Sie sind auf Seite 1von 44

PROJECT: DECENTRALIZED WASTE WATER

MANAGEMENT FOR KOYEFETCHE WWTPs


WWTP1: EXTENDED AERATION ACTIVATED
SLUDGE

CLIENT:
AAWSA- WATER AND SANITATION
DEVELOPMENT & REHABILITATION PROJECT
OFFICE

CONTRACTOR: TSEMEX GLOBAL ENTERPRISE PLC

CONSULTANT: SWS CONSULTANCY

March 2019
LOT-I: WWTP-01 SYSTEM LAYOUT
DESIGN DATA
 The  wastewater,  to  be  collected  and 
treated treatment plant, is mainly domestic waste water. 
 Industrial  wastewaters will  not be discharged and treated on this
system.
 It is intended that the WWTP is going to treat wastewater
for 68,090 people equivalent after 20 years at 2035.
 The max. daily water consumption  in the area  is about  170l/PE-day.
The 80% of the water consumption drops in  the  sewage  system  so 
the  maximum  daily wastewater production per capita is 136l/PE-day.
 Thus, design flow of the plant is 9,260m3/day or 107l/sec.

 The Wastewater Treatment Plant  is designed for maximum daily 


flow  for  the biological treatment phase and max. hourly peak flow for
the pre-treatment units.  
DESIGN WASTEWATER LOADS
 pollutant  loads  at  the  domestic  wastewater considered for design are as
follows;
 Organic loads BOD5:     60g BOD5/cap-day 
 Suspended Solid Loads TSS:   70g TSS/cap-day 
 Total N:     12g ΤΝ/cap-day 
 Total P:     1,5g TP/cap-day 

EFFLUENT LIMITS
 Treated effluent  is expected  to be used  for  irrigation  and or when  irrigation 
isn’t  required, to be discharged  into the river
 Thus, the treated effluent levels have been set in conjunction of various factors:  
 protection of human health;

 protection of  the environment  (both  the  river and  crops  to be 


irrigated); 
 the constraints of the technologies selected.    
WASTEWATER EFFLUENT CHARACTERISTICS 
TREATMENT DEMANDS
WHY TO TREAT WASTE WATER  

 Due to organic decomposition of accumulated untreated


wastewater, it leads to the production of malodorous gases.
  untreated wastewater usually contains numerous pathogenic or 
disease‐causing micro‐organisms.
 It  contains  nutrients, which  can  stimulate  the  growth  of
aquatic plants.
 it  may  contain  toxic  compounds. 

 For  these  reasons,  the  immediate  and nuisance‐


free removal of wastewater from its sources of generation, follo
wed by treatment and disposal, is not only desirable but also
necessary in an industrialised society.  
WASTEWATER TREATMENT PROCESS 

 the  treatment  plant  consists of the following:


 A complete WWTP of maximum capacity 68.090 P.E., using t
he method of activated  sludge (extended aeration system). 
 Two  treatment  lines  in  order  the  first  one  to  treat  the 
present  quantity  of 
the wastewater and the second one to be ready to treat the fut
ure flows. 
 A complete sludge  treatment  line  in order 
to stabilize and dewater  the biological which will be
produced.
WASTEWATER COMPOSITION  

 is a mix of water (~99%) and pollution load (~1%).


 Some  pollutants  are  suspended  and  some  dissolved  in  water.

 The purpose of  sewage  treatment  is  to  remove  the pollution 


load and discharge clean water into the water course. 
 Wastewater Treatment is the acceleration of natural degradation process
es. It involves physical, chemical and biological processes. 
 Settlement (physical) processes are generally employed to remove SS to
60% and BOD5 more to 25‐30%. 
 Secondary biological treatment removes the BOD5 up to 92% of the
pollution load.
 BOD  (in mg/l)  is a measure of the organic material  in a wastewater.

