Sie sind auf Seite 1von 23

Alabang Medical Clinic - 100

PHASE 2 - Weekly Report


WEEKLY ACCOMPLISHMENT
February 21, 2020
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE 2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

PAINTING AND SKIMCOATING AT FIRE EXIT AND MAINSTAIR


PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE 2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

MANPOWER:
PIC – 1
PE – 1
SEC – 1
MEPFS- 1
SAFETY OFFICER- 1
FOREMAN – 1
WAREHOUSEMAN – 1
MAINTENANCE - 1
TILING WORKS - 15
WALL / CEILING WORKS- 3
ELECTRICAL WORKS - 4
CIVIL WORKS - 6
DIETARY- 6
GUARDS - 2
TOTAL 44
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE 2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

EQUIPMENT:
LIFTING HOIST – 1
TOTAL 1

INCOMING EQUIPMENT
MOBILE CRANE 1
MINI LOADER 1
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE
2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

AMC 100 PHASE 2


DURATION 224 DAYS

START JAN 6, 2020


COMPLETION SEP 6, 2020
PREVIOUS TO DATE
SCHEDULE 4.7% 7.14%
ACTUAL 4.9% 8.22%
VARIANCE (+/-) +1.08%

VARIANCE = 1.08% X 224 DAYS = 2.49 DAYS


ADVANCED
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE 2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

PROJECT NAME : Phase 2 - AMC Alabang 100


LOCATION Wawa st. Brgy. Alabang, Muntinlupa City
SUBJECT S-Curve / Bar Chart
DATE: Thursday, February 20, 2020

January February March


ITEM NO. DISCRIPTION AMOUNT % WEIGHT W1 W2 W3 W4 W1 W2 W3 W4 W1 W2
1 2 3 4 5 6 7 8 9 10
Part 1 General Requirements
A1.1 Temporar y U tilities (Water, Electric & Telephone) 280,000.00 0.30% 0.0 0009 0.00 009 0.00 009 0.00 009 0.0 000 9 0 .000 09 0.00 009 0.00 009 0.0000 9 0 .00 009
A1.2 Serv ice/ Equipments/Deliv ery 85,000.00 0.09% 0.0 000 8 0 .000 08 0.00 008 0.00 008 0.0000 8 0 .00 008
A1.3 As-built Plan 100,000.00 0.11%
A1.4 Safety /Security Provision 140,000.00 0.15% 0.0 0005 0.00 005 0.00 005 0.00 005 0.0 000 5 0 .000 05 0.00 005 0.00 005 0.0000 5 0 .00 005
A1.5 Scaffolding 85,000.00 0.09% 0.0 000 8 0 .000 08 0.0000 8 0.00 008 0 .00 008 0 .0 0008
A1.6 Lay -out 50,000.00 0.05% 0.0 0007 0.00 007 0.00 007 0.00 007 0.0 000 7 0 .000 07 0.00 007 0.00 007
A1.7 Superv ision 250,000.00 0.27% 0.0 0008 0.00 008 0.00 008 0.00 008 0.0 000 8 0 .000 08 0.00 008 0.00 008 0.0000 8 0 .00 008

Part II Architectural Works


Part A Architectural
A.1 Wall Partition 13,332,034.01 14.20% 0 .0 0747
A.2 Painting Works 9,171,746.70 9.77% 0.00 407 0 .00 407 0 .0 0407
A.3 Floor Finishes 6,500,000.00 6.92% 0 .004 94 0 .004 94 0.00 494 0.0049 4 0.00 494 0 .00 494 0 .0 0494

Part B Plumbing Works (excluding fi xt. and Pumps)


B.1 Water Li ne s 8,947,811.47 9.53% 0.0 079 4 0.00 794 0.0079 4 0.00 794 0 .00 794 0 .0 0794
B.2 Sewer, Waste & Vent System 4,418,634.44 4.71% 0.0039 2 0.00 392 0 .00 392 0 .0 0392
B.3 Medical / Laboratory Waste Pipes 472,676.89 0.50% 0 .0 0046
B.4 Kitche n Waste 480,805.57 0.51%
B.5 Septi c Tank 598,136.21 0.64% 0.00 064 0 .00 064 0 .0 0064
B.6 Storm Drainage Syste m 3,132,773.02 3.34%
B.7 Equipme nts and Controlle rs 258,405.00 0.28%
B.8 Plumbing Fixtures and Accessories 622,017.75 0.66%
B.9 Others 86,135.00 0.09%

