Chapter 4 -

Managing
Project
Processes

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship

AOA AON

Figure 4.1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship

S precedes T, which precedes U.

AOA AON

S T U
1 2 3 4 S T U

Figure 4.1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship

S and T must be completed before U can be started.

AOA AON

1 S S
U
T 3 4 U

2 T

Figure 4.1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship

T and U cannot begin until S has been completed.

AOA AON

T 3 T
S
1 2 U S

4 U

Figure 4.1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship

U and V cannot begin until both S and T have been


completed.

AOA AON

1 S U 4 S U

T 3 V

2 5 T V

Figure 4.1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship

U cannot begin until both S and T have been completed;


V cannot begin until T has been completed.

AOA AON

S U
1 3 5 S U

Dummy
T V
2 4 6 T V

Figure 4.1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship

T and U cannot begin until S has been completed; V


cannot begin until both T and U have been completed.

AOA AON

S T V
1 2 4 5 S T V

Dummy
U
3 U

Figure 4.1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity Description Predecessor(s)
ASelect administrative and medical staff.
BSelect site and do site survey.
CSelect equipment.
DPrepare final construction plans and layout.
E Bring utilities to the site.
F Interview applicants and fill positions in nursing,

support staff, maintenance, and security.


GPurchase and take delivery of equipment.
HConstruct the hospital.
I Develop an information system.
J Install the equipment.
KTrain nurses and support staff.
Example 4.1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity Description Predecessor(s)
ASelect administrative and medical staff. —
BSelect site and do site survey. —
CSelect equipment. A
DPrepare final construction plans and layout. B
E Bring utilities to the site. B
F Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


