Beruflich Dokumente
Kultur Dokumente
Program:
The strategy that is to be followed and major actions that
needs to be taken in order to achieve or exceed objectives
Schedule:
A plan showing when individual or group activities or
accomplishments will be started or completed
Components of Project Plan
Organization:
Design of the number and types of positions, along with
corresponding duties and responsibilities, that are required to
achieve or exceed objectives.
Policy:
A general guide for decision making and individual actions.
Procedure:
A detailed method for carrying out a policy
Components of Project Plan
Budget:
Planned expenditures required to achieve or exceed objectives.
Forecast:
A projection of what will happen by a certain time.
Standard:
A level of individual or group performance defined as
adequate or acceptable.
If the planning is strictly operational, then these factors may be
clearly definable. However, if strategic or long range planning is
necessary, then the future economic outlook can vary, and re-
planning must be done at regular intervals because the goals and
objectives can change.
There are four basic reasons for project planning:
• Agreement on purpose
• Assignment and acceptance of individual responsibilities
• Coordination of work activities
• Increased commitment to group goals
• Lateral communications
At the organization or project level, planning must
include:
I. Realism
II. Capability
III. Flexibility
IV. Ease of use
Numeric and Non-Numeric Models
• Both are widely used, many organizations use both at the same
time, or they use models that are combinations of the two.
• Nonnumeric models are older and simpler and have only a few subtypes
to consider.
• Q Sort Method
The Sacred Cow
• First, the projects are divided into three groups—good, fair, and
poor—according to their relative merits. If any group has more
than eight members, it is subdivided into two categories, such as
fair-plus and fair-minus. When all categories have eight or fewer
members, the projects within each category are ordered from best
to worst. Again, the order is determined on the basis of relative
merit. The rater may use specific criteria to rank each project, or
may simply use general overall judgment.
The Q-Sort Method
Numeric Models: Profit/Profitability
money at time zero representing the discounted cash flows for the
project.
PV
between cash out flows and cash inflows on a present value basis.
Where:
• Annual Receipts
• $40,000(P/A, 12%, 10) $ 226,000
• Salvage Value
• $20,000(P/F, 12%, 10) $ 6,440
• Annual Disbursements
• $22,000(P/A, 12%, 10) -$124,000
• Initial Investment (t=0) -$100,000
FV
PV of $ 25,282
$25,282(P/F, 12%, 10) $ 8,140
FV of $ 8,140
$8,140(F/P, 12%, 10) $ 25,280
Annual Value
• Salvage
• Costs:
• Investment:
Since this is less than zero, the project is expected to earn less than the
• The benefit/cost ratio is also called the profitability index and is defined
as the ratio of the sum of the present value of future benefits to the
sum of the present value of the future capital expenditures and costs.
B/C Ratio Example
Project A Project B
• Present value cash inflows
$500,000 $100,000
• Present value cash outflows
$300,000 $ 50,000
• Net Present Value
$200,000 $ 50,000
• Benefit/Cost Ratio
1.67 2.0
Payback Period
One of the most common evaluation criteria used.
Simply the number of years required for the cash income from a
project to return the initial cash investment.
Alternative A
(45,000) 10,500 11,500 12,500 13,500 13,500 13,500 13,500 13,500 13,500 13,500
Alternative A
(120) 10 10 50 50 50 50 50 50 50 50
Alternative A
(120) 10 10 50 50 50 50 50 50 50 50
Alternative A
(120) 10 10 50 50 50 50 50 50 50 50
Alternative A
(250) 86 50 77 52 41 70 127 24 6 40
Alternative A
(250) 86 50 77 52 41 70 127 24 6 40
Alternative A
(250) 86 50 77 52 41 70 127 24 6 40
III. Team members write down all tasks they can think of
• Code of accounts
Uniquely identifies each element of the WBS.
• Work packages
A deliverable at the lowest level of the WBS.
• WBS dictionary
Includes work package instructions for the assigned team
member.
• Example
• Landscape project
• Lawn
• Install sprinkler system
• Code of Accounts:
• 1.
• 2.
• 2.1
• 2.2
• 2.2.1
• 2.2.2
• 2.2.3
• 2.2.4
• 2.3
Work Packages:
• Design Landscape
• Acquire land material
• Install sprinkler system
• Identify sprinkler locations
• Dig trenches
• Install pipe and hardware
• Cover sprinkler system
• Plant grass
Work Packages:
• Task description
To hire new employee for Product Specialist position.
• Goals and Objectives:
To fill position by June 15, 2020 and have trained by end of July.
• Job Description:
To provide the job description here with performance criteria.
• Acceptance Criteria:
Mr. Jamal must provide approval of selected candidate before the
job offer is made, and provide acceptance upon completion of
probationary period.
• Work packages should be…
• High-level WBS
Based on products, requirements, or deliverables, created from a
perspective of the project scope definition and is expressed as
nouns
Example: Low-level WBS
1. Preparation
1.1 Read recipe
1.2 Check ingredients at home
1.3 Make shopping list
1.4 Go on shopping trip
and so on…
High Level WBS:
Conference
October 15,
2021
By structural, process, system, or device components:
Airplane
Air Conditioning
Refrigerants
• By “intermediate” deliverables required in the production of the
“end” deliverables:
Software
Interface
Graphics