ORIENTATION BRIEF: PROJECTS

1. Tower Portfolio
2. GBT/RTT Construction Time Lines
3. Project Review
a) DPR – Daily
b) EPR – Weekly
c) Dash Board - Daily review
d) WBR – Weekly
e) CPAT – Weekly
4. Processes
a) Acquisition Processes
b) Project Management(Flow Chart)
c) Sharing
d) Quality Control & Quality Assurance
e) Site Evaluation
f) RFI declaration and Acceptance Test Certificate
g) Customer billing – coordination with finance
h) Customer Interaction and Periodic reviews
Tower Portfolio
Circle Wise Month Wise
S.No Month RTP RTT GBT Total
S.No Circle RTP RTT GBT Total
1 31-Dec-07 20 374 354 748
1 J&K 0 6 122 128 2 January 2 22 27 51

2 Punjab 14 283 264 561


3 February 0 0 33 33
4 March 1 0 12 13
3 Haryana 2 115 228 345
5 April 0 2 7 9
4 Delhi 0 17 3 20 6 May 0 3 4 7
7 June 0 1 3 4
5 UPW 1 24 27 52
8 July 0 14 22 36
6 UPE 1 50 70 121
9 August 0 68 43 111
7 Bihar 0 28 283 311 10 September 3 20 82 105
11 October 2 65 58 125
8 Jharkhand 1 4 53 58
12 November 9 80 47 136
9 RAJ 0 10 21 31 13 December 08 9 154 92 255

10 Maharashtra 3 181 41 225 14 January'09 0 85 90 175


15 February'09 1 132 150 283
11 AP 18 99 89 206
16 March'09 2 110 157 269
12 Karnataka 59 370 404 833 17 April'09 0 115 107 222
18 May'09 1 104 114 219
13 TN 0 613 526 1139
19 Jun'09 4 101 94 199
14 Kerala 3 136 113 252 20 Jul'09 9 66 83 158
21 Aug'09 0 59 92 151
15 Total 102 1936 2244 4282
22 Sep'09 4 84 114 202
23 Oct'09 0 102 129 231
24 Nov'09 21 87 137 245
25 Dec'09 14 88 193 295
  Total 102 1936 2244 4282
GBT - Time Line
 Tower Foundation -Timeline for completion: 21-23 days. Following activities are completed laying tower foundation:
– Excavation of soil (7 days)
– Leveling of pits and first-level concreting (2 days – for all isolated pits)
– Bar cutting and bending (3 days)
– Adding steel bars to pits as per site layout (2 days – for all isolated pits)
– Footing concrete – for weak soil (2 days – for all isolated pits)
– Curing (2 days – for all isolated pits)
– First-lift/ second level concreting to raise pit level to ground level (2 days – for all isolated pits)
– Curing (2 days – for all isolated pits)
– Backfilling excavated soil into pits (2 days – for all isolated pits)
– Third-level concreting (2 days – for all isolated pits)
– Curing of tower foundation (8 days)

 DG & Shelter Foundation– timeline for completion: 10 days

 Tower Errection - timeline for completion: 5-7 days

 DG, shelter and AC installation - timeline for completion: 2-3 days

 External Electrical work - timeline for completion: 3 days

 Internal Electrical work - timeline for completion: 2-3 days

 Fencing/ boundary wall building - timeline for completion: 7-10 days


RTT - Time Line
 Tower foundation - timeline for completion: 9 days. Following
activities are completed laying tower foundation:
– Chipping and exposing of steel columns (1 day)
– Insertion of steel rods, only in case column is not present (3
days)
– Bar cutting and bending (3 days)
– Concreting and adding steel bars (1 day)
– Curing (4 days)

 DG and Shelter foundation/ pedestal - timeline for completion: 9


days

 Tower erection - timeline for completion: 4 days

 DG, shelter and AC Installation - timeline for completion: 3 days

 External Electrical work - timeline for completion: 4 days

 Internal Electrical work - timeline for completion: 2-3 days


Daily Progress Report

Microsoft Office
Excel Worksheet

Format DPR
Excecutive Progress Report

Microsoft Office
Excel Worksheet

Format EPR
Dash Board

Microsoft Office
Excel Worksheet

Project 2010
Weekly Business Review

Microsoft Office
Excel Worksheet

WBR
CIRCLE PERFORMANCE
ASSESSMENT TRACKER (CPAT)

Microsoft Office
Excel Worksheet

CPAT
Site Evaluation

Microsoft Office
Excel Worksheet

Evaluation Matrix
Acquisition Process (Flow Chart)

Microsoft Office
Excel Worksheet

Flow Chart
Project Management (Flow
Chart)
Vision and Mission Customer Relationship Management
Regulatory Compliance Acquisition of Talent
Project Management Tools & Technologies

Vendor Allocation & Site Deployment


Material
Site Layout Invoice (incl. Sharing
Management
Authorisation Requests)

Quality Management of Acceptance Test & MIS Reporting &


Control/Assurance Site-related Issues RFI Declaration Review Meetings

Finance & Accounts Human Resource Management

SCM/ Administration Legal