Beruflich Dokumente
Kultur Dokumente
Sarajevo 25.10.2019
Agenda
• General introduction, specifics of planned
tunnel structure
• Safety concept + ventilation
• Geology + hydrogeology + geological risk
management
• Coffee break
• General tunnelling aspects and approaches
NATM/TBM
• Procurement
• Coffee
• Panel discussion
• Conclusions
General introduction,
specifics of planned
tunnel structure
• Tunnel Prenj = 10,1 km long tunnel
• Up to 1100 m overburden
• Entrance in the tunnel at altitude of app. 700 m
• Exit of the tunnel at altitude of app. 620 m
• Limestone/Dolomitic
rock/Karstification/Tectonised rock
25000
20000
• Čelebići (Konjic – Mostar) ADT = 8794 veh/day
(summer time 11687 veh/day, max 16807) 15000
• 8% of HGV 5000
0
2010 2015 2020 2025 2030 2035 2040 2045
Horizontal Alignment
Ventilation: Normal operations
• Semi-Transverse Ventilation
• fresh air is pulled in by the traffic and jet fans in the roadway; (if
needed) exhaust air is extracted via the overhead duct and fans at the
portal
Exhaust
air out at Exhaust
portal air out at
portal
UPGRADING EXISTING ROAD TUNNELS TO CURRENT NEEDS, TAKING THE ARLBERG TUNNEL AS AN EXAMPLE M. Bacher, P.J. Sturm Graz
University of Technology, Austria
Safety concept & ventilation
• Basic concepts
• Important input data
• A risk-based design approach
• Options
• Further steps
Basic concept
• Build one 2 lane tunnel for traffic with a parallel escape tunnel
(1+1 option) *
• traffic flows in both directions
• in an emergency people escape into the parallel tunnel
• Later there are two 2 lane tunnels (2 tunnel option)
• traffic flows in one direction in each tunnel - safer!
• in an emergency people escape into the parallel tunnel
• easier maintenance as one tunnel can be close, if needed
• Ventilation is used to control the air quality during operations
• both normal operations and emergencies
* building a single tunnel with refuges or escape via a ventilation duct is not a safe option
Important input data
• Regulations
• This is part of the Koridor Vc TEN route so it is assumed that normal EU
regulations apply
• Traffic forecast
• Volume of traffic (now and in the future); traffic mix (especially how many
HGVs)
• Geometrical inputs
• Road gradient -> fire risks from overheating engines / brakes; impact on air
quality as HGVs drive up a steep gradient
• Climate & location (e.g. pressure differences betwen portals)
• Other
• Traffic management concept (normal operations and maintenance)
Comments on base assumptions
Traffic volume predictions AADT
• One vs two tunnels 2%, 3%, 4% growth?
* the parallel tunnel should be the normal side for a road tunnel as it is too difficult to enlarge a smaller one.
Options
Phasing of work, what to build and when?
1 2 3 4 5 6 7 8
What do we know about Tunnel Prenj
hydrogeological conditions?
Green colour materials: highly permeable rock mass with high permeability and significant to high risk of
karstification, expected inflow into tunnel 250l/sec/km (?)
Yellow colour materials: rock mass with moderate permeability, expected inflow into tunnel 30l/sec/km
Brownish colour materials: rock mass with low to very low permeability, expected inflow into tunnel
3l/sec/km
What can go wrong if ground conditions are not understood good enough?
example Tapovan HRTTapovan Vishnugad HEP, India, problems of TBM HRT
New Delhi
Dhauliganga Valley at
Tapovan/Joshimath / near springs of
Ganges River
Project: Hydropowerplant, 520 MW with four turbines each 130 MW; 2,6 GWh/yr
Owner: NTPC
Subject: Headrace Tunnel with TBM and Drill/Blast/Backhoe excavation
Schedule: TBM started in 2008, currently stand-still of TBM since 2012
Status: Since 2014 arbitration at arbitration court in New Delhi, 500 Mio € claim and counter claim
Length of HRT = 12.1 km
Tapovan Vishnugad HEP, India (diameter = 6.65m)
24.12.2009: 1st TBM event/TBM blocked, water Right from beginn on repeated
inrush q = 700-800 l/s water inrush situations and partial
collapses during drill/blast/backhoe
excavtion
drill/blast/backhoe excavation
= 3.3 km
Quelle: Project tender
documents
Helong Formation (gneiss, mica schist Tender documents do not mention any Joshimat Formation (mainly
quartzite, amphibolite) fault beetween the two tectonic units gneiss
TBM drive:
Tapovan Vishnugad HEP, India Water inrush with q = 700-800 l/sec
Tapovan Vishnugad HEP, India
„first TBM incident“:
Measures for saving and repairing
the TBM:
Build by-pass tunnel, intensive
drainage ahead and around,
probing ahead and around.