GPurchase and take delivery of equipment. C
HConstruct the hospital. D
I Develop an information system. A
J Install the equipment. E,G,H
KTrain nurses and support staff. F,I,J
Example 4.1
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description Predecessor(s)
A Select
administrative and medical staff. —
B Select
site and do site survey. —
C Select
equipment. A
D
Prepare final construction plans and layout. B
E Bring
utilities to the site. B
F
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description Predecessor(s)
A Select
administrative and medical staff. —
B A Select
site and do site survey. —
C Select
equipment.
Start A
D
Prepare final construction plans and layout. B
E Bring
utilities to the site. B
F
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description Predecessor(s)
A Select
administrative and medical staff. —
B A Select
site and do site survey. —
C Select
equipment.
Start A
D
Prepare final construction plans and layout. B
E B Bring
utilities to the site. B
F
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description Predecessor(s)
A Select
administrative and medical staff. —
B A Select
site and do site survey. —
C Select
equipment.
Start C A
D
Prepare final construction plans and layout. B
E B Bring
utilities to the site. B
F
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description Predecessor(s)
A Select
administrative and medical staff. —
B A Select
site and do site survey. —
C Select
equipment.
Start C A
D
Prepare final construction plans and layout. B
E B D Bring
utilities to the site. B
F
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description Predecessor(s)
A Select
administrative and medical staff. —
B A Select
site and do site survey. —
C Select
equipment.
Start C A
D
Prepare final construction plans and layout. B
E B D Bring
utilities to the site. B
F
Interview applicantsEand fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description Predecessor(s)
A Select
administrative and medical staff. —
B A F Select
site and do site survey. —
C Select
equipment.
Start C A
D
Prepare final construction plans and layout. B
E B D Bring
utilities to the site. B
F
Interview applicantsEand fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description Predecessor(s)
A Select
administrative and medical staff. —
B A F Select
site and do site survey. —
C Select
equipment.
Start C G A
D
Prepare final construction plans and layout. B
E B D Bring
utilities to the site. B
F
Interview applicantsEand fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description Predecessor(s)
A Select
administrative and medical staff. —
B A F Select
site and do site survey. —
C Select
equipment.
Start C G A
D
Prepare final construction plans and layout. B
E B D H Bring
utilities to the site. B
F
Interview applicantsEand fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description
I Predecessor(s)
A Select
administrative and medical staff. —
B A F Select
site and do site survey. —
C Select
equipment.
Start C G A
D
Prepare final construction plans and layout. B
E B D H Bring
utilities to the site. B
F
Interview applicantsEand fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description
I Predecessor(s)
A Select
administrative and medical staff. —
B A F Select
site and do site survey. —
C Select
equipment.
Start C G A
D
Prepare final construction plans and layout. B
E B D H J Bring
utilities to the site. B
F
Interview applicantsEand fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description
I Predecessor(s)
A Select
administrative and medical staff. —
B A F K Select
site and do site survey. —
C Select
equipment.
Start C G A
D
Prepare final construction plans and layout. B
E B D H J Bring
utilities to the site. B
F
Interview applicantsEand fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AON Network Description
I Predecessor(s)
A Select
administrative and medical staff. —
B A F K Select
site and do site survey. —
C Select
equipment.
Start C G Finish A
D
Prepare final construction plans and layout. B
E B D H J Bring
utilities to the site. B
F
Interview applicantsEand fill positions in nursing,
Figure 4.2
support staff, maintenance, and security. A
Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AOA Network Description Predecessor(s)
A Select
administrative and medical staff. —
B Select
site and do site survey. —
C Select
equipment. A
D
Prepare final construction plans and layout. B
E Bring
utilities to the site. B
F
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AOA Network Description Predecessor(s)
A 2 Select
administrative and medical staff. —
B Select
site and A do site survey. —
C Select
equipment.
Start A
D 1
Prepare final construction plans and layout. B
E Bring
utilities to the site. B
F
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AOA Network Description Predecessor(s)
A 2 Select
administrative and medical staff. —
B Select
site and A do site survey. —
C Select
equipment.
Start A
D 1
Prepare final construction plans and layout. B
E B Bring
utilities to the site. B
F
4
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AOA Network Description Predecessor(s)
A 2 Select
administrative and medical staff. —
C
B Select
site and A do site survey. —
3
C Select
equipment.
Start A
D 1
Prepare final construction
5 plans and layout. B
E B Bring
utilities to the site.
D B
F
4
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AOA Network Description Predecessor(s)
F
A 2 8 Select
administrative and Imedical staff. —
C
B Select
site and A do site survey. —
3 7
C Select
equipment.
Start G A
D 1
H
Prepare final construction
5 6plans and layout. B
E B Bring
E
utilities to the site.
D B
F
4
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AOA Network Description Predecessor(s)
F
A 2 8 Select
administrative and Imedical staff. —
C
B Select
site and A do site survey. —
3 7 J
C Select
equipment.
Start G A
D 1
H
Prepare final construction
5 6plans and layout. B
E B Bring
E
utilities to the site.
D B
F
4
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AOA Network Description Predecessor(s)
F
A 2 8 Select
administrative and Imedical
Dummystaff. —
C
B Select
site and A do site survey. —
3 7 J
C Select
equipment.
Start G A
D 1
H
Prepare final construction
5 6plans and layout. B
E B Bring
E
utilities to the site.
D B
F
4
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
AOA Network Description Predecessor(s)
F
A 2 8 Select
administrative and Imedical
Dummystaff. —
C
B K Select
A
site and do site survey. —
3 7 J
C Select
equipment.
Start G A
Finish
D 1 9
H
Prepare final construction
5 6plans and layout. B
E B Bring
E
utilities to the site.
D B
F
4
Interview applicants and fill positions in nursing,
Figure 4.3
support staff, maintenance, and security. A
Example 4.1
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
Completion Time Description Predecessor(s)
A Select
administrative and medical staff. —
B Select
site and do site survey. —
C Select
equipment. A
D
Prepare final construction plans and layout. B
E Bring
utilities to the site. B
F
Interview applicants and fill positions in nursing,

support staff, maintenance, and security. A


G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
Completion Time Description I Predecessor(s)
15
A Select
administrative and medical staff. —
A F K
B 12 10 6 Select
site and do site survey. —
C Select
C G
equipment.
Start
10 35
Finish A
D
Prepare final construction plans and layout. B
B D H J
E 9 10 40 4 Bring
utilities to the site. B
F
Interview applicants Eand fill positions in nursing,
24
Figure 4.4
support staff, maintenance, and security. A
G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
Completion Time Description I Predecessor(s)
15
A Select
administrative and medical staff. —
A F K
B 12 10 6 Select
site and do site survey. —
C Select
C G
equipment.
Start
10 35
Finish A
D
Prepare final construction plans and layout. B
B D H J
E 9 10 40 4 Bring
utilities to the site. B
F
Interview applicants Eand fill positions in nursing,
24

support staff, maintenance, and security. A


G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
Completion Time Description I Predecessor(s)
15
A Select
administrative and medical staff. —
A F K
B 12 10 6 Select
site and do site survey. —
C Select
C G
equipment.
Start
10 35
Finish A
D
Prepare final construction plans and layout. B
B D H J
E 9 10 40 4 Bring
utilities to the site. B
F
Interview applicants Eand fill positions in nursing,
24

support staff, maintenance, and security. A


G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
Completion Time Description I Predecessor(s)
15
A Select
administrative and medical staff. —
A F K
B 12 10 6 Select
site and do site survey. —
C Select
C G
equipment.
Start
10 35
Finish A
D
Prepare final construction plans and layout. B
B D H J
E 9 10 40 4 Bring
utilities to the site. B
F
Interview applicants Eand fill positions in nursing,
24

