MAMUJU COAL FIRED STEAM POWER PLANT

2x25 MW

PROJECT PROGRESS
MILESTONE PROJECT (Status up to April 2015)

MILESTONE Target Unit #1 Target Unit #2 Status Remark


Site Development (Cut & Fill) May 2015 May 2015 Site Preparation

Commencement Of Date May 2015 May 2015 EPC Power Plant

First Piling July 2015 July 2015 EPC Power Plant

Boiler on Site Dec 2015 Januari 2016 EPC Power Plant

Boiler Steam Drum Lifting February 2016 April 2016 EPC Power Plant
Turbine Generator On site February 2016 April 2016 EPC Power Plant

Transmision Line & Substation ready September 2016 September 2016 Substation 150 KV &
operation Transmission (15km)
Back Feeding September 2016 September 2016 EPC Power Plant

Control Room Fully Operation October 2016 October 2016 EPC Power Plant

Demin Water Production October 2016 Nov 2016 EPC Power Plant

Hydrotest Boiler October 2016 Dec 2017 EPC Power Plant

January 2016 February 2017 EPC Power Plant


Coal handling System Ready

First Firing Boiler Februari 2017 April 2017 EPC Power Plant

Steam Blow March 2017 May 2017 EPC Power Plant

April 2017 June 2017 EPC Power Plant


First Synchrone
April 2017 June 2017 EPC Power Plant
RR

May 2017 July 2017 EPC Power Plant


PT

May 2017 July 2017 EPC Power Plant


COD
ENGINEERING ACTIVITIES
Status 29 April 2015 (Before Consinyering Meting)

Status 11 Mei 2015 (after Consinyering Meeting)


Schedule Equipment On Site
2015 2016 2017
Ma Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Ma Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Ma Jun jUL
y y y

M0 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26

Batch 1
Boiler Steel Structure On site (Oct’15)

Batch 2 Boiler Unit 1 On site (Dec’15)

On Site Batch 4 :
1. Coal crusher
2. Draft Fan(Induced draft fan,primary air
Batch 3
fan,secondary air fan)
3. Electrostatic precipitator
Turbine & Generator foundation bolts, plates,
4. Coal feeder Steel Structure unit 1 & 2 On site (Dec’15)
5. Feed pump
6. High pressure heater
7. Deaerator
Batch 4
8. Transformers Boiler Unit 2 On site (Jan’16)
9. Circulation-water pump
10. Condensate pump
11. Overhead crane Turbine house Batch 5 Turbine Generator unit 1 On Site (Feb’16)
On Site Batch 5 :
1. Coal handling system
2. Mechanical cooling tower
3. Coal Unloader
4. Seawater desalination Plant Batch 6
5. Chemical water treatment system On Site Batch 6 :
6. Vacuum pump 1. Air compressor
7. Ash handling system 2. Turbine bypass
8. Slag removal system 3. Rubber ball cleaning device
9. HP feed-water/steam pipe 4. DCS system
10. Hoisting Equipments Batch 7 5. HP fluidization fan
11. DC system Turbine Generator unit 2 On site (Apr’16) 6. Heating Ventilation Air Conditioning
7. Continuous Emission Monitoring
12. Electrical protection system
13. 6kV switch cabinet On Site Batch 7 System
14. 6kV switch cabinet delivery 1. Fire alarm system 8. Fuel oil pump house equipments 3.
15. PC&MCC cabinet 2. Chemical laboratory equipment Communication
16. HP&LP electrical panel cabinets 3. Thermal instrusments 9. Emergency diesel generator
17. Medium pressure and low pressure pipe (in 4. Motorized valve of CW system 10. Thermal control system
batches) 11. Plant & Demestic sewag treatment
18. Valves (in batches) device
19. Cable & Cable tray 12. Hydraulic fire system
CONSTRUCTION ACTIVITIES

I. Current Month Activities


1. Pekerjaan EPC Project PLTU 2x25 MW
a. Soil Investigation (Soil test)
•CHEC telah Memulai Pekerjaan Soil Test pada tanggal 26 Februari 2015.
Area Jumlah Rencana titik Soil Test Jumlah Aktual titik Soil Test Keterangan

BTG & Chimney 43 43 Done


BOP 24 11
Oil Tank 5 1
Coal Yard 28 23
Building 12 12 Done
Jetty 22 22 Done
Ash Yard 9 9 Done

b. Pekerjaan Temporary Facility dan Batching Plant


• Persiapan Pengiriman dan Install

2. Pekerjaan EPC Project 150KV Substation and Transmission Line (15KM)


a.Land Acquisition (Pembebasan Lahan) :
Proses pembebasan lahan Transmisi Line (15KM) bekerja sama dengan PT PLN UIP XIII dan Pemda Mamuju,
target total penyelesaian pembebasan lahan pada bulan Juli 2015.

b. Target Ready to Supply : September 2016