Part C Fire Protection (Pumps and Equipments Exc)


C.1 Pipes & Fitti ngs 7,749,113.35 8.25% 0.0 051 6 0 .005 16 0.00 516 0.00 516 0.0051 6 0 .00 516
C.1 Sprinkle rs 579,326.78 0.62% 0 .00 036 0 .0 0036
C.3 Valves and Other Device s 861,604.71 0.92%
C.4 Fle xible Connectors 18,752.20 0.02%
C.5 Others 980,128.93 1.04%

Part D Auxillary Works (Rough-ins)


D.1 Paging Syste m 324,288.74 0.35% 0 .00 018 0 .0 0018
D.2 CCTV 1,575,553.28 1.68% 0 .00 088 0 .0 0088
D.3 FDAS 639,345.34 0.68% 0 .00 036 0 .0 0036
D.4 CATV 446,393.71 0.48% 0 .00 025 0 .0 0025
D.5 DATA 609,415.89 0.65% 0 .00 034 0 .0 0034
D.6 TELEPHONE 442,388.74 0.47% 0 .00 025 0 .0 0025
D.7 Nurse Call Syste m 446,057.17 0.48% 0 .00 025 0 .0 0025

Part E Electrical Works


E.1 Lighting System 3,324,068.39 3.54% 0.0 019 7 0 .001 97 0.00 197 0.00 197 0.0019 7 0 .00 197
E.2 Lighting Fixtures 1,133,275.08 1.21%
E.3 Power System 19,064,634.58 20.30%
E.4 Panel Boards & Other Equipments 5,058,866.14 5.39%
E.5 Fitti ngs 1,632,587.41 1.74%

TOTAL AMOUNT 93,896,976.50 100.00%


PROJECTED WEEKLY ACCOMPLISHMENT 0.000 0.000 0.000 0.005 0.020 0.020 0.024 0.03 0.03 0.04
PROJECTED CUMMULATIVE WEEKLY ACCOMPLISHMENT 7.14 0.000 0.001 0.001 0.006 0.027 0.047 0.071 0.10 0.13 0.17
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE
2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

DIETARY BUILDING
DURATION 180 DAYS

START JAN 6, 2020


COMPLETION JULY 6, 2020
PREVIOUS TO DATE
SCHEDULE 15.24% 17.43%
ACTUAL 17.22% 18.20%
VARIANCE (+/-) +0.77%

VARIANCE =19.8% X 180 DAYS = 1.38 DAYS


ADVANCED
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE
2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

PROJECT NAME : Dietary Building


LOCATION Wawa st. Brgy. Alabang, Muntinlupa City
SUBJECT S-Curve / Bar Chart
DATE: 20/20/2020

January February March


ITEM NO. DISCRIPTION AMOUNT % WEIGHT WEEKS W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3
1 2 3 4 5 6 7 8 9 10 11
Part 1 General Requirements (DIET/MB)
A1.1 Temporary Utilities (Water, Electric & Telephone) 50,000.00 0.60% 28 0 .000 21 0.0002 1 0.0002 1 0.00021 0.00021 0.00021 0.00021 0.00021 0.00021 0.00021 0.00021

A1.2 Service/ Equipments/Delivery 25,000.00 0.30% 11 0.00027 0.00027 0.00027 0.00027 0.00027

A1.3 As-built Plan 30,000.00 0.36% 2


A1.4 Safety /Security Provision 80,000.00 0.95% 22 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043 0.00043

A1.5 Scaffolding 50,000.00 0.60% 12 0.00050 0.00050

A1.6 Lay-out 5,000.00 0.06% 5 0.00012 0.00012 0.00012 0.00012 0.00012

A1.7 Superv ision 50,000.00 0.60% 28 0.00021 0.00021 0.00021 0.00021 0.00021 0.00021 0.00021 0.00021 0.00021 0.00021 0.00021