TBM stand-still period:
December 2009 till March 2011,
in total 15 months. Monate.
Vortrieb
Dez 2009
Zeit
März 2011
Tapovan Vishnugad HEP, India
Indented/bent shield of TBM.
Tapovan Vishnugad HEP, India
Face collapses and lateral collapses with heavy water
inrush at tuunel driven by drill/blast/backhoe
excavation. Completely inadequate excavation/support
methodology.
High risk level for labour and site.
Review / revision of geological model 2011/2012 showed that HRT
Tapovan Vishnugad HEP, India alignment almost entirely located in a large important fault zone (in MCT =
Main Central Thrust Zone)
HRT
Tapovan Vishnugad HEP, India = MCT Zone
Helong Formation
HRT
Helong Formation
• Geological model/longitudinal section through tunnel derives purely from regional geological
mapping, significant uncertainty as no deeper site investigation performed up to now
• High uncertainty concerning karstification/size and frequency of karst voids/caves, tunnel
excavation method must consider potential caves/chimneys ….. Regular probing ahead with
sufficient overlap may help.
• High uncertainty concerning potential fillings of karst voids (volume, grain size, water pressure,…)
Regular probing ahead with sufficient overlap may help.
• High uncertainty concerning water inflow to be expected / high water pressure possible due to high
overburden – More site investigation and hydrogeological modelling
• Danger of polluting karst ground water body/ies during construction… Tunnelling works need to be
specified accordingly.
• Rock mass locally tectonized and faulted, mechanical properties of faulted rock mass/cataclasites,
any swelling clay minerals in fault gouge - not yet studied. Detailed site investigation works will help
to minimize this.
• Thickness of fault zones to be tunnelled not yet studied in detail - Detailed site investigation works
may help to minimize this shortcoming
How important is the preservation of the huge karst water body of
of Tunnel Prenj mountain range for entire BiH on the long range?
Even with the most diligent and thorough site investigation in a difficult geological situation such as
Tunnel Prenj, some geological and hydrogeological risks will remain during preparation of tender
documents. For this reason we would advise
• to accept that the Ground belongs to the Employer
• to accept that the Employer has to pay reasonable cost required to handle the ground conditions
encountered durring construction
• to include a clear definition of foreseen ground conditions as the basis for Tenders. This definition of
foreseen ground conditions should be the Geotechnical Baseline report GBR as described in the
FIDIC Emerald Book
• The GBR shall be the single contractual document that defines what ground conditions are to be
assumed to be encountered during execution of tunnelling works.
• The GBR contractually allocated risks between the Employer and the Contractor for defined
physical conditions
COFFE BREAK
General tunnelling aspects and
approaches NATM/TBM
• Peter
Constr.
