9 26-Jul 2-Aug 3-Aug 15 be cut off due to wiring works
Room (UGF)
to LVSB during replacement
Transformer Room (UGF) to EE
3.0 DPWH 5 20-Jul 24-Jul 10 9 27-Jul 3-Aug 4-Aug 10
Room B (3F)

Transformer Room (UGF) to EE affected areas – VRF ACCU


4.0 PME6F 8 5-Aug 12-Aug 10 11 15-Aug 24-Aug 25-Aug 10
Room B (6F) at UGF,3/F and 4/F
Transformer Room (UGF) to
5.0 PELF 5 11-Sep 15-Sep 10 11 18-Sep 27-Sep 28-Sep 10 affected – elevator (1-unit)
Machine Room (6F)

Transformer Room (UGF) to


6.0 PELA 5 29-Sep 3-Oct 10 9 6-Oct 13-Oct 14-Oct 10 affected – elevator (2-units)
Machine Room (6F)

Transformer Room (UGF) to affected – all power supply


7.0 DPLG 5 4-Aug 8-Aug 10 9 11-Aug 18-Aug 19-Aug 15
Security Office (LGF) for parking levels
Transformer Room (UGF) to AV
8.0 DPAV 5 26-Aug 30-Aug 10 9 2-Sep 9-Sep 10-Sep 10 affected – all AV supply
Storage (UGF)

Transformer Roon (UGF) to ATS affected - LVSG, whole


9.0 PFP 5 12-Aug 12-Aug 10 9 12-Aug 13-Aug 13-Aug 10
(B1) building

10.0 XLPE HVSG to metering pole 1 25-Jul 25-Jul 4 4 25-Jul 25-Jul 26-Jul 4 Building Energization
STATUS OF
INSTALLATION OF
LIGHTING FIXTURES
S T AT U S O F I N S T A L L AT I O N O F L I G H T I N G F I X T U R E S

PROJECT : CBCP
LOCATION: #60 E. LOPEZ DRV., COR. SAMAR AVE., QUEZON CITY
SUBJECT : STATUS OF INSTALLATION OF LIGHTING FIXTURES
DATE: as of August 16, 2019
LEGEND : - DONE/COMPLETED
- WITH ACCOMPLISHMENT
TESTED
UNIT/LEVEL INSTALLED TERMINATED
(wire)
BASEMENT 2 138/158 105/158 105/158
BASEMENT 1 140/158 73/158 73/158
LOWER GROUND 118/174 18/174 18/174
UPPER GROUND FLOOR 608/772 608/772 608/772
SECOND FLOOR 158/466 139/466 139/466
THIRD FLOOR 76/383 24/383 24/393
FOURTH FLOOR 494/746 124/746 124/746
FIFTH FLOOR 4/263 0/263 0/245
SIXTH FLOOR 33/58 0/58 0/58
TOTAL 1769/3170 1091/3170 1091/3170
STATUS OF
INSTALLATION OF
DEVICES (FDAS)
STATUS OF INSTALLATION OF DEVICES (FDAS)

PROJECT : CBCP LEGEND :


LOCATION: #60 E. LOPEZ DRV., COR. SAMAR AVE., QUEZON CITY - DONE/COMPLETED
SUBJECT : STATUS OF INSTALLATION OF DEVICES FOR AUXILIARY SYSTEM (FDAS) - WITH ACCOMPLISHMENT
DATE: as of July 31, 2019

FDAS
ADDRESSABLE FIREMAN'S
UNIT/LEVEL SMOKE STROBE HEAT DUCT MANUAL PULL ANNUNCIATOR
BEAM SMOKE TELEPHONE
DETECTOR LIGHT DETECTOR DETECTOR STATION PANEL
DETECTOR JACK
BASEMENT 2 7/7 0/4 - - - 0/4 0/1 1/5
BASEMENT 1 0/6 0/4 - - - 0/4 0/1 1/4
LOWER GROUND 0/13 0/3 - - - 0/3 0/1 0/4
UPPER GROUND FLOOR 50/54 18/18 - - - 7/9 0/1 0/3
SECOND FLOOR 59/74 6/12 - - - 5/5 0/1 0/1
THIRD FLOOR 51/64 12/15 - 0/4 - 5/5 0/1 0/3
FOURTH FLOOR 77/77 8/12 - - - 0/4 0/1 0/3
FIFTH FLOOR 0/33 0/8 0/4 - 0/2 0/3 0/1 0/3
SIXTH FLOOR 0/35 0/5 - - - 0/4 - 0/2
TOTAL 244/363 44/81 0/4 0/4 0/2 17/41 0/8 2/28