 The term BOD 
is normally measured as the oxygen demand of a settled sample over fiv
e days, (i.e. BOD5)  
PROCESS TECHNICAL DESCRIPTION    

 The activated sludge process  (or suspended growth system) was
developed in England in 1914 and was so named b/c it involves
production of an activated mass of micro-organisms capable of
aerobically stabilizing the organic matter of the waste water.
 The  suspended  growth  systems  are  classified  into  three broad 
categories based on  the organic and hydraulic  loading rates and
retention times namely; 
 high  rate Activated Sludge Process ( Solids retention period less than 2 hrs)
 conventional  Activated Sludge Process
( Solids retention period from 4 to 8 hrs)
   Extended aeration process
( Solids retention period exceeding about 24 hrs)
CONT…D    

 In  suspended  growth  systems,  the  biological  process may 


or may  not  be  preceded  by primary settlement.
 The  conventional  activated  sludge  system  has  primary 
settlement whereas  the  extended‐aeration  system  has  n
Advantages of extended aeration systems 
 relatively low construction cost 

 lowest sludge production of any activated sludge system

 high quality wastewater achievable 

 favourable reliability with sufficient operator attention 

 relatively minimal land require

 nitrification can occur; and 

 Sustaining shock loadings.    
CONT…D    

Disadvantages
 high power consumption 

 high operation and maintenance requirements 

 skilled operators are necessary 

 potential  for  rising  sludge due  to denitrification  in 


secondary   settlement  tank  in warmer months 
 Dewatering of extended‐ aeration sludge is comparatively diffic
ult. 
PHASES OF PROCESS FOR THE PROPOSED SYSTEM 

The proposed system of activated sludge includes the following phases:
 Inlet / Lift Pumping Station 

 Compact Pretreatment Unit 

 Pre Anoxic Tank for the sludge recirculation 

 Denitrification / Anoxic tanks (two lines) 

 Nitrification / Aerated tanks (two lines – two series

 Internal Recirculation of Mixed Liquid 

 Chemical removal of Phosphorous (two pits) 

 Final Clarification tanks (two tanks) 

 Recirculation of biological sludge  

 Measurement of flow in Parshall channel 

 Disinfection Unit – Chlorination Tank 

 Aeration Tank for stabilization of sludge 

 Gravity thickeners (2pieces) 

 Dewatering system – Belt Press System 

 Drainage recirculation  
PHASES OF PROCESS FOR THE PROPOSED SYSTEM 
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

Inlet / Lift Pumping Station 
 The wastewater coming to the treatment plant through the sewage network system will be
collected at the first phase of the plant called Lifting Pump Station (LPS).
 The LPS is designed for a retention time of about 10 minutes (phf). 

 Will be installed 6 submersible pumps (4 in oper. and 2 stand by).

 pump capacity 165m3/h at 10m, capable  for  peak  flow(656m3/h)

 These pumps must be Contrabloc impeller type with min. free passage of 120mm and


max. speed of 982rpm.
 Operation  of  the  pumps will  be  controlled  by  soft  starter  through  PLC  –  Scada 
system according to the waste water level.
 Thus, a hydrostatic level control will be installed in the pit.

 Also, safety  floater  switch will be  installed   in order  to protect  the


pumps from dry operation. 
 Pumps will feed waste water the two compact pre-treatment units.

 Each pumps will  be  installed  a  separate  nonreturnable and check valve (knife valve).

 Also a pressure gauge will be installed in order to measure the pressure of the pumping


station.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

LPS cont’….d
 Each pump will be protected with moisture wet sensor and thermal protection
 of coil of the motor according to Manufacturer standards. 
 Electromagnetic flow meter will be installed at the output of each pipeline in 
order to measure  the  flow.  
 A submersible mixer with installed power of 1.7kW will be installed in order
to avoid the sedimentation of the suspended solids in the bottom of the pit.
 Operation of mixers will be controlled by time program through PLC – Scada
 system according to the waste water level.
 A safety floater switch will be installed in order  to protect the mixer from dry
operation.
 Maintenance of pumps and mixers shall be carried out by well trained persons
at 2000 normal working hours or 1000 working hours if the liquid is muddy
or sandy but at least once a year.
 A manual hoist  will be installed for the pumps and mixers
above the pit in order to lift for maintenance purpose. 
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

