PROJECT REVIEW-AMI SOLUTION

SMART METERING-MEERUT
10-MAR-19

L&T CONSTRUCTION | SMART WORLD & COMMUNICATION | SECURITY SOLUTIONS


Meter Installation & Data Verification Status As on
Feb’19

Total No. of MI Data MI Data Old Meter Balance to be


DIVISION CI Completed MI Completed Verification By Verification By Submission to Submitted (Old
Consumer L&T DISCOM DISCOM Meters)

EUDD I 26454 0 0 0 0 0 0

EUDD II 63624 52882 0 0 0 0 0

EUDD III 60201 57542 9528 9508 9506 4890 4638

Grand Total 1,36,666 1,10,424 9,528 9,508 9,506 4,890 4638

L&T CONSTRUCTION | SMART WORLD & COMMUNICATION | SECURITY SOLUTIONS


Meter Installation & Data Verification Status As on
09/03/19

Total No. of MI Data MI Data Old Meter Balance to be


DIVISION CI Completed MI Completed Verification By Verification By Submission to Submitted (Old
Consumer L&T DISCOM DISCOM Meters)

EUDD I 26454 0 0 0 0 0 0

EUDD II 63624 61654 0 0 0 0 0

EUDD III 60201 57694 9887 9862 9506 7420 2108

Grand Total 1,36,666 1,19,348 9,887 9,862 9,506 7,420 2.108

L&T CONSTRUCTION | SMART WORLD & COMMUNICATION | SECURITY SOLUTIONS


Weekly Target of Meter Installation-Mar to Jun’19
Sl. Week-1 Week-2 Week-3 Week-4 Total

Month
No. of Man No. of MI No. of Man No. of MI No. of Man No. of MI No. of Man No. of MI
No. Power Per Per Day MI Target Power Per Per Day MI Target Power Per Per Day MI Target Power Per Per Day MI Target No. of MD MI Target
Day Day Day Day

1 Mar'19       45 200 1200 56 250 1500 113 500 3000 213.8 3000

2 Apr'19 120 533 3200 188 833 5000 188 833 5000 188 833 5000 683 18200

3 May'20 188 833 5000 188 833 5000 203 900 5400 203 900 5400 780 20800

4 Jun'19 188 834 5001 188 833 5000 203 900 5400 203 900 5400 780 20800

TOTAL     13201     15000     15800     15800 2243 59800

L&T CONSTRUCTION | SMART WORLD & COMMUNICATION | SECURITY SOLUTIONS


Support Required from DISCOM
1. Consumer awareness program is required

2. Required the availability of DISCOM JE's/Line man at Site

3. Armored Cable to be laid in advance and Feeder wise clearance to be given

4. Schedule Shutdown to be informed in advance.

5. Power failure to be maintained wherever MI work will be going.

4. Dicom/Vigilence Team/Police Protection is required in Vikas Puri Area and wherever required for MI

Post Meter Installation Issues


1. No Power complaint

2. Loose Connection from Pole


5

L&T CONSTRUCTION | SMART WORLD & COMMUNICATION | SECURITY SOLUTIONS


6

L&T CONSTRUCTION | SMART WORLD & COMMUNICATION | SECURITY SOLUTIONS