Erection Methods of Steel

Bridges
Content
1. Bent Method
2. Launching Method
3. Traveler Crane Method
4. Cable Erection Method ( Diagonal
Hanging)
5. Cable Erection Method (Vertical Hanging)
6. Other Erection Method
Bent   Method
Bent Method
Advantages
1. The most basic construction method and easy for geometrical
control.

2. Short construction period & economical method compared to


other methods.
3. Uses light equipment ( Main:Crane & Bent only)

Disadvantages
1. Impossible to use under the girder during the construction period.
2. Depends on the ground condition   (flat and firm ground
condition ).
3. Not suitable for high piers or heavy weight girder (ex. Large-block).
Up to 40m & 200ton
Bent Method
• Bent Installation
   Bent Height : L    L≦ 10m  Plane Bents(Single Type)
  L≧ 10m  Cubic Bents(Double Type)

Ground Condition
Firm => Spread foundation (Steel plate or concrete)
Soft => Pile foundation (H-pile or Steel-pipe Pile)
Bent Height: Exact Calculation!
Bent Method
  Bent (Concrete foundation) Bent (Pile foundation)  
Bent Method
• Girder Erection
   Crane Type : Ground condition Firm => Truck Crane
Soft => Crawler Crane
very soft => another erection method
Crane Capacity : Depend on
=> weight of the girder and working radius
Bent Method

Under construction
Bent Method
• Girder Erection Completed
Falsework(Scaffolding)=>joint part & Under the Girder
Joint Connecting
Joint Painting
Dismantling of Bents

Falsework for Joint

Falsework for Girder


Bent Method

Falsework for joint

Safety net (wire bridge) Falsework under the girder


Bent Method
• Accessory work,Dismantling & Completion

Expansion Joint Slab,Pavement &Guard Rail

Drainage attachment
Launching Method
Launching Method
Advantages
1. Not be influenced by the variable conditions under the girder.

Water, Heavy traffic road , Railway , etc


2. Short Construction Period compared to cable crane method.

Disadvantages
1. Spread & wide back yard is necessary.

2. Difficult to control of the stress & reaction under launching.

3. Heavy equipment is necessary.


Launching Method

Preparation Work
=> Back Yard Compaction (against the Dead-Load)

Impossible for Bent Installation

Water,heavy traffic road, railway,etc


Launching Method

Preparation Work
=> Steel Plate or Concrete Base construction
=> Depend on the Firmness of ground condition and Dead-Load
=> Decided by Calculation
Launching Method

Preparation Work
=> Bent Installation & Shoe Setting
=> Installation of Hydraulic Jack for launching by the crane
Launching Method

Launching Nose & Bent Launching Jack


Launching Method

・ Assembling of Erection Nose for Launching by the crane


・ Setting the Bogie
・ Girder transportation and assembling on the back yard by the crane
Launching Method

Bogie & Guide Rail


Launching Method

・  Launching and Girder assembling


    => Depend on the space of the back yard
・  20 ~ 40m   / Day is possible (depend on Jack capacity and
condition)
Reaction & Stress Check!
Displacement
Check!
Launching Method

Under launching
Launching Method

• Connection Girder assembling

Reaction & Stress Check!


Launching Method

• Dismantling of Erection Nose at the opposite side


Launching Method

Under launching
Launching Method

• Completion of Launching
=> Girder shall be received by connection girder
Launching Method

• Change of the bearing from Jack to sleeper


=> Detachment of Connection Girder for Jack Down
Launching Method

Dismantling of Nose Jack down


Launching Method

• Jack Down and detachment of the Bent one after another


=> Depend on the Stroke of the Jack (for Simple Beam)
=> Depend on the Reaction of Bearing (for continuous Beam)
Launching Method

Detachment of the connection girder Jack down


Launching Method

• Completion of Jack Down


Launching Method

• Accessory work,Dismantling & Completion


Launching Method

Dismantling of falsework Completion


Traveler Crane Method
Traveler Crane Method
Advantages
1. Not be influenced by the variable conditions under the girder

Water, Heavy traffic road , Railway , etc


2. Short Construction Period compared to cable crane method

3. Light equipment comparably


Disadvantages
1. Variable calculation for reinforcements under construction is necessary
2. Difficult to control of the stress & reaction under construction
Traveler Crane Method

• Preparation Work
   => Ground Levering for Bent Erection span
   => Accuracy Measurement of the Pier
(Span,Width,Elevation,etc)

Impossible for Bent Installation

Water,heavy traffic road, railway,etc


Traveler Crane Method

• Bent Installation
• Erection work for side span as a counter weight
=> from Ground Level by the crane
Traveler Crane Method

• Traveler crane setting by the crane


=> crane capacity : depend on the weight of the component
Traveler Crane Method
Traveler Crane Method

