Beruflich Dokumente
Kultur Dokumente
1
Production Data
Job A Job B
Due date: week 44 Due date: week 38
Operation WC Time Operation WC Time
(hours) (hours)
I 3 160 I 3 40
II 4 120 II 2 200
2
Scheduling Plan – Block Schedule
Operation Job A Job B
II 3 38 5 37
Interoperation 2 40 2 39
III 5 45 2 41
Inspect and 1 46 1 42
Deliver
3
Review The Schedule
• Calculate the CR ratio for those jobs:
44−28 16
CR (A) =160 120 200 = = 1.33
+ + 12
40 40 40
38−28 10
CR (B) =40 200 80 = = 1.25
+ + 8
40 40 40
4
Load and Capacity Data
Job A Job B
II 4 120 40 2 200 40
III 1 200 40 4 80 40
5
Gantt Chart
WEEKS
WC 32 36 40 44
1 Deliver A
39 44 45
2 B2
36
3 B1 A1
29 30 34
4 A2 B3 Deliver B
35 38 40 41
All the jobs are late
6
Aligning Completion Times and Due Date
• Lead time can be reduced by decreasing interoperation time.
Interoperation consists of wait time, move time and queue
time. The queue time can be reduced by increasing the
capacity of critical work or reducing the workload to specific
work centers.
• In short term, capacity can be increased by using overtime or
additional shifts, or subcontracting operations.
• Other technique can be applicable, such as: overlaping or lot
splitting.
• Operation splitting is another way to reduce the lead time. For
example: assigning more workers to the job in manual work
station, or the job is processed in several parallel machines
7
Improvement in Work Center 1 and 2
• By adding forty hour capacities at machine work center 1 and
2, can those jobs complete on time?
Job A Job B
II 4 120 40 2 200 80
III 1 200 80 4 80 40
8
Revised Scheduling
• Calculate the CR ratio for those jobs:
44−28 16
CR (A) =160 120 200 = = 1.68
+ + 9.5
40 40 80
38−28 10
CR (B) =40 200 80 = = 1.82
+ + 8
40 80 40
9
Gantt Chart
WEEKS
WC 32 36 40 44
1 A3 Deliver A
38 40.5 41.5
2 B2
35 37.5
3 A1 B1
29 33 34
4 A2 Deliver B
34 37 38.5 40.5 41.5
Job A finishes in the middle of week 42, that is, the job A can be done
before the due date, but job B is still late by approximately four weeks.
10
Revised the Schedule
• If it is employed the lot splitting or overlapping
techniques for job A, determine is it possible all the
jobs to meet the due date?
• If not, you suggest an alternative method to solve
this problem
11
Revised Schedule
• Splitting the job A does not hasten the completion of job B in
any work center.
• Try the SPT rule at machine center 3.
WEEKS
WC 32 36 40 44
1 Deliver A
40.5 43 44
2 B2
31 33.5
3 B1 A1
29 30 34
4 B3
34.5 36.5 39.5
37.5 Deliver B
12
Manufacturing Lead Time
Move
Move
Queue Setup Run Wait
13
Cycle Time
• “The length of time from when material
enters a production facility until it exits”
– APICS Dictionary 11th Edition
14
Example Problem
= 34 hours, 45 minutes
15
Scheduling Techniques
• Forward Scheduling • Backward Scheduling
– Start when the order is – Uses MRP logic
received – Schedule last operation
– May finish early to be complete on the
– Used to determine the due date
earliest completion date – Schedule previous
– Determine promise operations back from
dates the last operation
– Builds inventory – Reduces inventory
16
Forward and Backward Scheduling:
Infinite Load
Forward Scheduling
Material 1st 2nd 3rd
Ordered Operation Operation Operation
Backward Scheduling
17
Example Problem
Backward Scheduling
• A company has an order for 50 brand X to be delivered
on day 100
• Only one machine is available for each operation
• The factory works one 8 hour shift 5 days a week
• The parts move in one lot of 50
18
Example Problem Answer
Part A
OP 10 OP 20
X
Part B Assembly
OP 10
85 90 95 100
Working Days
19
Operation Overlapping
• The next operation is allowed to begin
before the entire lot is completed
• Reduces the manufacturing lead time
• Order is divided into at least two transfer
lots
Operartion A
SU Lot 1 Lot 2
T T Transfer Time
SU Lot 1 Lot 2
Operation B
20
Operation Overlapping
• Costs involved:
• Handling costs between work centers
• May increase queue and wait for other orders
• Idle time if the second batch doesn’t arrive in
time
21
Size of the Transfer Batch
SUA = Set up time operation A
SUB = Set up time operation B
RTA = Run time per piece operation A
RTB = Run time per piece operation B
QT = Total order size
T1 = size of the first transfer batch
T1 = QT x RTA - SUB T2 = QT - T1
RTA + RTB
22
Size of the Transfer Batch
• If the second operation is slower than the first
make the first transfer batch small
– i.e. get the slower machine started early
23
Example Problem
Operartion A
0 30 730 1,000 (Minutes)
30 70 x 10 = 700 30 x 10 = 300
T T Transfer Time
1,010
25
Operation Splitting
One Machine
SU Run
SU Run
26
Load Leveling
• Load Report
• Tells PAC the current and upcoming load on a
work center
• Based on standard hours of operation for each
order
27
Load Report
Work Center: 10 Available Time: 120 Hours per week
Description: Lathes Efficiency: 115%
Number of Machines: 3 Utilization 80%
Rated Capacity: 110 standard hours / wk
Week 18 19 20 21 22 23 Total
Released
80 30 0 0 315
Load 105 100
60 80 130 80 350
Planned Load
Total Load 105 100 140 110 130 80 665
Rated
110 110 110 110 110 110 660
Capacity
(Over) /
Under 5 10 (30) 0 (20) 30 (5)
Capacity
28
Bottlenecks