PRETREATMENT STAGE
 Two  PTUs  with capacity 100l/sec each to cover the max. hourly flow (181l/sec). The unit consists
of 
 Sewage waste Screening (6mm screen)
 Compacting
 Dehydrating
 Sand Collection (size greater than 0.2mm) and 
 Oil and grease separating and collecting  
 The PTU unit shall be fully covered and closed to avoid problems with odours. Collection,
transportation, of the dewatered screening, the sand and the grease shall be made in separate
containers.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

SECONDARY TREATMENT PHASE-


ACTIVATED SLUDGE PROCESS 
 The secondary treatment phase for BOD5, Nitrogen and P
hosphorus removal will have the following stages.
 Preanoxic stage for the denitrification of sludge recirculat
ion
 Anaerobic stage (Biological phosphorus removal) 

 Anoxic stage for denitrification of nitrates 

 Aeration stage for nitrification and BOD5 removal 

 Mixed Liquid recirculation 

 Chemical phosphorus removal. 

 Final clarification – Sludge recirculation
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

PRE‐ANOXIC TANK   
 The  wastewater  after  the  PTU enters to pre-anoxic tank by gravity with a small qty.
of nitrogen as NO3 (7mg/l).
 The recirculated sludge which comes from the bottom of final clarification also
enters to pre-anoxic tank for denitrification of nitrates. 
  In this tank the nitrates of the biological sludge will be reduced to 1mg/l.

 Two submersible mixers with installed power of 2.5kW will be installed


 to keep the particles suspended and to inhibit sediment formations in the tank
bottom.
 Operation of mixers will be controlled by time program through PLC – Scada system
according to the waste water level.
 A safety floater switch will be installed in order  to protect the mixer from dry
operation.
 Maintenance of pumps and mixers shall be carried out by well trained persons at
2000 normal working hours or 1000 working hours if the liquid is muddy or sandy
but at least once a year.
 A manual hoist  will be installed for the pumps and mixers
above the pit in order to lift for maintenance purpose. 
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

ANAEROBIC TANK (BIOLOGICAL PHOSPHORUS REMOVAL UNIT)   
 The  wastewater  after  the  pre  anoxic  tank  will enter through two overflows to anaerobic
tank.
  Are designed with a retention time of 1hr for the combined inlet and returned sludge flows.

 In  this  stage,  the  phosphorous  is  removed  by  biological means as under favourable
anaerobic conditions the microorganisms in the activated sludge mixed liquor are able to
remove an excess amount of Phosphorus over that required for growth (“Luxury uptake”).
 Phosphorous  is  carried  away  from  the  system through the removal of excess sludge.

 Six  concrete  tanks  will  be  constructed  and  they  are  to  be  equipped  with submerged
mixers (1.7kW) to ensure mixing of sludge and to avoid settling.  
 Operation will be controlled by time program through PLC – Scada system according to the
waste water level.
 A safety floater switch will be installed in order  to protect the mixer from dry operation.

 Maintenance of pumps and mixers shall be carried out by well trained persons at 2000
normal working hours or 1000 working hours if the liquid is muddy or sandy but at least
once a year.
 A manual hoist  will be installed for the pumps and mixers above the pit in order to lift for
maintenance purpose. 
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

ANOXIC TANK (DENITRIFICATION UNITS )
  Each  wastewater  stream  after  the  anaerobic  tanks  will overflow to  the  anoxic
tanks for denitrification. 
 Nitrogen  removal,  by  nitrifying  Ammonia  (NH3  or  NH4)  to  Nitrate  (NO3)  and 
then  de‐
nitrifying the Nitrate (NO3) molecules by stripping the Oxygen atoms to generate Nitro
gen (N) gas.
 De‐nitrification  requires a  retention  time  in Anoxic  conditions of over 30 minutes  in 
the  presence of a high concentration of Carbon. 
 Four submersible mixers  of 2.4kW each will be installed to keep the particles
suspended and to inhibit sediment formations.
 Operation of mixers will be controlled by time program through PLC – Scada system
according to the waste water level.
 A safety floater switch will be installed in order  to protect the mixer from dry operation.

