Beruflich Dokumente
Kultur Dokumente
By
FEASIBILITY STUDIES
SITE INVESTIGATION
DETAILED PLANNING OF WORKS
DETAILED PROJECT REPORTS CIVIL
ELECTRICAL
COST ESTIMATE
TECHNOECONOMIC
ENVIRONMENTAL
EVALUATION & APPRAISAL STAGE CLEARANCES FROM
STATUTORY BODIES
INVESTMENT DECISION
CONSTRUCTION STAGE
PLANNING
STAGES OF PLANNING INCLUDE A THREE STAGE PROCESS:
STAGE-I
STAGE-II
STAGE-III
Infrastructure Works.
Main Works:
Civil Works.
Hydro-Mechanical Works
List of E&M Equipment
1.0 TURBINE AND GOVERNING EQUIPMENTS
1.1 TURBINE
1.2 GOVERNING SYSTEM (DIGITAL TYPE) AND
ACCESSORIES
2.0 GENERATOR AND ASSOCIATED EQUIPMENTS
2.1 GENERATOR
2.2 EXCITATION SYSTEM
2.2 ISOLATED PHASE BUS DUCT
3.0 MECHANICAL SYSTEMS
3.1 EOT CRANE
3.2 COOLING WATER SYSTEM
3.3 DRAINAGE SYSTEM
3.4 DEWATERING SYSTEM
3.5 COMPRESSED AIR SYSTEM
3.6 HVAC SYSTEM
3.7 FIRE FIGHTING SYSTEM
3.8 OIL FILTRATION SYSTEM
3.9 D.G. SETS
3.10MECHANICAL WORKSHOP EQUIPMENTS
List of E&M Equipment
4.0 ELECTRICAL SYSTEMS
4.1 GENERATOR STEP-UP TRANSFORMERS
4.2 CONTROL, MONITORING AND PROTECTION SYSTEM
4.3 220V AND 48V DC SYSTEM
4.4 220KV/400KV XLPE CABLES
4.5 POWER AND CONTROL CABLES (INCLUDING CABLE
TRAYS)
4.6 11 KV SWITCHGEAR SYSTEM
4.7 415V SWITCHGEAR SYSTEM
4.8 STATION SERVICE TRANSFORMERS
4.9 UNIT AUXILIARY TRANSFORMERS
4.10 POWER LINE CARRIER COMMUNICATION SYSTEM
4.11 ILLUMINATION SYSTEM
4.12 GROUNDING SYSTEM
4.13 PUBLIC ADDRESS SYSTEM
4.14 ELECTRICAL WORKSHOP EQUIPMENTS
5.0 GIS AND POTHEAD YARD EQUIPMENTS
5.1 GAS INSULATED SWITCHGEAR
Erection Sequence
Readiness of GIS location, transformer
bay location , Pothead yard location.
Readiness of Crane beam.
Placement of ground mat & Concreting.
EOT Crane Erection.
Readiness of foundation for erection of
Draft Tube(DT) assembly.
Draft tube erection.
Erection Sequence
Draft tube concreting.
Foundation plate erection, Spiral case stay
ring, bottom ring & runner chamber
erection.
Concreting of above.
Lowering & installation of runner.
Shaft free.
Erection Sequence
Stator assembly in service Bay.
Stator winding connection & HV test.
Generator Rotor assembly in service Bay.
Assembly of lower combined bearing
Assembly of stator complete
Assembly of brake lifting, brake dust exhaust
system, standstill heaters & air shield Drive
End(DE).
Assembly of rotor and slip ring support.
Assembly of upper bracket
Erection Sequence.
Assembly of brush holder bracket and air shield
Non Drive End(NDE)
Assembly of slip ring complete and carbon dust
exhaust system
Run out check of generator rotor.
Coupling with turbine shaft
Run out check with coupled turbine
Adjusting magnetic center and air gap.
Assembly of covers.
Final assembly.
Erection Sequence
Parallel activity of the auxiliary equipment
like:
Governing system erection & pre
commissioning.
Static Excitation, AVR & Bus duct erection &
pre commissioning.
Generator step up transformer erection & pre
commissioning.
XLPE cables, GIS, Pothead yard, DC system,
control & monitoring, Protection system, UAT,
SST, cooling water & drainage systems, DG
sets, illumination, etc.
Erection Sequence
Unit axis alignment & box up.
Testing & Pre-commissioning.
Availability of water.
Spinning, dry out & synchronization.
