Assly Code Assly name
Action Plan
Cause 17-18 18-19 19-20 Action taken
Water Pump 02 00 01 All gear failed due to breakage of teeth of water pump.
Gear Teeth Reports of all failures sent to DMW/PTA for further
Broken analysis. DPT of gear is being done before fitment.
Hardness of gear teeth being checked before fitment.
Backlash of Water Pump Gear being checked at
supervisor level.
Gear sound being checked in every schedule &
corrective action taken, if required.
Additional lubrication connection for water pump gear
train provided.
Water pump 01 01 00 Run out of mating ring & shaft is being checked and water
seal Failure pump tested on test stand before giving on locomotive.
Water pump 01 00 00 Letter sent to POH/CB regarding improper fitment of
shaft key worn impeller on shaft with key.
out
Action Plan
Cause 17-18 18-19 19-20 Action taken
Water pump 01 00 01 Letter sent to firm for bad quality of the material.
bearing failure
Radiator core 02 02 00 Internal tube cleaning of radiator by specified cleaning
tube puncture agent & hydraulic testing is being done at 2.5 Kg/cm2
press. & 90oC Temp.
Proper checking of radiator fan’s jaali (Top & bottom)
along with all clamps is being done in every sch. and
condition of jaali is being ensured during fitment of
radiator fan.
Radiator fan 02 00 00 DPT of radiator fan blade is being done before fitment
blade broken on loco.
Play in Radiator fan bearing is being checked in every
schedule.
Action Plan
Cause 17-18 18-19 19-20 Action taken
Armoured joint, Pipe 08 05 03 Shelf life of gaskets, pipeline alignment & proper
line Gasket Joint , clamping being ensured.
Water jumper ‘O’ Ensuring clamping at both ends of armoured joint
Ring, Water header A test stand has been made to train staff for armoured
pipe, Water riser joint fitment.
crack, Bubble Cleaning & annealing of copper pipes being done
collector/ copper before fitment.
pipe broken/Flexible Shelf life of water riser i.e. 08 years being maintained
Pipe burst during M24 & above schedules.
Shelf life of flexible pipes also being ensured during
fitment on loco.
Proper cleaning , checking & DPT testing of water risers
is being done before fitment during major sch.
Expansion tank 04 02 01 Water leakage/ seepage from expansion tank is
crack/Pressurisation checked in every schedule by striking with the rubber
cap defective hammer.
During M24 schedule expansion tank bottom plate is
checked for corrosion by cutting on roof & corrective
action taken .
Misc. 00 02 01
----------------------------------------------------------
Air Brake System
Action Plan – Air Brake System
Year Nos.
2017-18 22
2018-19 15
2019-20 (up to June) 04
Action Plan
Cause 17-18 18-19 19-20 Action taken
Air pipe, 05 04 01 Proper clamping of pipe line being ensured in every schedule.
Horn Leakages of pipeline, flange, threads & horn etc being checked &
leakage/c attended in every schedule.
rack/ BP/ FP protection plate fitted in every loco & checked in every
Broken/A schedule to prevent the breakage of angle cock.
ngle cock Proper clamping being done near dresser joint of air flow measuring
valve outlet pipe.
Counseling of all staff regarding brake pipe dresser joint in control
stand is to be changed in M48 Sch. & to ensure tightness & any
leakage in every sch.
Valves 04 06 01 Staff counseled for proper cleaning before overhauling the valves.
Stick up/ Valves being checked in every schedule.
Defective Staff counseled for proper fitment and alignment of valves and their
respective gaskets.
Action Plan – Air Brake System
Cause 17-18 18-19 19-20 Action taken
Air dryer purge 01 02 01 Additional grill fitted above the purge valve to prevent the
valve/Auto ingress of desiccant particles.
drain valve Air dryer bypass arrangement provided to prevent line
defective failure.
C3W Distributor 03 00 00 C3W distributor valve being properly cleaned & overhauling
valve mal- being done with new kit only.
functioning Over due C3W distributor valve monitoring being done &
changed on priority basis.
Letter sent for counseling of loco pilot regarding “do not
tempered the valves during running”.
BP Gage 01 00 00 BP gauge reading is being matched with DID panel reading in
defective every Sch.
In M12 & above Sch. all gages being calibrated on calibration
test stand.
CCB failure/Air 03 01 00 Air leakage from CCB panel & valves are being checked in
leakage from every sch.
CCB Panel/stick 6 Yearly sch. of CCB 1.5 of loco no. 16521 competed in
up of CCB Dec’18 at IZN/Shed
valves
Misc. & CRO 05 02 01 --------------------------------------------------------------------
Fuel Oil System
Action Plan – Fuel Oil System
Year Nos.
2017-18 14
2018-19 14
2019-20 (up to June) 01
Action Plan
Cause 17-18 18-19 19-20 Action Plan
Breakage of Fuel 01 02 01 FP inlet screw torquing schedule has been reduced
Pump Inlet & being done during M2 schedule.
mounting Projection of gasket over FP inlet being ensured.
screw/gasket Fuel jumper bolts are replaced during M12 and
above schedule.
failure & leakage
from banjo bolt
Filter Choking 03 02 00 HSD Tank cleaning during M24 Schedule is being
and Housing ensured.
crack Monitoring of O/Due filter is being done.