 Maintenance of pumps and mixers shall be carried out by well trained persons at 2000
normal working hours or 1000 working hours if the liquid is muddy or sandy but at least
once a year.
 A manual hoist  will be installed for the pumps and mixers
above the pit in order to lift for maintenance purpose. 
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

AERATION TANK (NITRIFICATION UNITS)
  Aeration  tanks  are  designed  to  allow  efficient  removal  of 
pollutants  by biological processes. 
 The aeration system shall be based on bottom aeration, with compressed 
air  introduced into the tank bottom by rubber membrane diffusers.
 A total of four aeration tanks.
 Aeration  will  be  automatically  regulated  based  on  on‐line 
measuring  of  the  oxygen concentration in the individual tanks. 
 All  aeration  tanks  will  be  installed  an  oxygen meter  and  a 
pH meter.
 compressed air will be supplied from the blower station.
 The blowers shall be supplied with silencer hoods and the max.
acceptable noise level in the blower room is 80dBA. 
 Three blowers  (2  in oper. and 1 stand by) with capacity  2000m3/hr at
650mbar.
 
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

MIXED LIQUID RECIRCULATION PUMPING STATION   
 The wastewater from the four aeration tanks overflows into two separate pump
ing stations to recirculate mixed liquid back to anoxic tanks.
 Each mixed  liquid  pumping  station  has  been  designed  for  a  retention 
time  of  about  6minutes (peak hourly flow). 
 It  will  be  installed  three  (3)  submersible  pumps  (2  in  operation  and  1 
stand  by)  in  each pumping station, with capacity of 400m3/h at 7m, capable
for the recirculation flow.  
 pumps must be Contrabloc impeller type with minimum free passage of 
120mm and a max. speed of 980rpm.
 Operation  of  the  pumps will  be  controlled  by  inverter  through  PLC 
–  Scada  system according to the waste water level.
 Thus, a hydrostatic level control will be installed in the pit.

 Also, safety  floater  switch will be  installed   in order  to protect  the


pumps from dry operation.
 Each pumps will  be  installed  a  separate 
nonreturnable and check valve (knife valve).
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

MIXED LIQUID …..Cont’d   
 Also a pressure gauge will be installed in order to measure the
pressure of the pumping station.
 Each pump will be protected with moisture wet sensor and ther
mal protection of coil of the motor according to Manufacturer st
andards. 
 Electromagnetic flow meter will be installed at the output of eac
h pipeline in order to measure  the  flow.
 Maintenance of pumps shall be carried out by well trained
persons at 2000 normal working hours or 1000 working
hours if the liquid is muddy or sandy but at least once a
year.
 A manual hoist  will be installed for the pumps and mixers
above the pit in order to lift for maintenance purpose. 
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

CHEMICAL REMOVAL OF PHOSPHOROUS (COAGLANT PIT


 In case of difficult to reduce phosphorus concentration to <2mg/l by b
iological means alone. 
 The chemical processes for Phosphorus reduction require the addition 
of some sort of metal salts such as Fecl3.
of metal salts. Ferric or Ferrous Chloride is frequently used.  
 They tend to reduce the pH of the reactor.