support staff, maintenance, and security. A


G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
Completion Time Description I Predecessor(s)
15
A Select
administrative and medical staff. —
A F K
B 12 10 6 Select
site and do site survey. —
C Select
C G
equipment.
Start
10 35
Finish A
D
Prepare final construction plans and layout. B
B D H J
E 9 10 40 4 Bring
utilities to the site. B
F
Interview applicants Eand fill positions in nursing,
24

support staff, maintenance, and security. A


G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Immediate
Activity
Completion Time Description I Predecessor(s)
15
A Select
administrative and medical staff. —
A F K
B 12 10 6 Select
site and do site survey. —
C Select
C G
equipment.
Start
10 35
Finish A
D
Prepare final construction plans and layout. B
B D H J
E 9 10 40 4 Bring
utilities to the site. B
F
Interview applicants Eand fill positions in nursing,
24

support staff, maintenance, and security. A


G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Path Expected Time (wks) Immediate
Activity
Completion Time Description
I Predecessor(s)
A-F-K 28 15
A-I-K A 33 Select
administrative
A-C-G-J-K 67A and medical staff. —
F K
B
B-D-H-J-K 6912 10 6 Select
B-E-J-K site and do 43site survey. —
C Select
C G
equipment.
Start
10 35
Finish A
D
Prepare final construction plans and layout. B
B D H J
E 9 10 40 4 Bring
utilities to the site. B
F
Interview applicants Eand fill positions in nursing,
24

support staff, maintenance, and security. A


G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Path Expected Time (wks) Immediate
Activity
Completion Time Description
I Predecessor(s)
A-F-K 28 15
A-I-K A 33 Select
administrative
A-C-G-J-K 67A and medical staff. —
F K
B
B-D-H-J-K 6912 10 6 Select
B-E-J-K site and do 43site survey. —
C Select
C G
equipment.
Start
10 35
Finish A
D
Prepare final construction plans and layout. B
B D H J
E 9 10 40 4 Bring
utilities to the site. B
F
Interview applicants Eand fill positions in nursing,
24

support staff, maintenance, and security. A


G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Path Expected Time (wks) Immediate
Activity
Completion Time Description
I Predecessor(s)
A-F-K 28 15
A-I-K A 33 Select
administrative
A-C-G-J-K 67A and medical staff. —
F K
B
B-D-H-J-K 6912 10 6 Select
B-E-J-K site and do 43site survey. —
C Select
C G
equipment.
Start
10 35
Finish A
D
Prepare final construction plans and layout. B
B D H J
E 9 10 40 4 Bring
utilities to the site. B
F
Interview applicants Eand fill positions in nursing,
24

support staff, maintenance, and security. A


G To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital

Figure 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital I

15

A F K

12 10 6

C G
Start Finish
10 35

B D H J

9 10 40 4
Earliest Start
and
E
Earliest Finish Times 24 Example 4.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital I

15
Earliest start time

0
A F K

12 10 6

C G
Start Finish
10 35

B D H J

9 10 40 4
Earliest Start
and
E
Earliest Finish Times 24 Example 4.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital I

Earliest start time


15 Earliest finish time

0
A 12 F K

12 10 6

C G
Start Finish
10 35

B D H J

9 10 40 4
Earliest Start
and
E
Earliest Finish Times 24 Example 4.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital I

15

0
A 12 F K

12 10 6

C G
Start Finish
10 35

0
B 9 D H J

9 10 40 4
Earliest Start
and
E
Earliest Finish Times 24 Example 4.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital I

15

0
A 12 F K

12 10 6

C G
Start Finish
10 35

0
B 9 9
D 19 H J

9 10 40 4
Earliest Start
and
9 E 33
Earliest Finish Times 24 Example 4.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12
I 27

15

0
A 12 12
F 22 K

12 10 6

12
C 22 G
Start Finish
10 35

0
B 9 9
D 19 H J

9 10 40 4
Earliest Start
and
9 E 33
Earliest Finish Times 24 Example 4.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12
I 27

15

0
A 12 12
F 22 K

12 10 6

12
C 22 G
Start Finish
10 35

0
B 9 9
D 19 19
H 59 J

9 10 40 4
Earliest Start
and
9 E 33
Earliest Finish Times 24 Example 4.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12
I 27

15

0
A 12 12
F 22 K

12 10 6

12
C 22 22
G 57
Start Finish
10 35

0
B 9 9
D 19 19
H 59 J

9 10 40 4
Earliest Start
and
9 E 33
Earliest Finish Times 24 Example 4.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12
I 27