PREPARED BY:
GREEN BUILDING
REQUIREMENTS
GREEN BUILDING REQUIREMENTS

ITEM AREA ISSUE/FINDINGS STATUS


1.0 Toilets with PWD - Revise step to be accessible for PWDs - CBCP to provide threshold

2.0 Entrance at Drop-Off - Provide ramp going to main lobby - DONE


3.0 Reflectorized Signage - Provision - by CBCP, for fire exits, labels
of every rooms
4.0 Segregation Area/ - Must be inside the building - Relocated, MSC to submit
MRF - Enclosed proposal (shopdrawing,
- Provide faucet, drains, exhaust and trash costing)
bins
5.0 Aluminium Screen - To be provided for trench drains - By MSC, to be installed later
6.0 Jockey Pump, Fire - Certificate of hydro test - CPS - August 16-17
Pump (needed for Mechanical Permit) - Fire Pump- August 19-20
7.0 Genset - Testing Certificate
8.0 Escalator and Elevator - Testing Certificate TESTING:
- Escalator - August 18- sept 2
- Elevator – August 25 – Sept.15
COMMITMENT DATES
COMMITMENT DATES
M S C ’ s C O M M I T M E N T D AT E S
ITEM PARTICULARS COMMITMENT
1.0 Disinfection (Cistern Tank) - Commitment Date: August 09-10
- Catch-up: August 20
2.0 Turn-over of 4F – Pastor’s Office - Commitment Date: August 13
- Catch-up: August 20
3.0 Completion of Replacement of Wires with - Commitment Date: August 14
Damaged Insulation - DONE
4.0 Installation of Motor Controller and Roughing- - Commitment Date: August 14
Ins for Cooling Tower at Chiller Room - Catch-up Date: August 27
5.0 Delivery and Installation of ECB for VRF’s - Commitment Date: August 14-16
- Catch-up Date: August 20
6.0 Termination of Wires to Fire Pump Controller - Commitment Date: August 14
- Catch-up Date: August 20
7.0 Building Energization - Commitment Date: August 15
- DONE
8.0 Flushing out of STP Prior to Testing Proper - Commitment Date: August 16-17
9.0 Passivation - Commitment Date: August 19-23
COMMITMENT DATES
E Q U I P M E N T S U P P L I E R S ’ C O M M I T M E N T D AT E S

ITEM PARTICULARS CONCERN COMMITMENT


1.0 Cooling Towers and
COWP/CHWP
‒ Start-up of Chilled Water
Powertech insdustrial Sales, Inc. ‒ Commitment Date: August 16-17
Pimps and Condenser Water
Pumps
‒ Testing of Cooling Towers ‒ Commitment Date: August 28-30
2.0 Chillers

‒ Machine Connection to Piping ‒ Commitment Date: August 24-29


‒ Water Filling Dunham Bush Int’l Sales and ‒ Commitment Date: August 30
‒ Load Test at Chillers (1 Chiller Services, Inc.
‒ Commitment Date: Sept. 02-04
per day)
‒ Water Balancing ‒ Commitment Date: Sept.05-07
‒ Air Balancing ‒ Commitment Date: Sept.09-21
COMMITMENT DATES
E Q U I P M E N T S U P P L I E R S ’ C O M M I T M E N T D AT E S

