• OBJECTIVES
– Definition of Project Management
– Structuring Projects
Activity 1
Activity 2
Activity 3
Activity 4
Activity 5
Activity 6
Time
Horizontal Axis: Always Time
Projects Forms
Pure Project
A pure project is where a self-contained team works full-
time on the project
Pure Project: Advantages
• The project manager has full authority over
the project
• Team members report to one boss
• Shortened communication lines
• Team pride, motivation, and commitment
are high
Projects Forms
Pure Project: Disadvantages
• Duplication of resources
• Organizational goals and policies are ignored
• Lack of technology transfer
• Team members have no functional area
"home"
Projects Forms
Functional Project
A functional project is housed within a
functional division
President
Research and
Engineering Manufacturing
Development
Research and
Engineering Manufacturing Marketing
Development
Manager
Project A
Manager
Project B
Manager
Project C
Projects Forms
Matrix: Advantages
• Enhanced communications between functional
areas
• Pinpointed responsibility
• Duplication of resources is minimized
• Functional “home” for team members
• Policies of the parent organization are followed
Projects Forms
Matrix: Disadvantages
• Too many bosses
1 Project 1 Project 2
E(5)
Determine early starts ES=4
and early finish times EF=6
LS=4
LF=9
ES=4
Critical Path & Slack EF=6
Slack=(7-4)=(9-6)= 3 Wks
LS=4
LF=9
Duration=15 weeks
Example 2. CPM with Three Activity
Time Estimates
Immediate
Task Predecesors Optimistic Most Likely Pessimistic
A None 3 6 15
B None 2 4 14
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
Example 2. Expected Time Calculations
ET(A)= 3+4(6)+15
6
Immediate Expected
Task Predecesors Time
A None 7 ET(A)=42/6=7
B None 5.333
C A 14 Immediate
Task Predecesors Optimistic Most Likely Pessimistic
D A 5 A None 3 6 15
E C 11 B None 2 4 14
C A 6 12 30
F D 7 D A 2 5 8
E C 5 11 17
G B 11 F D 3 6 15
H E,F 4 G B 3 9 27
H E,F 1 4 7
I G,H 18 I G,H 4 19 28
A(7) H(4)
D(5) F(7)
I(18)
B G(11)
(5.333)
Example 2.
Probability Exercise
What is the probability of finishing this project in
less than 53 days?
p(t < D)
D=53
t
TE = 54
Example 2.
Probability Exercise
The probability of D - TE
finishing this project in Z =
less than D days? First
cp
2
determine Z by :-
t
D=53 TE = 54
D - TE 53 - 54
Z = = = -.156
cp
2 41
p(t < D)
t
TE = 54
D=56
D - TE 56 - 54
Z = = = .312
cp
2 41