15

0
A 12 12
F 22 K

12 10 6

12
C 22 22
G 57
Start Finish
10 35

0
B 9 9
D 19 19
H 59 59
J 63

9 10 40 4
Earliest Start
and
9 E 33
Earliest Finish Times 24 Example 4.2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12
I 27
Earliest start time Earliest finish time
15

0
A 12 12
F 22 63 K 69
12 10 6

12
C 22 22
G 57
Start Finish
Critical 10 35
path

0
B 9 9
D 19 19
H 59 59
J 63

9 10 40 4
Earliest Start
and
9 E 33
Earliest Finish Times 24 Figure 4.6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12
I 27

15

0
A 12 12
F 22 63 K 69
12 10 6

12
C 22 22
G 57
Start Finish
10 35

0
B 9 9
D 19 19
H 59 59
J 63

9 10 40 4
Latest Start
and
9 E 33
Latest Finish Times 24 Example 4.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12
I 27

15

0
A 12 12
F 22 63 K 69
12 10 63 69
6 Latest
finish
time
12
C 22 22
G 57
Start Finish
10 35

0
B 9 9
D 19 19
H 59 59
J 63

9 10 40 4
Latest Start
and
9 E 33
Latest Finish Times 24 Example 4.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12
I 27

15

0
A 12 12
F 22 Latest 63 K 69
12 10 start 63 69
6 Latest
time finish
time
12
C 22 22
G 57
Start Finish
10 35

0
B 9 9
D 19 19
H 59 59
J 63

9 10 40 4
Latest Start
and
9 E 33
Latest Finish Times 24 Example 4.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12 27
I
48 15 63

0
A 12 12
F
22 63 K 69
53 10 63 63 69
12 6

12
C 22 22
G 57
Start Finish
10 35

0
B 9 9
D 19 19
H 59 59 63
J

40 59 4 63
9 10
Latest Start
and
9 E 33
Latest Finish Times 24 Example 4.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12 27
I
48 15 63

0
A 12 12
F
22 63 K 69
53 10 63 63 69
12 6

12
C 22 22
G
57
Start Finish
10 24 35 59

0
B 9 9
D 19 19
H
59 59 63
J
19 40 59 59 4 63
9 10
Latest Start
and
9 E 33
Latest Finish Times 35 24 59
Example 4.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12 27
I
48 15 63

0
A 12 12
F
22 63 K 69
53 10 63 63 69
12 6

12
C
22 22
G
57
Start Finish
14 10 24 24 35 59

0
B 9 9
D
19 19
H
59 59 63
J
9 10 19 19 40 59 59 4 63
9
Latest Start
and
9 E 33
Latest Finish Times 35 24 59
Example 4.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12 27
I
Earliest start time Earliest finish time
48 15 63
Latest start time Latest finish time

0
A
12 12
F
22 63 K 69
2 12 14 53 10 63 63 69
6

12
C
22 22
G
57
Start Finish
14 10 24 24 35 59
Critical
path

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9
Latest Start
and
9 E 33
Latest Finish Times 35 24 59
Figure 4.7

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Gantt charts

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Gantt Charts

Figure 4.8
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12 27
I
48 15 63

0
A
12 12
F
22 63 K 69
2 12 14 53 10 63 63 69
6

12
C
22 22
G
57
Start Finish
14 10 24 24 35 59

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9

Activity Slack
9 E 33
Analysis 35 24 59
Example 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Activity
Adolf’s Slack
Hospital 12 27
I
48 15 63

0
A
12 12
F
22 63 K 69
2 12 14 53 10 63 63 69
6

12
C
22 22
G
57
Start
14 10 24 24 35 59 Finish

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9

Activity Slack
9 E 33
Analysis 35 24 59
Example 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Activity
Adolf’s Slack
Hospital 12 27
I
48 15 63
Slack = LS – ES
or 0
A
12 12
F
22 63 K 69
2 12 14 53 10 63 63 69
6
Slack = LF – EF

12
C
22 22
G
57
Start
14 10 24 24 35 59 Finish

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9

Activity Slack
9 E 33
Analysis 35 24 59
Example 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Activity
Adolf’s Slack
Hospital 12 27
I
48 15 63
SlackK = 63 – 63
or 0
A
12 12
F
22 63 K 69
2 12 14 53 10 63 63 69
6
SlackK = 69 – 69

12
C
22 22
G
57
Start
14 10 24 24 35 59 Finish

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9

Activity Slack
9 E 33
Analysis 35 24 59
Example 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Activity
Adolf’s Slack
Hospital 12 27
I
48 15 63
SlackK = 0
or 0
A
12 12
F
22 63 K 69
2 12 14 53 10 63 63 69
6
SlackK = 0