ITEM PARTICULARS CONCERN COMMITMENT


3.0 AHU’s and FCU’s for Chilled ‒ Commitment Date: Sept.02-04
Water System Niagara Industrial Equipment,
‒ Testing of AHU Corp. ‒ Commitment Date: Sept.02-04
‒ Testing of FCU ‒ Commitment Date: Sept.05-07
4.0 VRF and Inverter Split-Type AC
‒ Testing of 9 ACCU’s VRF ‒ Commitment Date: August 19-24
MIT-Air, Inc.
‒ Testing of Remaining ACCU’s ‒ Commitment Date: August 26 –
VRF Sept.06
5.0 Sanitary and Fire/Jockey Pumps
‒ CPS Pump Testing RHP Electromechanical Sales ‒ Commitment Date: August 16-17
‒ Fire Pump and Jockey Pump and Services, Corp.
‒ Commitment Date: August 19-20
Testing
COMMITMENT DATES
E Q U I P M E N T S U P P L I E R S ’ C O M M I T M E N T D AT E S

ITEM PARTICULARS CONCERN COMMITMENT


6.0 Ventilating Fans/ Blowers
‒ Start-up and Testing of ‒ Commitment Date: August 19-24
Niagara industrial Equipment,
FAF/JF/EF at Parking Levels
Corp.
‒ Start-up and Testing of All Other ‒ Commitment Date: August 26 –
Ventilating Fans Sept.06
7.0 Conveying Systems

‒ Testing of Escalators International Elevators and ‒ Commitment Date: August 15-30


Equipment, Inc
‒ Testing of Elevators ‒ Commitment Date: August 19 –
Sept.10
8.0 Sewage Treatment Plant Eco-System Technologies, Inc.
‒ Start-up and Testing of STP ‒ Commitment Date: August 19-21
CONCERNS
CONCERNS
A P P R O VA L O F C H A N G E O R D E R S

C.O. # DESCRIPTION COST CLAIM PROBABLE


DATE CHARGES/ (MSC
SUBMITTED CLAIM)
75 Construction of Clinic at 2nd August 01, 2019 124,779.98
Floor
CONCERNS
M AT E R I A L S B Y O T H E R T R A D E S N E E D E D T O B E C L E A R E D P R I O R T O F I N I S H I N G
AND PUNCHLIST WORKS

WORLD URBAN
CONCERNS
M AT E R I A L S B Y O T H E R T R A D E S N E E D E D T O B E C L E A R E D P R I O R T O F I N I S H I N G
AND PUNCHLIST WORKS

W I L - A N , P O W E R C O R E A N D S P U R W AY
CONCERNS
M AT E R I A L S B Y O T H E R T R A D E S N E E D E D T O B E C L E A R E D P R I O R T O F I N I S H I N G
AND PUNCHLIST WORKS

O S M M AT E R I A L
CONCERNS
M AT E R I A L S B Y O T H E R T R A D E S N E E D E D T O B E C L E A R E D P R I O R T O F I N I S H I N G
AND PUNCHLIST WORKS

MAGNA PRIME
CONCERNS
M AT E R I A L S B Y O T H E R T R A D E S N E E D E D T O B E C L E A R E D P R I O R T O F I N I S H I N G
AND PUNCHLIST WORKS

CITY TRADE & COMANCHE


CONCERNS
A C C U M U L AT E D R U S T S TA I N S O N T I L E S AT U G F - A M P H I T H E AT E R
CONCERNS
F I N I S H I N G O F C H I P P E D W A L L P R I O R T O PA I N T I N G W O R K S
PRIORITY FOR
ENERGIZATION
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
Fans & Blowers

PARKING JF-1 (X14)


Start:08/19/19
End:08/20/19
No. of Days:2
FRESH AIR WELL FAF-1 (X3)
Start:08/19/19
End:08/20/19
No. of Days:2
EXHAUST AIRWELL EF6 (X3)
Start:08/19/19
End:08/20/19
No. of Days:2

UTILITY ROOMS 1&2 EF-1 (X2)

