PROJECT MANAGEMENT
PROJECT SCHEDULING
𝑶 + 𝟒𝑴 + 𝑷
𝑴𝒆𝒂𝒏 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 =
𝟔
𝟐
𝑷−𝑶
𝑽𝒂𝒓𝒊𝒂𝒏𝒄𝒆 = ቆ ቇ
𝟔
C.) Find critical path and expected
project completion time.
Earliest Start Time (Forward) and Latest Completion Time (Backward)
FORMULA:
Earliest Start Time = Max (Previous Earliest Start Time + Mean Duration)
Latest Completion Time = Min (Previous Latest Completion Time – Mean Duration)
CRITICAL PATH CONDITIONS:
1. Starting node need to have equal E.S.T and L.C.T
2. Ending node need to have equal E.S.T and L.C.T
3. E.S.T ending node subtracted to E.S.T starting node must be equal to mean
duration of the activity
Add values of the mean duration of the critical path to determine the project
completion.
D.) What is the probability of
completing the project on or
before 22 weeks.
FORMULA:
𝑷𝒓𝒐𝒃𝒂𝒃𝒊𝒍𝒊𝒕𝒚 𝒙 ≤ 𝑫𝒆𝒂𝒅𝒍𝒊𝒏𝒆