To t al Amo u n t 290,000.00
Part II DIETARY BUILDING
Part A Structural Works
A.1 Earth Works 222,237.33 2.65% 5 0.00530 0.00530 0.00530 0.00530 0.00530

A.2 Concrete Works 711,360.00 8.47% 8 0.01059 0.01059 0.01059 0.01059

A.3 Reinforcing Steel Works 1,286,110.00 15.32% 9 0.01702 0.01702 0.01702 0.01702 0.01702 0.01702 0.01702 0.01702

A.4 Form Works 513,647.21 6.12% 8 0.00765 0.00765 0.00765 0.00765 0.00765 0.00765 0.00765

A.5 Structural Steel Works 521,080.29 6.21% 4


To t al Amo u n t 3,254,434.83
Part B Architectural Works
B.1 Masonry Works 395,518.08 4.71% 7 0.00673

B.2 Plastering 416,603.67 4.96% 6


B.3 Painting Exterior/Interior 381,308.58 4.54% 5
B.4 Floor Finishes 259,256.80 3.09% 5
B.5 Ceiling Finishes 273,336.00 3.26% 5
B.6 Doors 307,200.00 3.66% 2
B.7 Hardwares 58,600.00 0.70% 2
B.8 Windows 155,695.00 1.85% 4
B.9 Metal Steel Works 32,300.00 0.38% 9
B.10 Waterproofi ng 36,883.60 0.44% 3
B.11 Others 17,682.00 0.21% 3
To t al Amo u n t 2,334,383.73
Part C Electrical Works (rough-ins)
C.1 Electrical Works 586,679.03 6.99% 20 0.00349 0.00349 0.00349 0.00349 0.00349

To t al Amo u n t 586,679.03
Part D Plumbing and Sanitary Works
D.1 Plumbing Works 98,353.03 1.17% 21 0.00056 0.00056 0.00056 0.00056 0.00056

D.2 Sanitary Works 225,918.64 2.69% 18 0.00150 0.00150 0.00150

324,271.67
To t al Amo u n t
Part E Misc 1,604,082.99 19.11% 28 0.00683 0.00683 0.00683 0.00683 0.00683 0.00683 0.00683 0.00683 0.00683 0.00683 0.00683

To t al Amo u n t 1,604,082.99
TOTAL AMOUNT 8,393,852.24 100.00%
PROJECTED WEEKLY ACCOMPLISHMENT 0.013 0.013 0.013 0.030 0.038 0.032 0.037 0.047 0.049 0.049 0.056
PROJECTED CUMMULATIVE WEEKLY ACCOMPLISHMENT 17.43% 0.013 0.025 0.038 0.067 0.105 0.137 0.174 0.22 0.27 0.32 0.38

PREPARED AND VERIFIED BY:


Engr. Ian Relosa
PIC - DLCCC
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE
2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY
ACTIVITIES UNDER APPROVED SCOPE OF WORKS

TILING WALL AND FIRE ELECTRICA PAINTING DIETARY


WORKS CEILING PRO / L WORKS WORKS BUILDING
PLUMBING
FLOOR GROUND FLOOR RELOCATION OF INSTALLATION OF PAINTING OF REBARWORKS OF
PREPARATION AT TOILET PARTITION DRAIN, SEWER, WIRES AT UNDERSLAB AND COLUMNS
GROUND AND FROM REVISE COMMON TOILETS BEAMS @ 3RD
SECOND FLOOR TOILETS GROUND TO 6TH FLOOR
FLOOR
FLOOR TOPPING GRINDING OF CORING WORKS RE ALIGNMENT OF PAINTING OF FABRICATION OF
AT 4TH AND 3RD CEILING GROUND @ 4TH FLOOR ELECTRICAL LINES PERIMETER WALL STIRRUPS AND
FLOOR FLOOR @ 5TH FLOOR AT 5TH FLOOR FOOTING TIE
BEAMS

PREPARATION FOR ADDITIONAL INSTALLATION OF INSTALLATION OF PAINTING OF 5TH FABRICATION OF


WATER PROOFING FRAMES FOR WATER LINES @ CABLE TRAY AND 6TH LEDGES FORMWORKS
AT 4TH FLOOR TOILETS 4TH FLOOR HANGERS
RELOCATION OF READY FOR
SPRINKLER HEAD CONCRETING 1ST
@ 4TH FLOOR LIFT COLUMNS
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE
2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY
STATUS OF WORKS AS OF FEBRUARY 14 TO FEBRUARY 20, 2020
SEQUENCE OF WORK WILL START FROM 4TH FLOOR TO GROUND
FLOOR

