Beruflich Dokumente
Kultur Dokumente
power procurement
1
AGENDA
2
CONTEXT FOR TODAY’S DISCUSSION
3
INDIAN ELECTRICITY REGULATIONS ENVISAGE A COMPETITIVE MARKET
• “Under the competitive bidding route, the Commission perceives its function of
regulating tariffs to primarily be the scrutiny and approval of the process adopted for
competitive bidding, with a view to ensure that competitive conditions do prevail”
CERC order dated 9th March 2000 on a petition filed
by Power Trading Corporation Ltd.
4
THE TASK FORCE REPORT ALSO SEEKS TO ENHANCE COMPETITION IN
THE SECTOR USING COMPETITIVE BIDDING
* Page 289 – Report of the Task force on Power Sector Investment and Reforms (Feb 2004 Volume I) 5
OBJECTIVES OF TODAY’S DISCUSSIONS
6
AGENDA
7
POWER PROCUREMENT COST IS A LARGE PORTION OF THE TOTAL
COST OF SUPPLY
Paise/Kwh, 2001-02
469
106
365
357 349
98
Other cost 136 119
363
267
Power procurement cost 221 230
4000
Peak
3500
3000 Intermediate
2500
2000 Baseload
1500
1000
500
0
0% 20% 40% 60% 80% 100%
Hours of the year
Source: Delhi Electricity Regulatory Commission order on Delhi Transco ARR for 2002-03 and 2003-04 10
POWER MARKET IS REQUIRED TO EVOLVE TO A NEW STRUCTURE
• Single buyer model - SEB/transco pools • Multiple buyer model (e.g., each
distribution utility requirements to distribution company procuring for its
procure power own requirements)
• Primarily long duration contracts • Suitable mix of long, medium and short
term contracts
11
TO REACH THE REQUIRED STRUCTURE, IT IS IMPERATIVE TO ACHIEVE
COMPETITION IN GENERATION
What needs to be achieved as the
market transitions to full competition?
• Reduce inefficiencies in generation plants
to enable low cost power production
12
AGENDA
13
GUIDING PRINCIPLES FOR COMPETITIVE BIDDING
14
AGENDA
15
GUIDELINES SHOULD COVER PROCUREMENT BY VARIOUS ENTITIES
Buyers Sellers
Existing generating
Distribution stations
Licensee
Procurement
New generating
transaction stations
16
GUIDELINES SHOULD COVER BOTH GENERATION AND NEW
TRANSMISSION CAPACITY
Should guidelines
Procurement category cover it? Rationale
• Generation
– Capacity May be • Yes • This would form the bulk of the
baseload/Peak power procurement bids; hence it is
– Energy or off peak imperative that the guidelines cover
these
• Transmission capacity
– Existing • Not required • Rules for open access on
• Firm May be entire transmission lines already well
day/part day defined (e.g., transmission service
• Non-firm
charge bidding)
– Setting up • Yes • New capacity addition not based on
new capacity competitive bidding so far, but lends
itself to the process quite naturally
• Ancillary services
– Spinning reserves • Not initially • The concept of ancillary services
– Reactive Power not well developed yet
– Harmonics etc. • In future as market matures
guidelines may be expanded to
include these as well
17
TODAY, DISCOMS/TRANSCOS PROCURE POWER MAINLY THROUGH
LONG TERM BILATERAL CONTRACTS
Description/Details
• Generally 15-25 year contracts. New capacity may be added if needed
Long term
• Capacity added in three ways -
– Self generation – Allocation from central – Independent power
(SEB owned generating stations ; producers; Bid/MOU route
generators); capacity CERC determines for projects; CERC/SERC
cleared by SERC as tariffs vets the tariff
required
Medium No clear process currently for bridging medium term requirements (i.e. more
term than one year and less than 15 year duration)
• Upto one year duration contracts; (form small part of total power procured)
Short term
• SEBs propose power purchase from third parties in their ARRs, prior to actual contract
• Some SERCs have taken a hands off view on these bids as long as the total annual
power purchase cost remains within budget
18
PROPOSED GUIDELINES WOULD COVER POWER PROCUREMENT PHASE