DPT of S/Filter housing being done during sch.
Letter sent to concerned RDI regarding bad fueling
(Water contamination)
Action Plan – Fuel Oil System
Cause 17- 18- 19- Action taken
18 19 20
Leakage from 03 02 00 Sleeves on pipes being provided to prevent rubbing.
Pipe Line/HSD Pipes renewed during major schedules.
Glow rod Fuel cross over pipes removed & hydraulic testing done during M4 sch.
gauge/HSD Counseling of technicians is done regarding proper fitment &
tank alignment of HSD glow rod.
HSD tank inspection cover gkt. Is being changed during M24 &
onward.
Fuel Header 02 00 00 Tightness of fuel header mounting bolt checked in every sch.
Adaptor Thread condition of fuel header and adopter being ensured before
Leakage/Break fitting.
age Cleaning of fuel header being done during M24 Sch. & ensuring no
foreign particle inside the header at supervisor level.
Rel. /Reg. 03 03 00 Test cock pressure & delivery being checked in M2 sch. for monitoring
Valve defective of performance of the valves.
In case of any pressure difference, cause identified and corrective
action taken.
Fuel buster 02 00 00 Letter sent to firm (DEC-PUNE) for bad quality of the material &
pump warranty replacement as failed within 02 months.
defective.
2017-18 03 10 13
2018-19 08 05 13
2019-20 (up to June) 00 01 01
Action Plan-Cable & Lug
Condition of power and control circuit cables & wires with wire lug
terminals being checked during M-4 and above schedules.
Proper securing of power and control cables being done during M-4
and above schedules.
Critical location lugs, terminal board connections and wire lug
terminal tightness being ensured during M-12 and above
schedules.
Checking and securing of AF-1 & AF-2 cables of TA being ensured
during M-4 and above schedule.
Proper securing of power and control circuit harness with the help
of insulating tape & ties being ensured with renewal of critical
location wire lug terminals on condition basis during M-24 and
above schedules.
Relay & Contactors
Action Plan – Relay & Contactors
Year Nos.
2017-18 10
2018-19 14
2019-20 (up to June) 02
Action Plan
Cause 17-18 18-19 19-20 Action taken
Master 02 00 00 Master controller finger interlock contact
Controller pressure being checked during M2 & above Sch.
Defective. Stick type master controller being overhauled
during M4 & above Sch.
Collar of accelerating shaft cleaning & checking
of cam profile being done during M2 & above
Sch.
Operating coil 00 00 00 Operating coil condition checked during M24 &
burnt & open above Sch. & renewed on condition basis.
circuit FPC Coil value measurement is being done
during M4 & above. Sch.
Action Plan – Relay & Contactors
Action Plan
Cause 17-18 18-19 19-20 Action taken
Reverser, BKT & 04 12 00 A test bench for checking contact pressure of
GF, Cranking electromagnetic contactor developed.
Contactor, Aux. Ensuring cleaning of reverser & contactors
contactor, FPC during M2 and above sch.
Defective & Gov. Ensuring wiping action of electro magnetic
control unit contactors during M-2 and above schedules.
During A/E after POH, CK1, CK2 & CK3
contactors being checked on test stand.
Proper working of governor control unit &
reverser contactor is checked in every sch.
Malfunctioning 04 01 02 Proper attention being given during Sch. Work
of Relays & for preventing ingress of foreign material like
Contactors, washer, bolt, nut etc. between contacts.
Master Roof sealing is being done on drive basis to
controller etc prevent the water ingress during rainy weather.
Misc 00 01 00 Nothing found abnormal in data downloading.
Injection System
Action Plan – Injection System
Year Nos.
2017-18 09
2018-19 16
2019-20 (up to June) 00
Action Plan
Cause 17-18 18-19 19-20 Action taken
OSTA Plunger 03 09 00 OSTA plunger being Zyglo tested.
broken /Check nut RPM of OSTA plunger being adjusted on test bench only and OSTA
work out/OST RPM being checked M2 sch. onwards.
tripping/Stud broken
Control Shaft Jam 03 02 00 OSTA dog gap being maintained in order to ensure full & free rack
movement.
Play in between pin and shaft, dog & its key etc being checked
during every sch. and corrected if found.
Free movement of control shaft being checked in every sch. &
ensured at supervisor level.
FIP holder /Bottom 01 00 00 Over-tightness of HP tube bottom nut prohibited.
collar/ foundation New snubber valve being fitted during M24 & condition checked
bolt broken during M12 sch.
FIP foundation bolt’s depth in FIP support is being checked for
uniform size before fitment on loco during M24 & above sch.
HP Tube broken/ 02 05 00 Counseling of staff done regarding over-tightness of nut & proper
Bottom nut crack care taken for alignment during fitment of the HP tube.
HP tubes are properly overhauled & tested in OVH sec.
Lube Oil System
Action Plan – Lube Oil System
Year Nos.