Start:08/19/19 LPB2-B DPLG LVSB


End:08/20/19
No. of Days:2
UTILITY ROOM 3 EF-2
Start:08/19/19
End:08/20/19
No. of Days:2
STP ROOM EF-3
Start:08/19/19
End:08/20/19
ELECTRICITY – No. of Days:2
COOLING -
SUMP PUMP ROOM EF-4
Start:08/19/19
- DONE
End:08/20/19
- DELAYED No. of Days:2
- AHEAD PUMP ROOM EF-5
Start:08/19/19 Start: End:8/15/2019 Start:
- TARGET NEXT WEEK
End:08/20/19 End:TESTED End:TESTED
BASEMENT 02 No. of Days:2 No. of Days: No. of Days:
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
Fans & Blowers

FRESH AIR
FAF-1 (X3)
WELL
Start:08/21/19
End:08/22/19
No. of Days:2
EXHAUST
EF-6 (X3)
AIRWELL
Start:08/21/19
End:08/22/19
No. of Days:2
LPB1-B DPLG LVSB
PARKING JF1 (X14)
Start:08/21/19
End:08/22/19
No. of Days:2
UTILITY
EF-1 (X2)
ROOMS 1&2
Start:08/21/19
End:08/22/19
No. of Days:2
ELECTRICITY –
TOILET TEF-4 (X2)
COOLING -
Start:08/21/19 Start: Start:8/10/2019 Start:
- DONE End:08/22/19 End:TESTED End:8/17/2019 End:TESTED
- DELAYED No. of Days:2 No. of Days: No. of Days:7 No. of Days:
- AHEAD
- TARGET NEXT WEEK
BASEMENT 01
MECHANICAL TESTING AND COMMISSIONING SCHEDULE

Fans & Blowers

PARKING JF1 (X14)


Start:08/23/19
End:08/24/19
No. of Days:2
TOILET ROOM TEF-1 (X1) LPLG-B DPLG LVSB
Start:08/23/19
End:08/24/19
No. of Days:2
TOILET ROOM TEF-4(X2)
Start:08/23/19 Start: End: 08/25/19 Start:
End:08/24/19 End:TESTED End:TESTED
ELECTRICITY –
No. of Days:2 No. of Days: No. of Days:
COOLING -

- DONE
- DELAYED
- AHEAD
- TARGET NEXT WEEK
LOWER GROUND FLOOR
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
Fan Coil Unit, VRF Type

BOOKSTORE AND
FCU-102
COFFEE SHOP

Start:08/19/19
End:08/24/19 LPBC DPA
No. of Days:6

BOOKSTORE AND Panel LVSB


FCU-104 (x4)
COFFEE SHOP

Start:08/19/19 Start: Start:


End:08/24/19 End:TESTED End:TESTED
No. of Days:6 No. of Days: No. of Days:

ACCU-118 PME5F DPMEB


Start:08/19/19 Start:08/07/19 Start: Start:
End:08/24/19 End:08/18/19 End:TESTED End:TESTED
No. of Days:6 No. of Days:12 No. of Days: No. of Days:

FCU-C145 (x4)
Start:08/19/19
MULTIPURPOSE
End:08/24/19 LPMR DPA
ELECTRICITY – RM. 01
No. of Days:6
COOLING - Panel LVSB
FCU-C145 (x4)
- DONE Start:08/19/19 Start: Start:
- DELAYED End:08/24/19 End:TESTED End:
No. of Days:6 No. of Days: No. of Days:
- AHEAD
ACCU-103 (X2) Panel PME6F DPMEB
- TARGET NEXT WEEK Start:08/19/19 Start:08/07/19 Start: Start:
End:08/24/19 End:08/18/19 End: End:TESTED
UPPER GROUND FLOOR No. of Days:6 No. of Days:12 No. of Days: No. of Days:
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
Fan Coil Unit, VRF Type

MULTIPURPOSE
FCU-C104 (x2) LPMR DPA
RM. 02
Start:08/19/19 Start: Start:
Panel LVSB
End:08/24/19 End: End:TESTED
No. of Days:6 No. of Days: No. of Days:
ACCU-104 Panel PME6F DPMEB
Start:08/19/19 Start:08/07/19 Start: Start:
End:08/24/19 End:08/18/19 End:TESTED End:TESTED
No. of Days:6 No. of Days:12 No. of Days: No. of Days:

YOUTH, ADMIN
OFFICE AND AV FCU-W101 (x3)
EQUIP STO. RM.
Start:08/19/19 LPUG DPA
End:08/24/19
No. of Days:6 Panel LVSB
VIP LOUNGE FCU-W102 (x2)

ELECTRICITY – Start:08/19/19 Start:08/07/19 Start:


COOLING - End:08/24/19 End:08/18/19 End:TESTED
No. of Days:6 No. of Days:12 No. of Days:
- DONE ACCU-105 Panel PME6F DPMEB
Start:08/19/19 Start:08/07/19 Start: Start:
- DELAYED
End:08/24/19 End:08/18/19 End:TESTED End:TESTED
- AHEAD No. of Days:6 No. of Days:12 No. of Days: No. of Days:
- TARGET NEXT WEEK
UPPER GROUND FLOOR
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
Fan Coil Unit, VRF Type

PLAY/GATHERIN
FCU-C203
G AREA
Start:08/19/19
End:08/24/19 Panel LPSS2 Panel DPA
No. of Days:6

CLASSROOM 201- Panel LVSB


FCU-S203 (x6)
203
Start:08/19/19 Start:08/12/19 Start:
End:08/24/19 End:08/13/19 End:TESTED
No. of Days:6 No. of Days:2 No. of Days:

ACCU201 PME5F DPMEB


Start:08/19/19 Start:08/07/19 Start: Start:
End:08/24/19 End:08/18/19 End:TESTED End:
No. of Days:6 No. of Days:12 No. of Days: No. of Days:

CLASSROOM 204-
FCU-S203 (x6) LPSS2 DPA
206

Start:08/19/19 Start:08/12/19 Start: Panel LVSB


ELECTRICITY – End:08/24/19 End:08/13/19 End:TESTED
No. of Days:6 No. of Days:2 No. of Days:
COOLING -
ACCU204 PME5F DPMEB
Start:08/19/19 Start:08/07/19 Start: Start:
- DONE
End:08/24/19 End:08/18/19 End:TESTED End:
- DELAYED No. of Days:6 No. of Days:12 No. of Days: No. of Days:
- AHEAD
- TARGET NEXT WEEK
2ND FLOOR
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
Fan Coil Unit, VRF Type

BOARD ROOM
AND CHOIR & AV FCU-C402 (x4) LPPOF DPB
RM.
Panel LVSB
Start:08/19/19 Start:08/12/19 Start:
End:08/24/19 End:08/13/19 End:TESTED
No. of Days:6 No. of Days:2 No. of Days:
ACCU 409 PME6F
Start:08/19/19 Start:08/07/19 Start:
End:08/24/19 End:08/18/19 End:TESTED
No. of Days:6 No. of Days:12 No. of Days:

MEETING RM
1&2 AND FCU-W450 (x2) LP4FB
DISCIPLESHIP
Start:08/19/19 Start:08/12/19
End:08/24/19 End:08/13/19
No. of Days:6 No. of Days:2
MEETING RM
1&2 AND FCU-W450 (x6) DPB
DISCIPLESHIP
Panel LVSB
Start:08/19/19
End:08/24/19 LPPOF
No. of Days:6
ELECTRICITY –
COOLING - PRAYER ROOM
FCU-W401 (x3)
AND OFFICES

- DONE Start:08/19/19 Start:08/12/19 Start:


- DELAYED End:08/24/19 End:08/13/19 End:TESTED
No. of Days:6 No. of Days:2 No. of Days:
- AHEAD ACCU 409 PME6F DPMEWH
- TARGET NEXT WEEK Start:08/19/19 Start:08/07/19 Start: Start:
End:08/24/19 End:08/18/19 End:TESTED End:TESTED
4TH FLOOR No. of Days:6 No. of Days:12 No. of Days: No. of Days:
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
CHLLERS (WATER COOLED TYPE)

WCH-1 X3 DPMEWH LVSB


Start:09/02/19 Start: Start:
End:09/04/19 End:TESTED End:TESTED
No. of Days:3 No. of Days: No. of Days:

COOLING TOWERS

CT-1 X3 PME6FC DPMEWH LVSB


Start:08/28/19 Start:08/07/19 Start: Start:
End:08/30/19 End:08/14/19 End:TESTED End:TESTED
No. of Days:3 No. of Days:8 No. of Days: No. of Days:
Catch-up: Aug.20
CHILED & CONDENSER WATER PUMPS

CHWP-1 (X3)
Start:08/16/19
End:08/17/19 PME6FC DPMEWH LVSB
No. of Days:2
ELECTRICITY –
COOLING - COWP-1 (X3)
Start:08/16/19 Start:08/07/19 Start: Start:
- DONE End:08/17/19 End:08/14/19 End:TESTED End:TESTED
- DELAYED No. of Days:2 No. of Days:8 No. of Days: No. of Days:
- AHEAD Catch-up: Aug.20
- TARGET NEXT WEEK
ROOF DECK
MECHANICAL TESTING AND COMMISSIONING SCHEDULE
FIRE PROTECTION

FP-01
Start:08/19/19
End:08/20/19 PFP ATS LVSB
No. of Days:2
JP-01
Start:08/19/19 Start:08/17/19
End:08/20/19 End:08/18/19
No. of Days:2 No. of Days:2

PLUMBING WORKS

CPS PUMPS
(triplex)
Start:08/16/19
End:08/17/19
No. of Days:2 PSE DPMEA

UGF SEWAGE SUMP


HALLWAYS PUMP (duplex)

Start:08/16/19 End:08/15/19 Start:


End:08/17/19 End:TESTED LVSB
No. of Days:2 No. of Days:

UGF ELEVATOR PIT


LPB2B DPLG
ELECTRICITY – HALLWAYS SUMP PUMP
COOLING - Start: End:8/15/2019
End:TESTED
- DONE No. of Days:
- DELAYED
STP Power
- AHEAD PSE DPMEA
provision
- TARGET NEXT WEEK Start:08/16/19 End:8/15/2019 Start: Start:
End:08/17/19 End:TESTED End:TESTED
FIREPRO AND PLUMBING No. of Days:2 No. of Days: No. of Days:
PROGRESS
PHOTOS
PROGRESS PHOTOS
ELECTRICAL WORKS

T E S T I N G O F L I G H T I N G F I X T U R E S AT B A S E M E N T 0 1
PROGRESS PHOTOS
ELECTRICAL WORKS

T E S T I N G O F L I G H T I N G F I X T U R E S AT L G F
PROGRESS PHOTOS
ELECTRICAL WORKS

I N S TA L L AT I O N A N D T E S T I N G O F L I G H T I N G F I X T U R E S AT
UGF - TOILET
PROGRESS PHOTOS
ELECTRICAL WORKS

HVSG AND TRANSFORMER


PROGRESS PHOTOS
MEPFS WORKS

MODIFIED EXHAUST PIPING


PROGRESS PHOTOS
CEILING WORKS

I N S TA L L E D C E I L I N G B O A R D S AT 3 R D F L O O R - C W H
PROGRESS PHOTOS
CIVIL WORKS

I N S TA L L E D R O L L - U P D O O R S A L O N G E . L O P E Z A N D
S A M A R AV E .
PROGRESS PHOTOS
CIVIL WORKS

F I N I S H E D S T E P S G O I N G T O S TA G E AT 3 R D F L O O R - C W H
PROGRESS PHOTOS

EXTERIOR VIEW OF THE BUILDING ALONG EL JARDIN


PROGRESS PHOTOS

EXTERIOR VIEW OF THE BUILDING ALONG MONTEIRO RESIDENCE


PROGRESS PHOTOS

EXTERIOR VIEW OF THE BUILDING ALONG E.LOPEZ


PROGRESS PHOTOS

E X T E R I O R V I E W O F T H E B U I L D I N G A L O N G S A M A R AV E .
PROGRESS PHOTOS

PERSPECTIVE VIEW OF THE BUILDING