12
C
22 22
G
57
Start
14 10 24 24 35 59 Finish

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9

Activity Slack
9 E 33
Analysis 35 24 59
Example 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12 27
I
48 15 63

0
A
12 12
F
22 63 K 69
2 12 14 53 10 63 63 69
6

12
C
22 22
G
57
Start
14 10 24 24 35 59 Finish

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9

Activity Slack
9 E 33
Analysis 35 24 59
Example 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Node Duration ES LS Slack
St. Adolf’s Hospital 12 27
I
48 15 63

0
A
12 12
F
22 63 K 69
2 12 14 53 10 63 63 69
6

12
C
22 22
G
57
Start
14 10 24 24 35 59 Finish

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9

Activity Slack
9 E 33
Analysis 35 24 59
Example 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Node Duration ES LS Slack
St.
A Adolf’s
12 0 2 Hospital
2 12 27
I
B 9 0 0 0 48 15 63
C 10 12 14 2
D 10 9 9 0
E 24 9 35 26
A 12 F
0 12 22 63 K 69
F 10 12 53 41
2 12 14 53 10 63 63 69
G 35 22 24 2 6
H 40 19 19 0
I 15 12 48 36 C G
J 4 59 59 0 12 22 22 57
Start
14 10 24 24 35 59 Finish
K 6 63 63 0

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9

Activity Slack
9 E 33
Analysis 35 24 59
Example 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Node Duration ES LS Slack
St.
A Adolf’s
12 0 2 Hospital
2 12 27
I
B 9 0 0 0 48 15 63
C 10 12 14 2
D 10 9 9 0
E 24 9 35 26 F
12 22 63 K 69
F 10 12 53 41
53 10 63 63 69
G 35 22 24 2 6
H 40 19 19 0
I 15 12 48 36 C G
J 4 59 59 0 12 22 22 57
14 10 24 24 35 59 Finish
K 6 63 63 0

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9

9 E 33
Critical Path 35 24 59
Example 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital 12 27
I
48 15 63

0
A
12 12
F
22 63 K 69
2 12 14 53 10 63 63 69
6

12
C
22 22
G
57
Start Finish
14 10 24 24 35 59

0
B 9 9
D
19 19
H
59 59 63
J
0 9 10 19 19 40 59 59 4 63
9 9

9 E 33
Critical Path 35 24 59
Example 4.4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Activity Slack

Figure 4.9

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Cost-Time Relationships in Cost Analysis
8000 —

7000 —
Direct cost (dollars)

6000 —

5000 —

4000 —

3000 —

0—

| | | | | |
5 6 7 8 9 10 11

Figure 4.10 Time (weeks)


To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Cost-Time Relationships in Cost Analysis
8000 —

7000 — Crash cost (CC)


Direct cost (dollars)

6000 —

5000 —

4000 —

3000 —

0— Normal cost (NC)


| | | | | |
5 6 7 8 9 10 11
(Crash time) (Normal time)
Figure 4.10 Time (weeks)
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Cost-Time Relationships in Cost Analysis
8000 —

7000 — Crash cost (CC)


Direct cost (dollars)

Linear cost assumption


6000 —

5000 —

4000 —

3000 —

0— Normal cost (NC)


| | | | | |
5 6 7 8 9 10 11
(Crash time) (Normal time)
Figure 4.10 Time (weeks)
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Cost-Time Relationships in Cost Analysis
8000 —

7000 — Crash cost (CC)


Direct cost (dollars)

Linear cost assumption


6000 —
Estimated costs for
5000 —
5200 a 2-week reduction,
from 10 weeks to
4000 —
8 weeks
3000 —

0— Normal cost (NC)


| | | | | |
5 6 7 8 9 10 11
(Crash time) (Normal time)
Figure 4.10 Time (weeks)
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Maximum
Normal Normal Crash Crash Time Cost of
Time Cost Time Cost Reduction Crashing per
Activity (NT) (NC) (CT) (CC) (wk) Week

A 12 $ 12,000 11 $ 13,000 1 $ 1,000


B 9 50,000 7 64,000 2 7,000
C 10 4,000 5 7,000 5 600
D 10 16,000 8 20,000 2 2,000
E 24 120,000 14 200,000 10 8,000
F 10 10,000 6 16,000 4 1,500
G 35 500,000 25 530,000 10 3,000
H 40 1,200,000 35 1,260,000 5 12,000
I 15 40,000 10 52,500 5 2,500
J 4 10,000 1 13,000 2 1,000
K 6 30,000 5 34,000 1 4,000
Totals $1,992,000 $2,209,000

