Introduction
This Training Course is intended to give a comprehensive introduction
to the concept and use of Tribon to the trainees.
The trainees are expected to actively participate in the training and
exercises, and their understanding of Tribon will be assessed by a test.
WHAT IS TRIBON….?
Tribon: Industry standard software for CAD CAE CAM in
Shipbuilding.
Tribon Concept
Tribon has been designed to provide a structured way to develop and
improve the information flow between the different tasks within the
shipbuilding process, where many design development tasks are
performed in parallel.
Information Model
PIM A comprehensive "Ship Database" containing all information
about a specific project.
Characteristics of PIM
Multi User Concurrent Access to the Product Information Model.
The data in the Product Information Model can be created and updated by
many designers and production engineers working both in parallel within
technical disciplines and across disciplines.
Hull and outfitting designers, for example, can therefore work together in a
concurrent manner
Characteristics of PIM
Integration of Hull and Outfitting.
The close association between the Hull and Outfit data in allows the hull
structure and outfit designers to work in parallel sharing the most up-to-date
information during design development and producing well integrated final
arrangements.
Component Catalogue.
The Component Catalogue is continuously updated by a shipyard, and
component data can easily be shared between yards and design agents.
Characteristics of PIM
Additional information can be readily derived, from the PIM.
For example, if there is a rule that a stiffener is welded to an adjacent plate,
then the amount of weld can be calculated from that rule and the stiffener
model.
Characteristics of PIM
Integration of Design and Production Engineering Data Structures.
of the PIM
Surface
E.g. Main Deck, Engine room Bulkhead, Inner Bottom etc.
of the PIM
Compartment
Eg. Cargo Tank or a Machinery Space.
of the PIM
System
E.g. a Sea Water ballast system and a Lub Oil system
A system contains equipment that is inter-connected objects and
components, such as by pipes, cables or ventilation trunks, etc.
of the PIM
Block
Typically a major assembly of hull steel and outfit support structure and
which is typically then lifted into its final hull position in the building
dock
of the PIM
Module
It could be all outfit in a compartment or in a complex section or
region, for example, deck piping in a supporting frame work.
of the PIM
Assembly
A grouping of parts or sub assemblies which will be joined together in
the construction process at a particular stage.
TRIBON DRAFTING
For Product Information Model viewing,
For the developing of drawings and
For three-dimensional, 3D, volume modelling.