www.huawei.com
5. Integration Verification
6. FAQs
Page2
du LTE Project Network Topology
Page 3
Performing the E NodeB Power-On Check
After all devices are installed, you need to check the power-on status of the BBU and RRU.
Figure 1 BBU power-on check process
Checking the Power-On Status of the RRU
BBU3900 Slot Allocation
Before we proceed with the software commissioning please make sure the
Hardware are inserted as per the design and make sure the board types are
as mentioned in design.
Local Commissioning Modes
Note: Please ensure to download and activate the Digital certificates before
Proceeding with Commissioning.
LMT Commissioning Procedure- Digital Certificates
Preparation
Procedure
Download the operator's root CA certificate to the eNodeB by running the DLD
CERTFILE command.
DLD CERTFILE:IP="192.168.0.50",USR="admin",PWD="*****",SRCF="Huawei
RadioSubCA.crt",DSTF="Huawei RadioSubCA.cer",CT=TRUSTCERT;
LMT Commissioning Procedure- Digital Certificates
Preparation
2.Downloading the Digital Certificate on the LMT
Procedure
Download the operator's root CA certificate to the eNodeB by running the DLD
CERTFILE command.
DLD
CERTFILE:IP="192.168.0.50",USR="admin",PWD="*****",SRCF="CentralElementSu
bCA(20111206).p7b",DSTF="CentralElementSubCA(20111206).p7b",CT=TRUSTCE
RT;
LMT Commissioning Procedure- Digital Certificates
Preparation
2.Downloading the Digital Certificate on the LMT
Procedure
Add the operator's root CA certificate by running the ADD TRUSTCERT.
ADD TRUSTCERT:CERTNAME="Huawei RadioSubCA.cer";
LMT Commissioning Procedure- Digital Certificates
Preparation
2.Downloading the Digital Certificate on the LMT
Procedure
Add the operator's root CA certificate by running the ADD TRUSTCERT.
ADD TRUSTCERT:CERTNAME="CentralElementSubCA(20111206).p7b “;
LMT Commissioning Procedure---System
Requirements
LMT Commissioning Procedure- Connecting PC to Main
UMPT Board
Ethernet cable LMPT: The Ethernet cable directly connects the laptop to the
eNodeB.
Fill in the User Name, Password, and Verify Code boxes. Set User Type to
Local.
LMT Commissioning Procedure---FTP Server Setup
Configuring the FTP Server Context:
Because the eNodeB software, data configuration file, and license are downloaded
from the FTP
server to the LMT, ensure that the FTP server has been configured before the
download.
LMT Commissioning Procedure---FTP Server
Setup
Procedure for FTP setup
Step 1 From the LMT main menu, click the Software Management tab. The Software
Management tab page is displayed.
Step 2 In the navigation tree, double-click FTPServer Configuration. The FTPServer
Configuration pane is displayed, as shown
3. Set User name, Password, and Working directory for the FTP server. The default user
name and password are admin. Working directory must be set to the directory where the
software and data configuration file are saved. The default transmission security mode isBoth.
4. Click OK.
LMT Commissioning Procedure---FTP Server Setup
Procedure for FTP setup (Continue….)
Step 5 Save the FTP server configuration on the LMT main window.
1.On the LMT, click Software Management. The Software Management tab page is
displayed.
2. On the FTP Server Configure tab page, set IP address for the FTP server.
3. Enter User name and Password based on the settings in Step 4.3. The default name
and password are admin.
Procedure
1. In the MML window on the LMT, run the LST VER command to query the active eNodeB
software version.
LMT Commissioning Procedure---Script and License
Downloading
Download and activate the eNodeB software and data configuration file
using the GUI or MML commands.
Using GUI
a.On the LMT, click Software Management. The Software Management dialog box is displayed.
b.In the navigation tree, double-click Download and Activate Software. The Download and Activate
Software window is displayed,
C. Select tasks to be performed accordingly and set the parameters related to the tasks.
Local Commissioning Using a USB Flash Drive
Commissioning Procedure
This section describes how to perform local eNodeB commissioning using a Universal Serial Bus
(USB)
Prerequisites
* The eNodeB software package and data configuration file are available.