STATUS OF
TILING
WORKS

STATUS OF
Wall and
Ceiling
Works

STATUS OF
FIRE PRO /
PLUMBING
WORKS
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE
2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

STATUS OF
DIETARY
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE 2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

STATUS OF WORKS AS OF FEBRUARY 14 TO


FEBRUARY
ARCHITECTURAL WORKS 20, 2020
(GROUND FLOOR)

Installation of Wall
Partition
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE 2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

STATUS OF WORKS AS OF FEBRUARY 14 TO


FEBRUARY
MEPFS WORKS (GROUND 20, 2020
FLOOR)

Fabrication and Installation of Cable


Tray
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE 2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

STATUS OF WORKS AS OF FEBRUARY 14 TO


FEBRUARY
ARCHITECTURAL WORKS 20,FLOOR)
(THIRD 2020

Floor Topping
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE 2)
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

STATUS OF WORKS AS OF FEBRUARY 14 TO


FEBRUARY
ARCHITECTURAL WORKS 20,FLOOR)
(THIRD 2020

Painting of Underslab
PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE 2)
LOCATION: 90 WAWA ST. ALABANG., MUNTINLUPA CITY

STATUS OF WORKS AS OF FEBRUARY 14 TO


FEBRUARY
MEPFS WORKS (THIRD FLOOR)20, 2020

Installation of Sanitary Pipes


PROJECT: PROPOSED SIX STOREY HOSPITAL (PHASE 2)
LOCATION: 90 WAWA ST. ALABANG., MUNTINLUPA CITY

STATUS OF WORKS AS OF FEBRUARY 14 TO


FEBRUARY
ARCHITECTURAL WORKS 20, 2020
(FOURTH FLOOR)

Floor Topping Preparation and Lay


PROJECT: DIETARY BUILDING
LOCATION: 90 WAWA ST. ALABANG., MUNTINLUPA CITY
PROJECT: DIETARY BUILDING
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

STATUS OF WORK

Concrete Pouring of Footing


PROJECT: DIETARY BUILDING
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

STATUS OF WORK

Rebar Installation (Columns)


PROJECT: PROPOSED SIX STOREY HOSPITAL
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

CATCH UP SCHEDULES
Feb 24 – 29, 2020

1.TILING WORKS AT SECOND FLOOR AND


GROUND FLOOR.
2.TOILET WALL PARTITIONING GROUND FLOOR.
3.WATERPROOFING OF TOILETS @ 4TH FLOOR.
4.ELECTRICAL WORKS AT 4TH FLOOR .
5.PAINTING WORKS AT SECOND FLOOR.
6.GRINDING OF CEILING AT GROUND FLOOR
PROJECT: PROPOSED SIX STOREY HOSPITAL
LOCATION: WAWA ST. ALABANG., MUNTINLUPA CITY

ISSUES AND CONCERNS


ISSUES:
1. GLASS SOLUTION TO TRANSFER THEIR FABRICATION AND OFFICE.
2. UMS TO TRANSFER THEIR OFFICE / WAREHOUSE.
3. VN TO PREPARE AND READY THERE STAGING AREA, MANPOWERS,
AND BARRAKS.
CONCERNS:
1. LIGHTING LAYOUT FOR 6TH FLOOR (LATEST PLAN) ALREADY
FORWARD TO CM.
2. SUBMIT ENDORSEMENT LETTER TO DLCCC BEFORE ENTERING THE
SITE FOR CONFIRMATION AND RECORDS
PROJECT: PROPOSED SIX STOREY HOSPITAL
LOCATION: WAWA ST. ALABANG.,
MUNTINLUPA CITY

PREPARED BY: ENGR. JINKY DESIO


DLCCC – PROJECT ENGINEER

NOTED BY: ENGR. IAN RELOSA


DLCCC – PROJECT IN CHARGE

THANK YOU!