2x25 MW
PROJECT PROGRESS
MILESTONE PROJECT (Status up to April 2015)
Boiler Steam Drum Lifting February 2016 April 2016 EPC Power Plant
Turbine Generator On site February 2016 April 2016 EPC Power Plant
Transmision Line & Substation ready September 2016 September 2016 Substation 150 KV &
operation Transmission (15km)
Back Feeding September 2016 September 2016 EPC Power Plant
Control Room Fully Operation October 2016 October 2016 EPC Power Plant
Demin Water Production October 2016 Nov 2016 EPC Power Plant
First Firing Boiler Februari 2017 April 2017 EPC Power Plant
M0 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26
Batch 1
Boiler Steel Structure On site (Oct’15)
On Site Batch 4 :
1. Coal crusher
2. Draft Fan(Induced draft fan,primary air
Batch 3
fan,secondary air fan)
3. Electrostatic precipitator
Turbine & Generator foundation bolts, plates,
4. Coal feeder Steel Structure unit 1 & 2 On site (Dec’15)
5. Feed pump
6. High pressure heater
7. Deaerator
Batch 4
8. Transformers Boiler Unit 2 On site (Jan’16)
9. Circulation-water pump
10. Condensate pump
11. Overhead crane Turbine house Batch 5 Turbine Generator unit 1 On Site (Feb’16)
On Site Batch 5 :
1. Coal handling system
2. Mechanical cooling tower
3. Coal Unloader
4. Seawater desalination Plant Batch 6
5. Chemical water treatment system On Site Batch 6 :
6. Vacuum pump 1. Air compressor
7. Ash handling system 2. Turbine bypass
8. Slag removal system 3. Rubber ball cleaning device
9. HP feed-water/steam pipe 4. DCS system
10. Hoisting Equipments Batch 7 5. HP fluidization fan
11. DC system Turbine Generator unit 2 On site (Apr’16) 6. Heating Ventilation Air Conditioning
7. Continuous Emission Monitoring
12. Electrical protection system
13. 6kV switch cabinet On Site Batch 7 System
14. 6kV switch cabinet delivery 1. Fire alarm system 8. Fuel oil pump house equipments 3.
15. PC&MCC cabinet 2. Chemical laboratory equipment Communication
16. HP&LP electrical panel cabinets 3. Thermal instrusments 9. Emergency diesel generator
17. Medium pressure and low pressure pipe (in 4. Motorized valve of CW system 10. Thermal control system
batches) 11. Plant & Demestic sewag treatment
18. Valves (in batches) device
19. Cable & Cable tray 12. Hydraulic fire system
CONSTRUCTION ACTIVITIES