Table 4.1

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Path B-D-H-J-K: 69 weeks


Crash Activity J by 3 weeks @ $1,000/week

Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Path B-D-H-J-K: 69 weeks


Crash Activity J by 3 weeks @ $1,000/week
3($28,000) – 3($1,000) = $81,000
Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Path B-D-H-J-K: 66 weeks


Crash Activity J by 3 weeks @ $1,000/week
3($28,000) – 3($1,000) = $81,000
$2,624,000 – $81,000 = $2,543,000
Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000 $2,543,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Path B-D-H-J-K: 66 weeks


Crash Activity J by 3 weeks @ $1,000/week
3($28,000) – 3($1,000) = $81,000
$2,624,000 – $81,000 = $2,543,000
Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
I
Minimum Cost Schedule 15

A-I-K: 33 weeks B-D-H-J-K: 69 weeks


A-F-K: 28 weeks A B-E-J-K:
F 43 weeks
K
A-C-G-J-K: 67 weeks 12 10 6

Total cost = $2,624,000 $2,543,000


C G
Start Finish
Indirect costs = $8,000/week
10 35
Penalty cost = $20,000/week after week 65
B D H J
Critical Path B-D-H-J-K:
699 weeks
10 40 1

Crash Activity J by 3 weeks @ $1,000/week


E
24
3($28,000) – 3($1,000) = $81,000
$2,624,000 – $81,000 = $2,543,000

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
I
Minimum Cost Schedule 15

A-I-K: 33 weeks B-D-H-J-K: 69 weeks


A-F-K: A
28 weeks F B-E-J-K: K43 weeks
12 10 6
A-C-G-J-K: 67 weeks

Total cost = $2,624,000C $2,543,000


G
Start Finish
Indirect costs = $8,000/week
10 35

Penalty cost = $20,000/week after week 65


B D H J
9 10 40 1
Critical Path B-D-H-J-K: 69 weeks
Crash Activity J by 3 weeks @ $1,000/week
E
24
3($28,000) – 3($1,000) = $81,000
$2,624,000 – $81,000 = $2,543,000

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000 $2,543,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Path B-D-H-J-K: 66 weeks


Crash Activity D by 2 weeks @ $2,000/week

Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000 $2,543,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Path B-D-H-J-K: 66 weeks


Crash Activity D by 2 weeks @ $2,000/week
$28,000 + $8,000 – 2($2,000) = $32,000
$2,543,000 – $32,000 = $2,511,000
Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000 $2,511,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Path B-D-H-J-K: 64 weeks


Crash Activity D by 2 weeks @ $2,000/week
$28,000 + $8,000 – 2($2,000) = $32,000
$2,543,000 – $32,000 = $2,511,000
Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
I
Minimum Cost Schedule 15

A-I-K: 33 weeks B-D-H-J-K: 69 weeks


A-F-K: 28 weeks A B-E-J-K:
F 43Kweeks
A-C-G-J-K: 67 weeks 12 10 6

Total cost = $2,624,000 C$2,511,000


G
Start Finish
Indirect costs = $8,000/week
10 35

Penalty cost = $20,000/week after week 65


B D H J
Critical Path 9
B-D-H-J-K:
69 weeks 40
10 1

Crash Activity D by 2 weeks @ $2,000/week


E
24
$28,000 + $8,000 – 2($2,000) = $32,000
$2,543,000 – $32,000 = $2,511,000

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
I
Minimum Cost Schedule 15

A-I-K: 33 weeks B-D-H-J-K: 69 weeks


A-F-K: 28 weeks A F
B-E-J-K: 43Kweeks
10
A-C-G-J-K: 67 weeks12 6

Total cost = $2,624,000 C$2,511,000


G
Start Finish
Indirect costs = $8,000/week
10 35

Penalty cost = $20,000/week after week 65


B D H J
9 8 40 1
Critical Path B-D-H-J-K: 69 weeks
Crash Activity D by 2 weeks @ $2,000/week
E
24
$28,000 + $8,000 – 2($2,000) = $32,000
$2,543,000 – $32,000 = $2,511,000

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000 $2,511,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Paths B-D-H-J-K and A-C-G-J-K: 64 weeks


Crash Activity K by 1 week @ $4,000/week

Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000 $2,511,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Paths B-D-H-J-K and A-C-G-J-K: 64 weeks


Crash Activity K by 1 week @ $4,000/week
$8,000 – $4,000 = $4,000
$2,511,000 – $4,000 = $2,507,000
Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000 $2,507,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks


Crash Activity K by 1 week @ $4,000/week
$8,000 – $4,000 = $4,000
$2,511,000 – $4,000 = $2,507,000
Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
I
Minimum Cost Schedule 15