Discom forecasts its power Covered by
requirements for Regulator approves competitive bidding
Discom procures
• Long term forecasted power guidelines
• Medium term need power
• Short term
Pricing mechanism
Traders
Competitive
bidding • Competitive bidding
Generators
Discom power
procurement
Pricing mechanism
• Competitive bidding
by Trader
19
IN TERMS OF DURATION, GUIDELINES WOULD COVER ALL
PROCUREMENT CONTRACTS OUTSIDE THE DAY AHEAD AND REAL-TIME
MARKET Proposed scope
of guidelines
21
BIDDING PROCESS WOULD START WITH THE REGULATOR APPROVING
THE DEMAND FORECAST FOR THE DISTRIBUTION COMPANIES
Path 1
Using standard
bid documents
Demand forecast for Regulatory
approval of Procurement
short / medium / process Path 2
long term by discom forecast
Using non-standard
bid documents
22
PROPOSED POWER PROCUREMENT BIDDING PROCESS IF STANDARD
DOCUMENTS ARE USED
Post bid
negotiations
23
PROPOSED POWER PROCUREMENT BIDDING PROCESS IN CASE OF
DEVIATIONS FROM STANDARD BIDDING DOCUMENTS
Regulatory Prepare
Requirement Shortlist
clearance of bidding Initiate RFQ A
definition bidders
forecast documents
Iterations on
development of
bid documents
Seek regulatory
approval
Regulatory
Post bid
approval if
negotiations Even though active
required
regulatory approval
needed in only certain
stages, but the regulator is
• Any modifications
always kept informed of
suggested by bidders, or
all developments
due to any other reasons to
be approved by regulator –
possibly over several
rounds of iterations
24
IN THE RFQ STAGE, BIDDERS SHOULD BE SCREENED ON THE BASIS OF
AN ARRAY OF METRICS
Technical metrics Past record Financial metrics
25
FOR MEDIUM/LONG TERM CONTRACTS, AT RFP STAGE, BIDS SHOULD
BE SCREENED BASED ON NON PRICE EVALUATION PRIOR TO PRICE
COMPARISONS
Element for
evaluation Details
26
BUYER SHOULD SPECIFY THE BID STRUCTURE IN DETAIL
Discussed further
• Energy
What is being bid
for? • Capacity
• Percentage of load (varying)
• No part bidding
Elements Whether part bidding
of a bid is allowed?
• Part bidding allowed
• Part bidding allowed in multiples of
some pre-specified minimum bid unit
(preferred option)
27
BID PRICING STRUCTURE WOULD USUALLY EMPLOY A TWO PART TARIFF
Aspect Details
* Index might be a reference fuel price, or price of a basket of fuels, or some other index
Note: Medium term contracts could follow a pricing mechanism similar to long term contracts with simplified indices 28
FOR SHORT TERM CONTRACTS, THREE ASPECTS SHOULD BE
MODIFIED TO SPEED UP THE PROCESS
Discussed further
Aspect Details
• Bid process may be started (public notification stage) upto a few weeks
Short lead before the actual requirement of the contract
times
• Thus mostly traders and existing generators would likely bid for these
29
EMPANELMENT OF BIDDERS - DETAILS
30
INTERNATIONAL PRECEDENTS OFFER SEVERAL USEFUL TIPS FOR
FORMULATING THE COMPETITIVE GUIDELINES
Reference document
Aspect International examples Issue date/number
Financial guarantees
• RFP for Central Maine Power Company required • November 18, 2003;
bidders to provide financial guarantees upto US$ issued by Maine PUC
from bidders
1.21 million/month and 1.50 million/month while
bidding for service to 2 classes of consumers 31
INTERNATIONAL BIDDING PROCESS - EXAMPLE
33
SYSTEMS REQUIRED TO ENSURE SPEED, TRANSPARENCY AND
FAIRNESS
Discussed further
Standardization
• Standard contract documents to cover as many
Spee scenarios as possible
d of contracts
• All deviations counted as material deviations –
requiring regulatory approval
• All details of bid process and method given to all bidders
Information
Transparency
• All factors that will be considered and their relative
dissemination
weights notified in advance
34
STANDARDIZED BIDDING DOCUMENTS NEEDED FOR EXPIDITING
PROCESS
35
IMPORTANT ISSUES FOR DEBATE – NOT EXHAUSTIVE
37