METHODE OF BRIDGE

RRDP LOAN NO.2817-INO


PACKAGE : 34-RCP-03
Sequence of Bridge Works
Preparation

Mobilization Pile pipe


delivery
Clearing and matras
Setting
neccesary accord.
Equipment
Elevation of design

Pilling

Abutment

Girder +
diafragm

Deckslab, Trotoar and


railling

Oprit
embankment

Aspalt
pavement
MATRAS OF PILING ELEVATION

2.3 m

12.0 M (minimal)
PILING WORK

12.0 M (minimal)
PILING WORK

12.0 M (minimal)
ILUSTRATION OF PILING WORK

Area pancang
12 x 18 m2

5M

9 M (min)
Pilling Equipment
4 M (min)

12 M
ILUSTRATION OF PILING WORK

Pilling Equipment 5M

9 M (min)

4 M (min)

12 M
ILUSTRATION OF PILING WORK

Pilling Equipment

5M

9 M (min)

4 M (min)

12 M
ILUSTRATION OF PILING WORK

Pilling Equipment

5M

9 M (min)

4 M (min)

12 M
ILUSTRATION OF PILING WORK

5M

9 M (min)
Pilling Equipment
4 M (min)

12 M
FOOTING EXCAVATION

11.00 M (min)

2.8 M
ABUTMENT STRUCTURE
AND WING WALL

1. Lean concrete
2. Cutting pile ( if neccesary)
3. Concreting in pipe
4. Rebar, form work of Abutment
5. Concreting of
Abutment
6. Rebar and
formwork of wing
Wingwall
wall
7. Curing time
before girder
intallation
COMMON EMBANKMENT

Layer by layer 95 % compacton


Top layer 100 % compaction
INSTALLATION GIRDER AND DIAFRAGM

Install girder
Including grouting pad,
bearing pad
And diafragm
Pouring concrete of deckslab
and concrete conductor

Deck-slab (including rebar,


formwork and deck drain)
Conductor Concrete
(including rebar,
formwork and anchorage)
Deckslab, barrier, railling
toping of wingwall

Deck slab : including deck plat, rebar, install deck drain


Barrier and Railling
Trotoar (pedestrian road)
Toping of wingwall
Asphalt and road marking