 Chemical addition can also improve the final BOD quality of the treat
ed effluent.
 The chemical addition will be made 
in a mixing tank, which will contain also a  low speed agitator for
mixing with a rotated power of 0.37kW  rotated  at max. 4rpm.
 The  chemical  addition  will  be  made  by  a  dosing  system,  which 
shall  be  installed  in  a chemical room. 
 The dosing system will consists of one automatic preparation unit and 
a dosing pump.  
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

FINAL CLARIFICATION TANKS 
The wastewater after the aeration tanks passing through the coagulation
pit enters to final clarification tank (circular).
The liquid shall be diverted to the clarifiers’ centre. 
In the inlet point, an appropriately sized drum will be positioned in
each tank.
In  the  clarifiers the treated wastewater will be separated from the
biological sludge.
The  supernatant  shall  overflow  through  double  V‐notched 
overflow  weirs  that  will  be mounted in each tank to create tranquilly
hydraulic conditions for the sludge to settle unhindered.
The scum will be scraped and collected  in a scum pit from which 
it shall be pumped to a mixed storage sludge pumping station.
One bottom/surface scraper of half bridge will equip every tank. 
One sludge blanket meter shall be mounted in each scraper to detect the
 sludge level and automatically adjust the return flow rate. 
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

RECIRCULATION & EXCESS SLUDGE PUMPING STATION   
The sludge flows by gravity from the central rings of clarifiers to the return sl
udge pumping station.
Four (2+2 stand‐by) submersible pumps equipped with  inverters shall be 
installed  for the recycling of sludge in a common pipe back to each anoxic
tank.
The pumps  for  return  sludge  shall be 
submersible, operating at 950rpm with capacity of 175m3/hr at 7m.
pumps must be Contrabloc impeller type with minimum free passage of 
100mm and a max. speed of 1470rpm.
Operation  of  the  pumps will  be  controlled  by  inverter  through  PLC 
–  Scada  system according to the waste water level.
Thus, a hydrostatic level control will be installed in the pit.
Also, safety  floater  switch will be installed to protect pumps from dry
operation.
Each pumps will  be  installed  a  separate 
nonreturnable and check valve (knife valve).
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

SLUDGE PUMPING  …..Cont’d   
 Also a pressure gauge will be installed in order to measure
the pressure of the pumping station.
 Each pump will be protected with moisture wet sensor and 
thermal protection of coil of the motor according to Manuf
acturer standards. 
 Electromagnetic flow meter will be installed at the output o
f each pipeline in order to measure  the  flow.
 In the same pit will be 
installed two submersible pumps (1 
in operation & 1 stand by) for excess sludge. 
 Pumps will be with a capacity of  30m3/h at 12m and
will send sludge to aerated sludge tank.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

SLUDGE PUMPING  …..Cont’d   
 Pumps must  be  vortex  impeller  type with min. free  passage  of 
80mm  and max.  speed  1440rpm. 
 Operation  of  the  pumps will  be  controlled  by  inverter  through  PLC 
–  Scada  system according to the waste water level.
 Thus, a hydrostatic level control will be installed in the pit.

 Also, safety  floater  switch will be installed to protect pumps from dry
operation.
 Each pumps will  be  installed  a  separate 
nonreturnable and check valve (knife valve).
 Also a pressure gauge will be installed in order to measure the pressure
of the pumping station.
 Each pump will be protected with moisture wet sensor and thermal prote
ction of coil of the motor according to Manufacturer standards. 
 Electromagnetic flow meter will be installed at the output of each pipelin
e in order to measure  the  flow.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

SLUDGE PUMPING  …..Cont’d   
 Maintenance of pumps shall be carried out by well trained
persons at 2000 normal working hours or 1000 working
hours if the liquid is muddy or sandy but at least once a year.
 A manual hoist  will be installed for the pumps and mixers
above the pit in order to lift for maintenance purpose.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

FLOW MEASUREMENT 
 The effluent from the final clarification tanks shall be collected 
in one pit for each tank and through a pipe line to collection pit and
then to the flow meter.
 The flow measurement shall be installed parshall flume flow mete
r.

DISINFECTION UNIT – CHLORINATION TANK 
 The wastewater after  the  flow measurement unit will be discharged
to the disinfection unit (chlorination tank) in order to decrease the
microbiological load.
 This unit is designed with a plug flow scheme to have a retention
time of 20minute.
 A double dosing system of NaOCl (10‐110l/h) shall be  installed 
in order to send the chemical dilution at the entrance of the tank. 
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

SLUDGE TREATMENT 
 All wastewater treatment plants produce sludge as a by‐product. 

 quantity and quality depends on the method of sludge treatment.

