Beruflich Dokumente
Kultur Dokumente
© 2011 Chevron 8
CS WUR CONTRACT HIGHLIGHTS
IMPROVEMENT FROM CS WUR LONG TERM CONTRACT
© 2011 Chevron 9
CS WUR CONTRACT HIGHLIGHTS
Contract Administration Governance Model
CPI ECM
DELEGATION OF AUTHORITY:
• Program Management
• Work Authorization
• Contract Administration
LEGAL: OPERATIONS:
• Contract Ts&Cs • Engineering
• Management System • Project Management:
• Work Authorization •Project Controls
• Accrual & Billing: •Work Acceptance
•Work •Process Improvement
• Acceptance
•Invoicing & Payment • Construction Supervision:
CS WUR / •HES
RUR •QA/QC
•CEM
• Quality Acceptance
© 2011 Chevron 14
CS WUR CONTRACT HIGHLIGHTS
Work Order Sequence
Work Execution
• Work Progress is recorded in CCMS, include RCO if required
Close Out
• Work Acceptance Certificate
© 2011 Chevron 15
CS WUR CONTRACT HIGHLIGHTS
Work Assignment Proposal and Service Request Time Line
SR Start SR End
Date
Date
© 2011 Chevron 16
CS WUR CONTRACT HIGHLIGHTS
Penalty and Billing
Mechanical Completion
(Exh. A-18.1)
Commencement SR Closure
Date of SR Certificate
Certificate of Certificate of Work
Physical
Completion Mechanical Acceptance
Signed by CPI Acceptance Released by CPI
Released by CPI
SR Period
© 2011 Chevron 21
CS WUR CONTRACT HIGHLIGHTS
EXHIBIT A – Scope of Work
SR Closure
Within two (2) month as of issuance of Work Acceptance Certificate (WAC) by
Company, Company and Contractor shall close-out each SR.
Unless specified differently by Company, at minimum or as applicable Contractor
shall submit the following documents for SR closure:
1. As-built drawing
2. Material usage report
3. Copy of invoice documents
Contractor shall provide 1 copy of SR closure documents in CD Format and the
hardcopy original to Company.
Report and Schedule & Cost Control
Contractor shall furnish Company with weekly reports containing significant
information of work progress, resource loading, and material usage, which will allow
Company to appraise each and overall work status.
Contractor shall provide the Monthly report by the tenth (10th) day of each month.
Contractor shall supply additional reports if required by Company. Company will
require a minimum of three (3) copies of all reports required.
© 2011 Chevron 23
CS WUR CONTRACT HIGHLIGHTS
EXHIBIT A – Scope of Work
© 2011 Chevron 25
CS WUR CONTRACT HIGHLIGHTS
EXHIBIT A – Scope of Work
© 2011 Chevron 26
CS WUR CONTRACT HIGHLIGHTS
EXHIBIT A – Scope of Work
© 2011 Chevron 27
CS WUR CONTRACT HIGHLIGHTS
EXHIBIT A – Scope of Work
Standby Cost
Contractor has notified in writing to Company since the beginning of the delay that
caused the crew and equipment cannot work and have to standby at Job Site.
Contractor has made maximum effort to minimize the number of crew and
equipment standby at the Job Site by re-assigning them to other Job Site.
Contractor has recorded and obtained Company’s Approval to the list of crew and
equipment that standby and standby hours at the Job Site for each day of
occurrence.
Claims for reimbursement of standby cost has to be made by Contractor to
Company for the Direct Cost actually incurred to Contractor for keeping the crews
and equipment in standby during the hours of work delay.
Company has the right to reject and Contractor no longer has the right to claim the
cost of crew and equipment standby in the event Contractor failed to provide the
above information or evidence of the Direct Cost incurred.
© 2011 Chevron 28
CS WUR CONTRACT HIGHLIGHTS
EXHIBIT A – PENALTY
© 2011 Chevron 29
PROJECT INFORMATION
PROJECT TITLE
SCOPE OF WORK
PROJECT EARN VALUE MANAGEMENT
ANALISA EVM
PROJECT EARN VALUE MANAGEMENT
Welding Simulasi
PROJECT SUMMARY
Thank you
© 2011 Chevron 81