*The commissioning license is ready if you need to load and activate the license file using the USB
flash drive.
•The USB flash drive and commissioning files have been scanned by using the antivirus software and
no virus was detected. The commissioning files include the software package,data configuration file,
and license file.
USB flash drive
* The USB flash drive is equipped with an indicator that indicates the data transmission status.
* Capacity ≥ 256 MB
*The USB flash drive must not provide any additional functions,such as encryption, virus scanning,
and bootstrapping. In addition, it cannot be an MP3 player, MP4 player, or smartphone.
*The USB flash drive used for commissioning cannot be used for other purposes
USB Commissioning Procedure
Pre check Points
1. Obtain the eNodeB software and files for automatic eNodeB deployment.
NOTE
* The eNodeB software package is ready, and can be downloaded from Huawei Engineer.
The default configuration file (Precfg.ini) is provided in the software package.
*The name of the data configuration file must be CFGDATA.XML. The file name is case-sensitive.
2. Save the required files to the following paths of the USB flash drive, depending on the specific
scenarios, shown in Table 2 (The save path is case-sensitive and cannot be changed.)
USB Commissioning Procedure-
Step 1 Check whether the eNodeB is powered on. If it is not powered on, power on the
eNodeB. If it
is already powered on, go to Step 2.
NOTE
Ensure that the RRU is powered on and the common public radio interface (CPRI) connections
are correct
before you power on the eNodeB. Check for faults by monitoring the CPRI indicator status on
the LBBP
after the eNodeB is powered on. For details, see Checking the Status of Indicators.
Step 2 When the eNodeB operates properly, insert the USB flash drive into the USB port
on the
BBU3900 main control board. If an LMPT is used, the USB port is shown in Figure 3-15; if an
UMPT is used, the USB port is shown in Figure
USB Commissioning Procedure
Step 3 Wait for the eNodeB to automatically upgrade the software and data configuration file.
If the download or activation fails, commission the eNodeB by updating the software and data
configuration file in the USB flash drive or using a new USB flash drive.
If the download or activation still fails, perform the local eNodeB commissioning on the LMT.
When the software and data configuration file are being upgraded, the normal status of the
indicators on the USB flash drive and main control board is shown .
Integration Verification
Integration Verification
LST IPRT
Page29
Integration Verification
Ping test till the router gateway to verify the reachabillty till routers
Integration Verification
2.Software verification
DSP IKESA
Integration Verification
Checking the Operating Status of the eNodeB on the LMT
Procedure
1.On the LMT, click Self-Test. On the displayed Self-Test tab page, a man-machine language (MML) command
script with the complete parameter settings is automatically imported to the command area.
2.Click Execute. The execution result is displayed in the area below Execute.
NOTE:
If all items pass the check, the eNodeB operates properly. Otherwise, check for active alarms and clear them. If
all active alarms are cleared but the fault persists, contact Huawei for technical support.
FAQs
1. How to check physical link status is up?
To check the port Attribute should be “Fiber” or “Copper” based the real
connection.
Page34
FAQs
2. What’s the issue Macro site 2*2 MIMO cell setup failure?
For Macro site, due to low speed of SFP module, 2*2 MIMO cells are
failed to setup.
o Check Optical model type @ eNB and RRU sides.
BOM#34060365 MultiMode SFP required
0 0 3 Head 2.5
0 60 0 0 2.5
(Number of results = 2
Notes: For IBS sites, SFP is required 1.25Gbit/s to setup SISO cell.
Page35
FAQs
3. What kindly of files need to be well-prepared to integrate one new LTE site?
o NodeB Script file named as “NodeBCFG.xml” (It will be sent through email)
o IP Plan Database in LLD file “du LTE Expansion Project Low Level Design
V3.0-Wireless (18th,Oct).xlsx”
Page36
Huawei Support Contact
Page37
Thank You