A-I-K: 33 weeks B-D-H-J-K: 69 weeks


A-F-K: 28 weeks A F
B-E-J-K: 43Kweeks
10
A-C-G-J-K: 67 weeks12 6

Total cost = $2,624,000 C$2,511,000


G
Start Finish
Indirect costs = $8,000/week
10 35

Penalty cost = $20,000/week after week 65


B D H J
9 8 40 1
Critical Path B-D-H-J-K: 69 weeks
Crash Activity D by 2 weeks @ $2,000/week
E
24
$28,000 + $8,000 – 2($2,000) = $32,000
$2,543,000 – $32,000 = $2,511,000

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
I
Minimum Cost Schedule 15

A-I-K: 33 weeks B-D-H-J-K: 69 weeks


A-F-K: 28 weeks A F
B-E-J-K: 43Kweeks
10
A-C-G-J-K: 67 weeks12 5

Total cost = $2,624,000 C$2,511,000


G
Start Finish
Indirect costs = $8,000/week
10 35

Penalty cost = $20,000/week after week 65


B D H J
9 8 40 1
Critical Path B-D-H-J-K: 69 weeks
Crash Activity D by 2 weeks @ $2,000/week
E
24
$28,000 + $8,000 – 2($2,000) = $32,000
$2,543,000 – $32,000 = $2,511,000

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000 $2,507,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks


Crash Activities B and C by 2 weeks
@ $7,000/week and $600/week

Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000 $2,507,000


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Paths B-D-H-J-K and A-C-G-J-K: 63 weeks


Crash Activities B and C by 2 weeks
@ $7,000/week and $600/week
2($8,000) – 2($7,600) = $800
$2,507,000 – $800 = $2,506,200 Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Minimum-Cost Schedule
A-I-K: 33 weeks B-D-H-J-K: 69 weeks
A-F-K: 28 weeks B-E-J-K: 43 weeks
A-C-G-J-K: 67 weeks

Total cost = $2,624,000 $2,506,200


Indirect costs = $8,000/week
Penalty cost = $20,000/week after week 65

Critical Paths B-D-H-J-K and A-C-G-J-K: 61 weeks


Crash Activities B and C by 2 weeks
@ $7,000/week and $600/week
2($8,000) – 2($7,600) = $800
$2,507,000 – $800 = $2,506,200 Example 4.5

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
I
Minimum Cost Schedule 15

A-I-K: 33 weeks B-D-H-J-K: 69 weeks


A-F-K: 28 weeks A F
B-E-J-K: 43Kweeks
10
A-C-G-J-K: 67 weeks12 5

Total cost = $2,624,000 C$2,511,000


G
Start Finish
Indirect costs = $8,000/week
10 35

Penalty cost = $20,000/week after week 65


B D H J
9 8 40 1
Critical Path B-D-H-J-K: 69 weeks
Crash Activity D by 2 weeks @ $2,000/week
E
24
$28,000 + $8,000 – 2($2,000) = $32,000
$2,543,000 – $32,000 = $2,511,000

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
I
Minimum Cost Schedule 15

A-I-K: 33 weeks B-D-H-J-K: 69 weeks


A-F-K: 28 weeks A F
B-E-J-K: 43Kweeks
10
A-C-G-J-K: 67 weeks12 5

Total cost = $2,624,000 C$2,511,000


G
Start Finish
Indirect costs = $8,000/week
8 35

Penalty cost = $20,000/week after week 65


B D H J
7 8 40 1
Critical Path B-D-H-J-K: 69 weeks
Crash Activity D by 2 weeks @ $2,000/week
E
24
$28,000 + $8,000 – 2($2,000) = $32,000
$2,543,000 – $32,000 = $2,511,000

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Coors Field

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Probabilistic Time Estimates

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Probabilistic Time Estimates
Probability

Time

Figure 4.11
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Probabilistic Time Estimates
Probability

Time
a m b
Mean
Figure 4.11 (a)
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Probabilistic Time Estimates

Area under curve


between a and b
is 99.74%
Probability

3σ 3σ Time
a m b
Mean
Figure 4.11 (b)
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilistic I

Time Estimates
A F K

Start C G Finish

B D H J

Example 4.6
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilistic I

Time Estimates
A F K

Activity B
Most Start C G Finish
Optimistic Likely Pessimistic
(a) (m) (b)
B D H J
7 8 15

Example 4.6
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilistic I

Time Estimates
A F K

Activity B
Most Start C G Finish
Optimistic Likely Pessimistic
(a) (m) (b)
B D H J
7 8 15

7 + 4(8) + 15 E
te = = 9 weeks
6

Example 4.6
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilistic I

Time Estimates
A F K

Activity B
Most Start C G Finish
Optimistic Likely Pessimistic
(a) (m) (b)
B D H J
7 8 15

