Project Delivery : BurJuman Centre Mall,

Dubai
• Combined Cooling Capacity : 13,287 tons
• Equipment:7 Chillers(1898 tons each) and 7 cooling towers
• Stage of completion:
• Work Phase 1(Completed by 31/8/2019) :Curve Fit data and specifications
document generated.
• Work Phase 2(In progress) :Model Creation/Data Upload Completed on
Planning tool. Simulation execution and validation step is going on .
Target completion date - 31/12/2019
Project Delivery : Emirates Palace Hotel, Abu
Dhabi
• Combined cooling capacity : 12000 tons
• Equipment:6 chillers (2000 tons) and 6 cooling towers
• Stage of completion:
• Work Phase 1(completed by 31/8/2019) :Curve Fit data and specifications
document generated. Work Phase 2 :One run of optimal/baseline/Q-sweep
simulations generated, but required a re-evaluation as results were not
satisfactory. New kernel release is requested to re-run the simulation.
Target completion date – 31/10/2019