Beruflich Dokumente
Kultur Dokumente
Group Members:
1. Jafar Ghori (X012-18)
2. Manish Kumar (X015-18)
3. Ujjwal Kumar (X021-18)
4. Shyam Kumar (X019-18)
5. Rohan Kumar (X017-18)
6. A Anabarasu (X004-18)
Project Destiny Case Questions
as well as MS project.
2. Calculate the Early start, Early Finish, Late Start, Late Finish.
Mr. Brent Collver, President and Chief executive officer of Romet Limited was preparing for the “Project Destiny” team
meeting on Friday morning i.e April 27, 2018. He had just finalized the architectural design and layout for the
company’s new plant and was reviewing the activities required to complete the move.
As per Brent Collver, Romet is a growing company and now it needs a larger facility. The company have leased a 75,000
sq.ft plant on Timberlea Bolulevard, about two blocks from current location on Matheson Boulevard.
The new building will give an additional 20,000 sq.ft and the layout will provide for improved material flow.
He wanted to have the move completed before the Christmas shutdown, which starts on December 21, 2018
This means that the total time for project move will be from April 27 to December 21, i.e ~ 34 weeks.
1. Project network diagram for plant relocation
2. Calculating the Early start, Early Finish, Late Start, Late Finish
Estimated
Early Early Late Late
Activity Description Immediate Time Slack
Start Finish Start Finish
Predecessor (Weeks)
A Finalize lease - 4 0 4 0 4 0
B Obtain permits A 10 4 14 4 14 0
C Zoning approval A 8 4 12 6 14 2
D Electrical and pneumatic construction B,C 16 14 30 17 33 3
E Quality/supervisor pod construction B,C 16 14 30 14 30 0
F Anodizing line installation B,C 14 14 28 19 33 5
Machine shop equipment removal and
G reinstallation D,F 2 30 32 33 35 3
Climate controlled proving room
H construction E 4 30 34 39 43 9
I Assembly relocation G 1 32 33 35 36 3
J Paint line relocation I 6 33 39 36 42 3
K Auxilary equipment J 1 39 40 42 43 3
L Office construction E 12 30 42 30 42 0
M Information technology services E 12 30 42 30 42 0
N Office move L,M 1 42 43 42 43 0
O Project end H,K,N - 43 43 43 43 0
3. Finding the critical path of the network
# Path Time (Weeks) Critical path
1 ABDGIJKO 40
2 ABEHO 34
3 ABELNO 43 Critical path (Longest time)
4 ABEMNO 43 Critical path (Longest time)
5 ABFGIJKO 38
6 ACDGIJKO 38
7 ACEHO 32
8 ACELNO 41
9 ACEMNO 41
10 ACFGIJKO 36
Here we have multiple critical path, hence selecting the individual critical path and
performing crashing activity
Critical path before crashing
Selecting critical path -1 : A B E L N O
Path A B F G I J K O Path A C E L N O
Path A C E M N O
Path A C D G I J K O
Path A C F G I J K O
As Brent Collver,
o I would take the maximum benefits of state of the art equipment and a strong team
image what Romet Limited have by completing the project destiny before December
21, 2018.
o I would try to achieve zero downtime & no disruption in the customer service.
o Strategic priorities would be centre as customer satisfaction & product innovation
o I would focus more on deploying good skilled manpower for pod construction &
electrical and pneumatic construction in 12 weeks.
o I would focus on office construction and negotiate the contract for construction in 5
weeks through extra manpower.