7 + 4(8) + 15 E
te = = 9 weeks
6

( 15 - 7
)
2
σ 2
= = 1.78
6
Example 4.6
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Time Estimates (wk) Activity Statistics
Optimistic Likely Pessimistic Expected Variance
Activity (a) (m) (b) Time (te ) (σ 2 )

Example 4.6
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Time Estimates (wk) Activity Statistics
Optimistic Likely Pessimistic Expected Variance
Activity (a) (m) (b) Time (te ) (σ 2 )
A 11 12 13 12 0.11
B 7 8 15 9 1.78
C 5 10 15 10 2.78
D 8 9 16 10 1.78
E 14 25 30 24 7.11
F 6 9 18 10 4.00
G 25 36 41 35 7.11
H 35 40 45 40 2.78
I 10 13 28 15 9.00
J 1 2 15 4 5.44
K 5 6 7 6 0.11
Example 4.6
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days

Example 4.7
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
T –TE
σ 2
= Σ (variances of activities) z =
σ 2

Example 4.7
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
T – TE
σ 2
= Σ (variances of activities) z =
σ 2

σ 2
= 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

Example 4.7
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
T – TE
σ 2
= Σ (variances of activities) z =
σ 2

σ 2
= 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

72 – 69
z=
11.89

Example 4.7
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
T – TE
σ 2
= Σ (variances of activities) z =
σ 2

σ 2
= 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

72 – 69
z= = 0.87
11.89

Example 4.7
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilities
Critical Path = B - D - H - J - K
T = 72 days TE = 69 days
T – TE
σ 2
= Σ (variances of activities) z =
σ 2

σ 2
= 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

72 – 69 From Appendix 2
z= = 0.87 Pz = .8078 ≈ .81
11.89

Example 4.7
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilities
Normal distribution:
Critical Path
Length of = B - D - H - J - K= 69 weeks;
Mean
critical path σ = 3.45 weeks
T = 72 days TE = 69 days
Probability of T - TEof
σ 2
=Σ (variances
meeting the of activities) Probability
z exceeding
= 72
weeks is σ
schedule is 2
0.8078 0.1922

σ 2
= 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

72 - 69 69 72
z= = 0.87
11.89 Project duration (weeks)
Figure 4.12

Example 4.7
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Probabilities
Path = A - C - G - J - K
T = 72 days TE = 67 days
T – TE
σ 2
= Σ (variances of activities) z =
σ 2

σ 2
= 0.11 + 2.78 + 7.11 + 5.44 + 0.11 = 15.55

72 – 67 From Appendix 2
z= = 1.27 Pz = .8980 ≈ .90
15.55

Example 4.7
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
I

A F K

Start C G Finish

B D H J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
St. Adolf’s Hospital
Activity Duration Earliest Start Latest Start Slack

C 10 16 14 –2
G 35 26 24 –2
J 4 61 59 –2
K 6 65 63 –2
D 10 10 9 –1
H 40 20 19 –1
E 24 10 35 25
I 15 16 48 32
F 10 16 53 37

Table 4.2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Project Life Cycle

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Project Life Cycle
Resource requirements

Start Finish
Time
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Project Life Cycle
Definition Planning Execution Close out
and
organization
Resource requirements

Figure 4.13 Start Finish


Time
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Solved Problem 1

A D
4 6

G
4
Finish
B E
Start
7 3
H
3

C F
5 11

Figure 4.14

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Solved Problem 2

D Finish

A E

Start C G

Figure 4.15(a)

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Solved Problem 2

D
1 Finish

A Dummy

G
Start 3
E
B C

F
2 F

Figure 4.15(b)

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Solved Problem 2
D
4.0 16.0
Finish
8.0 20.0
12.0
A E
0.0 4.0 9.0 15.5
4.0 8.0 9.0 15.5
4.0 6.5

C
Start 5.5 9.0
5.5 9.0
3.5

B G
0.0 5.5 15.5 20.0
0.0 5.5 15.5 20.0
5.5 4.5

F
5.5 14.5
6.5 15.5
9.0 Figure 4.16

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.
Solved Problem 2
D
4.0 16.0
Finish
8.0 20.0
12.0
ES EF
A E
0.0 4.0 LS LF 9.0 15.5
4.0 8.0 9.0 15.5
4.0 6.5

C 0 4
Start 5.5 9.0
5.5
3.5
49.0 8 1
B
A G
0.0 5.5 15.5 20.0
0.0 5.5 15.5 20.0
5.5 4.5
Start
F
5.5 14.5
6.5 15.5
9.0 Figure 4.16

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition © 2002 Prentice Hall, Inc. All rights reserved.