• Cantilever erection for another span by traveler crane


Bridge component => transported by bogie on the girder

Bogie Counter weight


Traveler Crane Method
Traveler Crane Method

• Cantilever erection for another span by traveler crane


Bridge component => transported by bogie on the girder
• Bent Dismantling (one after another => Bent reaction force = 0)

Up-Lift Check! Negative Moment Check! Calculation

Displacement:Large
Traveler Crane Method

• Cantilever erection for another span by traveler crane


Bridge component => transported by bogie on the girder
Traveler Crane Method

• Traveler crane dismantling, Accessory work & Completion


Cable Erection Method

(Diagonal Hanging Method)


Cable Crane Method
Advantages
1. Not be influenced by the variable conditions under the girder

Water, Deep valley


2. No need for spread & wide back yard

Disadvantages
1. Long construction period
2. Difficult to control of the displacement under construction

3. Heavy equipment
Cable Erection Method (Diagonal)
• Preparation Work => Installation of wire bridge

Wire Bridge : easy to come and go for workman

Wire Bridge
Cable Erection Method (Diagonal)

Before construction Wire-Bridge


Cable Erection Method (Diagonal)
• Setting Anchorage for Cable-crane

Ground anchor
(direct-anchor for the earth)
Gravity anchor
Steep landscape
Flat & wide landscape
Cable Erection Method (Diagonal)

Boring for anchor Anchorage & Bearing Beam


Cable Erection Method (Diagonal)
• Installation of Concrete Base & Steel Tower for Cable crane

Steel Tower

Concrete Base
Cable Erection Method (Diagonal)

Steel tower assembling Completion


Cable Erection Method (Diagonal)
• Installation of Back-Stay & Main Cable for the crane
Back Stay Cable
Track Cable

Main Cable Carrier


Cable Erection Method (Diagonal)

Wire unreeling Wire Installation

Main  
Cable

Track cable
Cable Erection Method (Diagonal)
• Installation of Shoe, Bent & some equipments

Bet-Beam for reaction

Shoe setting

Support
installation
Cable Erection Method (Diagonal)
• Main Arch Erection

Displacement
Check!
Cable Erection Method (Diagonal)
Arch-rib under construction
Cable Erection Method (Diagonal)
• Main Arch Erection
Cable Erection Method (Diagonal)
• Dismantling of Diagonal stay wire
Cable Erection Method (Diagonal)
Arch-rib closure & Dismantling diagonal stay
Cable Erection Method (Diagonal)
• Girder & Vertical Brace erection
Cable Erection Method (Diagonal)

Girder erection Connected by high-strength Bolts


Cable Erection Method (Diagonal)
Girder erection
Cable Erection Method (Diagonal)
• Dismantling Cable crane
Cable Erection Method (Diagonal)
• Completion
Cable Erection Method (Diagonal)
Completion
Cable Erection Method (Diagonal)
Completion
Cable Erection Method

(Vertical Hanging Method)


The same procedure
to assemble of cable crane
Cable Erection Method (Vertical)
• Shoe setting & Vertical Hanging Wire attachment

Wire length: Exact Calculation!


Cable Erection Method (Vertical)
Vertical Hanging wire & Bed-Beam setting
Cable Erection Method (Vertical)
• Bottom code components erection
Cable Erection Method (Vertical)
Bottom code components erection
Cable Erection Method (Vertical)
• Diagonal components erection
Cable Erection Method (Vertical)
Diagonal components erection
Cable Erection Method (Vertical)
• Upper components erection
Cable Erection Method (Vertical)
Upper components erection
Cable Erection Method (Vertical)
• Dismantling Vertical Hanger
Cable Erection Method (Vertical)
• Dismantling Cable crane
Cable Erection Method (Vertical)
Dismantling Cable crane
Cable Erection Method (Vertical)
• Completion
Cable Erection Method (Vertical)
Completion
Another erection methods

1.Combined by basically method


2.Large block erection
3.Cable-stayed bridge & suspension bridge
Cable-Stayed Bridge
Cable-stayed Bridge Erection procedure
Cable-stayed Bridge Erection procedure
Cable-stayed Bridge Erection
procedure
Cable-stayed Bridge Erection procedure
Cable-stayed Bridge Erection procedure
Cable-stayed Bridge Erection procedure
Cable-stayed Bridge Erection procedure
Cable-stayed Bridge Erection procedure
Cable-stayed Bridge Erection procedure
Cable-stayed Bridge Erection procedure
Cable-stayed Bridge Erection procedure
Conclusion
Accidents usually occurred during construction

Planning is the most important !

1. Investigate valuable conditions


2. The most safe method
3. Appropriate construction period
4. Calculation & analysis under construction
5. The most economical method