Field tests & handover.
SITE TESTING PHILOSPHY
1. Motors.
2. Control panels.
3. Pumps.
4. Compressors.
5. Relays.
6. CT/PT/CVT.
7. Circuit breaker.
8. Isolator
9. Generator.
Continued---
10. Turbine.
11. Inlet valve.
12. GSU Transformer.
13. UAT/SST.
14. LT Panel/HT panel.
15. Excitation equipment.
16. Governor.
REMOTE TESTS/SYSTEM
TESTS:
1. Unit control scheme including Inlet valve
control.
2. Unit Protection Scheme
Mechanical protective Devices
Electrical protection.
3. Feeder control.
4. Feeder Protection.
5. Alarm & Annunciation system including
Sequence Event Recorder.
Continued---
6. Auxiliary System.
Cooling Water system.
Compressed Air system.
O.P.U
O.L.U.
7. A.C Supply system including 11KV.
8. D.C Supply system.
9. Drainage & Dewatering system.
10. Fire Protection System
GSU TRANSFORMER:
1. I.R. Value of Transformer Winding.
2. Transformer oil test.
B.D.V
TAN DELTA
P.P.M
3. Ratio test at Diff.Taps.
4. Resistance at Diff Taps.
5. Mag .Current at 415 V from both end.
Continued---
Polarity check.
Ratio Test.
Magnetising.
MOTORS:
I.R Value.
Direction of Rotation.
CIRCUIT BREAKER:
1) Functional Check.
2) Open/close test.
3) Opening/closing time check.
4) Breaker duty cycle test.
5) Pole discrepancy check.
6) Pressure Relay test.
7) Contact Resistance check.
L.T. PANEL/H.T. PANEL:
Physical Inspection.
I.R Value check.
Disconnection of Ext. cable.
Functional check.
Opening/closing operation.
Tripping through protection.
Pre-commissioning
check/tests on generator
A. STATOR:
After completing the winding connection.
The Stator is put on dry out with a
rectiformer.
During dry out test,we take the megger
value of winding and P.I(Polarisation Index)
After dry out each winding of stator is
subjected to high voltage test(I.e at 23KV
AC for 11 KV stator) for one minute
B. ROTOR : Continued---
C. GENERAL:
Functional Check.
Field breaker operation check-Closing ,
opening and tripping on fault
Auto/Manual control of generation
voltage.
Alarm & Annunciation check.
Indication check.
Metering check.
Control Panels:
Physical inspection.
Insulation resistance tests.
Continuity test.
Tests to prove correct operation of interlocks,
tripping and closing circuits,indication etc.
Meter calibration check.
Protective relay test and setting.
Sequential operation check.
Protective gear timing tests as may be
applicable.
Test operation of alarm devices.
COMMISSIONING TESTS OF
RELAYS
1. GENERAL INSPECTION
2. INSULATION CHECK
3. AC CIRCUIT CHECK(CT/PT)
4. SECONDRY INJECTION OF RELAYS
5. PRIMARY INJECTION TEST OF CTs AND
STABILITY AND SENSITIVITY TEST OF
RELAYS.
6. D.C FUNCTIONAL CHECK.
7. CHARGING OF EQUIPMENT AND LOAD
CHECKS.
TEMP. SENSING DEVICES
1. CALIBRATION OF TSD AT VARIOUS
TEMP. (OPERATION RANGE)
2. TEST FOR ALARM AND TRIP SETTINGS
AND CONTACT CHANGE OVER CHECK
Continued---
SYNCHRONISATION CHECKS.
OVER SPEED TEST.
OVER LOAD THROW OFF TEST AT
DIFFERENT LOADS.
RECORDING AND MONITORING OF
VOLTAGE RISE AT THE TIME OF LOAD
REJECTION TEST.
TESTS PERFORMED ON
EACH MACHINE BEFORE
COMMERCIAL RUN:
DETERMINATION OF THE
TEMPERATURE OF BEARINGS.
PHASE SEQUENCE CHECK.
Open Circuit Test (OCC).
Short Circuit Test (SCC).
MEASUREMENT OF AIR GAP.
VIBRATION MEAUSREMENT OF
MACHINE PARTS .
LOAD REJECTION TESTS.
SHAFT VOLTAGE MEASUREMENT.
P.H.
SECTION
SPIRAL CASING
SHOP ASSEMBLY OF SPIRAL
CASE AND STAY RING
BUTTERFLY VALVE
Thank You