Plabutschtunnel
1+e
1+1
1978
1987
13972
10085
4,5
7
NATM
NATM
0,32
0,69
road tunnels in
Gleinalmtunnel 1+1
2003
1978
10085
8320
4
5
NATM
NATM
0,40
0,60
Austria
2017 8320 4 0,48
Karawankentunnel
1 + (1) 1991 7864 5 NATM 0,64
Landecker Tunnel
1 2000 6955 3,5 NATM 0,50
Pfändertunnel 1+1 1980 6718 6 NATM 0,89
2006 6718 4 TBM 0,60
Tauerntunnel 1+1 1975 6401 4 NATM 0,62
2010 6401 4 NATM 0,62
Strenger Tunnel
2 2006 5851 6 NATM 1,03
Katschbergtunnel 1974
1+1 2009 5898 4 NATM 0,68
Bosrucktunnel 1+1 1983 5509 3,5 NATM 0,64
2011 5509 4 NATM 0,73
Roppener Tunnel
1+1 1990 5095 3 NATM 0,59
Felbertauerntunnel
1+e 1967 5282 5 NATM 0,95
Schmittentunnel 1 1996 5111 3 NATM 0,59
Average 0,64
Constr.ti
Long Railway
Name Tubes E L (m)
me
(yrs) Method yr/km tunnels in
Wienerwaldtunnel TBM+NA
Inntaltunnel
2 2012 13356 8 TM 0,60 Austria
1 1994 12696 4,5 NATM 0,35
Lainzer Tunnel
1 2012 12300 6 NATM 0,49
Arlbergtunnel
1 1884 10648 4 NATM 0,38
Tauerntunnel
1 1906 8550 8 NATM 0,94
Karawankentunnel
1 1906 7976 4 NATM 0,50
Siebergtunnel
1 2001 6480 5 NATM 0,77
Galgenbergtunnel
1 1998 5460 4,5 NATM 0,82
Kaponig-Tunnel
1 1996 5096 4 NATM 0,78
Semmering-
Basistunnel TBM+NA
2 2026 27300 14 TM 0,51
Brennerbasistunnel TBM+NA
2 2027 64000 15 TM 0,23
Average 0,58
What do we now compare with?
• NATM • TBM
double shell, drained tunnel, membrane • shield machine with segmental lining
exhaust ventilation • single or double shell
Important features of long road tunnels
• Ventilation compartments inside cross section
Important features of long road tunnels
• Ventilation shafts and caverns
Important features of long road tunnels
• Cross passages every 300m
• Lay-by niches each 1000m
• In bi-directional traffic lay-by niches on both sides
What this means for construction method
NATM TBM
• completely flexible in shape • first, you build a circular
tunnel only
• for other sections: lining has
to be cut open – NATM works
• NATM site facilities have to
be here as well
Example TBM tunnel and niche widening
Speed of NATM excavation works
16
15
14 Kalotte
[m/AT]
13
(m/d)
12
[m/AT]
11
speed
10 wide range of
Vortriebsleistung
9 advance rate
8 Systemleistung
Advance
Kal.+Str. [m/AT]
7
6
5
4
3
VKL 3/1,15 VKL3/2,05 VKL4/1,75 VKL 4/2,95 VKL 5/3,85 VKL5/5,54 VKL6/4,43 VKL6/6,43 VKL6/8,43 VKL6/10,43
2
3.00 3.00 2.20 2.20 1.70 1.70 1.30 1.30 1.30 1.30
Abschlagslänge max. [m]
Advance length (m)
Pro‘s and Con‘s
NATM pro‘s NATM con‘s
quick start less speed
flexible in shape likely longer construction time
more local manpower
involved
cash flow better distributed
adaptive to ground conditions
does seldom get stuck
Pro‘s and Con‘s
NATM pro‘s NATM con‘s
quick start less speed
flexible in shape likely longer construction time
more local manpower
involved
cash flow better distributed
adaptive to ground conditions
does seldom get stuck
Pro‘s and Con‘s
NATM pro‘s NATM con‘s
quick start less speed
flexible in shape likely longer construction time
more local manpower
involved
cash flow better distributed
adaptive to ground conditions
does seldom get stuck
Pro‘s and Con‘s
NATM pro‘s NATM con‘s
quick start less speed
flexible in shape likely longer construction time
more local manpower
involved
cash flow better distributed
adaptive to ground conditions
does seldom get stuck
Example of a construction program TBM
2 x 8.8 km railway tunnel
Cuts, portals, starting tube, TBM manufacturing
6.5 years
…delayed… 1 year
TBM drive 1st tube
• Transactional (One-off)
Client
• Known Scope
• Hands-on client
Consultant Contractor
(Design) (Build)
ECI Why ECI?
• Contractor involved in early decision
Client
making
Consultant
• Management of designers
(Design)
• Buildability & Value management
throughout
• Assured delivery time
Contractor
• Capture resources and supply chain
Public Inquiry
Design and Build
• Price competition strategic
61
UK Construction Industry 2014
The industry have done a successful transformation
from adversarial to collaborative contracting
• Effects of construction of section on the regional financial developement ROI • Exact BOQ
• Time schedule • Exact time schedule
• Risk analysis for geotechnical works
• Handling with waste material and material reuse
Panel discussion
• Open questions
Conclusions