 Disposal  must  be  considered  as  an  important  part  of  the  wastewater treatment

process.
 Sewage  sludge  is highly polluting  in  its  raw  state  and  can 
rarely be disposed of without some form of additional treatment to enable
environmentally acceptable disposal.
 volume of sludge requiring disposal is very often quite large and is generally considered 
economically viable to treat the sludge before final disposal. 
 The sludge, which is produced by the whole plant, needs further treatment before

dewatering.
 The treatments of sludge can be classified into two main forms, stabilization,
conditioning and dewatering.
 Stabilization is the process by which the organic load of the primary sludge is degreased.

 Conditioning is the process by which sludge is prepared prior to entering the final
treatment stage of drying or dewatering.
 The conditioning of the sludge is the mixing (primary and secondary) and thickening by

gravity.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

AERATED SLUDGE TANK 


 Normally, the primary sludge from the primary sludge pumping station enters
in the aerated sludge tank in order to be stabilized.
 The primary sludge contains a great quantity of organic load that is why
stabilization is necessary. The stabilization becomes through aeration of the
sludge.
 In extended aeration there is no production of primary sludge. The biological
sludge is already stabilized because of high solid retention time in the
bioreactors.
 However, an aerated sludge tank will be constructed in order to collect the
biological sludge.
 This tank will operate as balance tank in order to feed the thickening and the
dewatering system only 5 days per week.
 Aeration has been added not for the stabilization of the sludge but for mixing.

 The aeration system shall be based on bottom aeration, with compressed air
introduced into the tank by stainless steel tubular diffusers placed at the
bottom of the tanks.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

GRAVITY THICKENING
 The sludge is collected from the sludge tank.
 From this tank (2 + 2) submersible pumps 30m3/h at 12m are feeding the
two gravity sludge thickener.
 The sludge will enter the pumping station at concentration of 0,8% Dry
Solids (8000mg/l SS) and after the thickener it will be about 3%
(30000mg/l SS).
 A substantial reduction in sludge volume can normally be achieved by
consolidation in holding tanks.
 The sludge is allowed to settle under stable conditions, while supernatant
fluids are drawn off and recycled to the inlet of the treatment process.
 This method is not considered viable for the activated sludge treatment
process.
 The gravity thickener shall be equipped with bottom suction scrapers to
operate automatically.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

GRAVITY THICKENING
 The supernatant shall overflow through double V‐
notched overflow weirs that will be mounted in
each sludge thickener tank to create tranquilly
hydraulic conditions, for the sludge to settle
unhindered.
 The gravity sludge thickener shall be circular and
the tanks’ bottom will be straight.
 The sludge removal shall be via dry progressive
cavity pumps and they will feed the sludge
dewatering system.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

DEWATERING SYSTEM
Dewatering is an additional process to digestion by which the
conditioned sludge can be further treated by the removal of excess
water by mechanical processing.
As the name implies, it relies of the use of a belt press to separate the
water from the conditioned sludge, which is far more efficient in terms
of both land use and time, although will require the addition of an
additional energy input.
The use of belt press is generally efficient, increasing the dried solids
content of approximately 20% dry solids.
This system also needs the addition of a polyelectrolyte, on line before
the belt press.
The reject water outlets from the dewatering equipment shall be in
close connection with the floor drains in order to avoid any splashing.
The reject water shall be led back to the Inlet via the Internal Sewage
Pumping Station for Site Drainage.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

DEWATERING SYSTEM
The system shall be mounted with the necessary
numbers of valves for isolating pumps and plants as
well as sample cocks for inlet sludge, dewatered
sludge and reject water.
For rinsing the dewatering unit and dilution of the
polymer, treated wastewater shall be used from the
Technological Water Pumping Station.
Final sludge disposal is envisaged as for use in
agriculture i.e. land farming where applicable and
where the sludge is of suitable composition, subject to
the approval of the relevant authorities, or land filling
to a suitable landfill.
DETAILED DESCRIPTION OF TREATMENT SYSTEM  

DRAINAGES RECIRCULATION
 The drainage water from the sludge thickener and the
dewatering system is collected by gravity to the
drainages pit. From there by gravity, they go back to the
pre – anoxic tank.
CURRENT PROJECT STATUS
CONTRACT SUMMARY
No. Description Data
1 Date of signing of the contract 19 August 2016
2 Contract value / main 104,149,211.28 ETB without VAT and
agreement‘ 6,780,200.25 EURO without VAT..