2017-18 11
2018-19 11
2019-20 (up to June) 01
Action Plan
Cause 17-18 18-19 19-20 Action taken
Armoured/Dresser 01 04 00 Shelf life of gaskets, pipeline alignment & proper
/ Victaulic joint clamping being ensured.
leakage/Regulating Ensuring clamping at both ends of armoured joint
& relief valve. A test stand has been made to train staff for
armoured joint fitment.
Correct gap and alignment being ensured in lube oil
strainer outlet armoured joint in M-24 Schedule.
Rigid pipe / 06 01 00 • DPT done after welding of pipe lines before fitting in
Copper pipe joint Loco.
leakage/ crack • Lube oil outlet ‘Z’ pipe is being changed with new one
during M24 sch. & above.
• Proper annealing of copper pipes is being done
before fitment.
Lube oil leakage 00 00 01 • Letter sent to DMW/PTA to improve quality of
from delivery joint. material.
Action Plan – Lube Oil System
Cause 17-18 18-19 19-20 Action taken
Leakage 01 02 00 Counselling of BG major mechanical staff done regarding proper
from pipe fitment of pipe line and it’s connector/cone.
line
Leakage 00 02 00 In every sch. leakage is being checked at higher temp.
from self Foundation bolt tightness of self centrifuge & its bracket being
centrifuge checked in every sch.
& PTLOC Lube oil leakage from PTLOC plate & gasket is to be ensured in
every sch.
Lube oil 00 01 00 Staff counselled for proper cleaning of engine sump during
pump M24/M48 Schedule and strictly prohibited use of any wooden
defective/ patches during fitment of LO pump.
Gear teeth
broken
Lube oil 01 01 00 Counselled all staff for lube oil filter drum ‘O’ ring groove
filter drum checking regarding depth, width & any sharp edge and proper
‘O’ ring tightness and torquing of fly nuts
leakage
Misc. 02 00 00
-------------------------------------------------------------------
Traction Motor
Action Plan – Traction Motor
Year Nos.
2017-18 08
2018-19 06
2019-20 (up to June) 04
Action Plan
Cause 17-18 18-19 19-20 Action taken
Brg. seizure & 00 02 00 PE end bearing NU-330 being changed during M48 Sch.
retaining Shock pulse meter and vibration meter being used during M24 & above Sch.
collar out. for bearing condition detection.
Retaining collar position being checked during M12 & above Sch.
Carbon brush 3 01 01 Special attentions are being given and counseling done for proper carbon
holder brush fitment, pig tail securing, ensuring proper sleeve, condition of brushes &
failure/epoxy epoxy glass sheet etc.
glass sheet Carbon brush holder and its insulating stud condition being checked during
damaged. M4 and above sch.
Armature 04 03 03 Ovality correction of the TM armature being done during M-24 schedule
failure/ and complete overhauling during M-48 schedule.
Interpole IR Hi-potential test, Millivolt drop test, resurfacing of the commutator being
done in M48 Sch.
less.
TM light run test is being done during M-24 and out of course changing.
Complete bogie light run test and ovality correction is being done in out of
course changing.
Misc. 01 00 00 During checking nothing found, precautionary TM changed.
Cam shaft/Crank shaft
Action Plan – Cam shaft/Crank shaft
Year Nos.
2017-18 05
2018-19 01
2019-20 (up to June) 02
Action Plan
Cause 17-18 18-19 19-20 Action taken
Cam gear/Split 03 00 00 •Cam gear temp. measured in every Sch. & necessary action
gear teeth taken if required.
broken • Backlash of cam gear checked at supervisor level.
• Molycot powder used between teeth of gear train during
fitment.
• Spray nozzle cleaning done in M4 & above Sch.
• Cam gear removed during M24 Sch. and fitted after DPT.
• Letter sent to DMW/PTA to improve quality of material.
Cam 02 00 00 •Letter sent to DMW/PTA & RDSO LKO to improve quality of
shaft/Crank material.
shaft broken. • Warranty claim of power pack logged on DMW/PTA as new
power pack was received on 04/2017
Cam shaft 00 01 02 • Counselling of staff for proper tightening of cam shaft
flange joint flange joint bolts were done.
bolt broken
Compressor / Expressor
Action Plan – Compressor / Expressor
Year Nos.
2017-18 04
2018-19 01
2019-20 (up to June) 00
Action Plan
Cause 17-18 18-19 19-20 Action taken
Improper 03 00 00 • To ensure proper checking and cleaning of compressor
cleaning of drain sump during M4 sch. & onward.
passage during • To ensure proper checking of ‘S’ Pipe cones and
sump sch. & annealing of ‘S’ Pipe during M-12 schedule & onward.
checking oil level • Proper cleaning & checking of oil level indicator is to be
indicator ensured during sump sch. & oil filling.
Fast coupling 01 01 00 • Proper alignment of compressor is to be ensured during
gear teeth & M24 & onward.
inter cooler fan • Cardium compound filling in fast coupling is to be
blade breakage ensured.
• Proper cleaning & DPT of inter cooler fan is to be
ensured before fitment during M24 sch. and onward.