Beruflich Dokumente
Kultur Dokumente
Power Project
Milestones 27-01-2020
Installation (Phase 2)
24-12-2019
Procurement (Phase 2)
07-11-2019
Water Discharge
07-11-19
Installation (Phase 1)
24-09-2019
Procurement (Phase 1)
10-08-2019
Pre-construction
240
29-06-2019 days
Planning
01-06-2019
Project Approach
Adani group needed to procure 2500 acres of land
matching certain criteria.
Procurement of machinery, equipments, solar
panels, micro-inverters from different countries.
By October end the team had hardly managed to
installed enough solar panels to generate only 1.6
MW of power though the target was of 90 MW.
Phase 2 of installation is expected to start by the
end of December & the company would have to
install enough solar panels to generate 13 MW of
power each day to meet the deadline.
ng
Task Name Duration Start Finish
es
Cost
Risk Matrix
Risk-tier Description
Project Management/Development Risks that may be encountered
throughout the development of the
PV project: changes in costs,
design issues, permit issues, etc
Hardware Risks related to the hardware
components of the system:
compatibility
Natural Calamities Risks from any kind of natural
disaster like earthquake, flood or
strong wind
Government Risks related to changes in
governmental policies & priorities
Recommendations
Avoid • Change the project plan to eliminate the risk or to protect the
project objectives (time, cost, scope, quality) from its impact
• Some threats that arise early in the project can be avoided by clarifying
requirements, obtaining information, improving communication, or
acquiring expertise
• Risk mitigation may take resources or time and hence may represent a
tradeoff. However, the overall result may reduce risk to the overall
project objective
• Shift the negative impact of a threat to a third party
through: insurance, performance bonds, warranties,
guarantees, incentive/disincentive clauses, cost & time
contracts, provided the price for the risk transfer can be
supported by project cash flow