3 Performance bond amount 27,501,025.89 ETB, Valid until October


10% of the contract amount 22,2019
(ETB+Foreign)

4 Contract Period 365 days as of the date of commencement

5 Commencement date For civil works - 31 December 2016


For activities that need the opening of Letter
of credit -04 April 2017

6 Completion date Civil work –31 December 2017


Electro mechanical work –04 April 2018
7 Revised completion date 13 July 2019
CONTRACT Cont..d
8 Percentage of work done (%)  General Provision & Provisional Sum-5% (Engineer’s
site office & Geotechnical Investigation)
 Civil work-42%
 Electromechanical-Work-3% (MAS preparation and
approval)
9 Advance payment guarantee 17,954,125.60 (Renewed amount)
Valid until April 12,2019
10 Advance sum paid 22,415,011.39 ETB with 15% VAT
11 Advance sum repaid Ethiopian Portion: Birr 9,143,225.84 with 15%
VAT
Foreign Portion : Nil
12 Advance sum repaid in % Ethiopian Portion: 40.8%
Foreign Portion : Nil
13 Interim payment certified to date Ethiopian Portion :- 34,585,245.57 ETB
by the consultant with15%VAT
Foreign Portion : -
14 Interim Payment certified in % Ethiopian Portion:- 28.9%
Foreign Portion :-
15 Time elapsed in days Civil works-790, EM works-696
16 Time elapsed in % 85.4% for Civil work, 83.8% for E-M Works
TECHNICAL PERFORMANCE (CIVIL WORK)
Progress
S.N Descreption
(%)
1 Unit 1. Lift Pump Station -
2 Unit 2. Self-Cleaning Screen -Grid Separator-Oil separator/PTU 110
3 Unit 3. Distribution Chamber -
Units 4,5,6, 7,8,9 11 and 12. Biological Treatment (Pre-Anoxic,
4 Anaerobic, Denitrification and Aeration tanks) 53.8
5 Units 10,13,14 and 15 Final clarification tanks 1.3
Units 21-23. Biological / Sludge Treatment (Dewatering Building /
6 Blower Building / Energy Building) 16.6
7 Unit 24 Control Building 90
8 Unit 25 Guard House -
9 Unit 18 Chemical Building 52.1
10 Units 16 and 17 Parshall Flow Meters and Chlorination Tank 23.4
11 Units 19 and 20 Aerated storage sludge tank and Gravity Thickener 120
12 Site and Compound works 11.9
13 Additional Bulk Excavation and Compound Leveling works 100
  Overall (Weighted average-Financial) 42
MAJOR PROBLEMS ENCOUNTERED

• Change of location of original project site –This has


taken some time to commence the project
• The issue of Electro-Mechanical work has taken long
time to resolve and the LC has not been settled yet.
• Slow progress of works due to shortage of materials
mainly reinforcement bar and ready mix concrete-
This has affected the progress significantly
• Problem of integration of civil work with E-M works
due to absence of E-M Contractor and shortage of
embedded puddle flange pipes.
CONCLUSION AND RECOMMENDATIONS
 The Civil work achievement is about 42%
 The Employer has approved VA TECH WABAG GmbH as
Electro-Mechanical Sub-Contractor in place of LANDUSTRIE
SNEEK BV
 The Employer is still expected to facilitate the opening of LC
as soon as possible
 The Contractor is now expected to Complete the remaining
civil works as per civil work program before the rainy season.

Das könnte Ihnen auch gefallen