Sie sind auf Seite 1von 65

Commissioning & Maintenance

of Protective Relays

GRID
Technical Institute

This document is the exclusive property of Alstom Grid and shall not be
transmitted by any means, copied, reproduced or modified without the prior
written consent of Alstom Grid Technical Institute. All rights reserved.
Test Options (1)

1. Primary injection sensitivity tests only

 Minimum of time consumed


 If results incorrect, secondary injection and CT tests
required
 Unable to check :-
a. Adequate timing curves
b. Directional properties
c. Power and impedance relays

 Not suitable for maintenance tests

> Commissioning & Maintenance of Protective Relays


Test Options (2)

2. Secondary injection tests


(But with C.T.’s still connected)

 True primary sensitivity easily equated


 If results incorrect isolated relay and CT mag.
curve checks necessary
 Ref. for maint., but system outage required
 Primary tests on C.T. ratio and polarity still
required on commissioning

> Commissioning & Maintenance of Protective Relays


Test Options (3)

3. Secondary injection tests


(But with relays isolated by test facility)

 Proof of isolated relay characteristic obtained


 Ref. for maintenance obtained
(relay if necessary tested with system on load)
 Full primary injection/on load tests done on initial
commissioning only

> Commissioning & Maintenance of Protective Relays


Test Options (4)

4. On load tests

 Checks that expected C.T. / V.T. quantities present at test


facility
 Scheme stability for external faults
 Proof of correct directional characteristics

> Commissioning & Maintenance of Protective Relays


Summary

ALSTOM’s preference:-

1. Secondary injection (isolated relay)

2. Primary injection
(incl. C.T. ratio, phasing and mag. curve)

3. On load tests

> Commissioning & Maintenance of Protective Relays


Site Testing and Commissioning
of Protection Equipment

 To assure ourselves, and the interested authorities,


that the overall protective system functions
correctly

 Resist pressures to take risks

 Study wiring diagrams and protection requirements


 Key diagram

 Delegate responsibilities

 Observe safety of self and others

> Commissioning & Maintenance of Protective Relays


Commissioning Flow Chart
Summary (1)

To assure ourselves, and the interested


authorities, that the overall protective
system functions correctly.


Study of wiring diagrams and protection
requirements.


Careful delegation of responsibilities to
reduce the duplication of effort and to
ensure that all the following aspects are
covered :-


> Commissioning & Maintenance of Protective Relays
Commissioning Flow Chart
Summary (2)

Insulation Tests

Secondary Injection Tests (Relay Tests)
 Ensure clean dust free area
 Mechanical inspection
 Out-going contact wiring
 External resistors
 C.T. shorting and isolating switches
 Contact follow-through and pressures
 Electrical checks on each basic electrical function
to prove satisfactory operation
 Prove trip and alarm circuits
 Test results (record and maintenance purposes)

> Commissioning & Maintenance of Protective Relays


Commissioning Flow Chart
Summary (3)


Primary injection tests
 D.C. flick tests on C.T.’s
 C.T. mag curve tests
 C.T. ratio and polarity tests
 Primary sensitivity tests
 Stability tests
 Test results

0 > Commissioning & Maintenance of Protective Relays


Commissioning Flow Chart
Summary (4)

 Line / Transformer / Generator energisation


 V.T. ratio and phasing tests
 On load tests
 Stability tests
 Directional properties

At the end of each stage ask yourself :-


Is there anything wrong, wiring or otherwise, that I
have not checked that may prevent correct operation
If so, CHECK IT OUT !

1 > Commissioning & Maintenance of Protective Relays


 Measuring instruments
 D.C. auxiliary supplies

Peak 1.6 x AV.

Average D.C.

0V.

Mean D.C. Peak to Peak V

<12% of mean D.C. comp.


0V.

 Faulty relays

2 > Commissioning & Maintenance of Protective Relays


Maintenance of
Protective Relays (1)

Frequency of Maintenance

Dictated by :-
a) The site condition
b) The availability of maintenance staff and
resources
c) The availability of plant outage times
d) The risks involved if the protection should fail
e) The type of relay construction

3 > Commissioning & Maintenance of Protective Relays


Maintenance of
Protective Relays (2)

Frequency of Maintenance (continued)

f) The proven reliability of devices under


identical site conditions
g) The availability of built-in self-check features
or semi-automatic test facilities, and the
difficulties of alternative tests
h) The interval of time an unexpected catastrophic
failure, component or otherwise, that may go
undetected and leave the system unprotected

4 > Commissioning & Maintenance of Protective Relays


Maintenance of
Protective Relays (3)

Onerous site conditions :-


1. Dusty or dirty environments
2. Corrosive chemical atmospheres
3. Frequent or continuous vibration
4. High humidity
5. High or cycling temperatures
6. Consistently high levels of energising or auxiliary
quantities
Typically maintain every 12-18 months under ideal
conditions and decrease frequency

5 > Commissioning & Maintenance of Protective Relays


Maintenance of
Protective Relays (4)

 Visual inspections

 The commissioning test stage

 At each maintenance test

 After heavy fault clearance

 More regularly if onerous site conditions


 Calibration tests
 Trip testing

6 > Commissioning & Maintenance of Protective Relays


Maintenance of
Protective Relays (5)

Recommended maintenance tests

 Instruction manuals
 Record relay settings
 Visual inspection
 Secondary injection tests
 Contact integrity
 Return to ‘in-service’ settings
 Check energising quantities

7 > Commissioning & Maintenance of Protective Relays


Maintenance of
Protective Relays (6)

 Relays involving static (electronic) components

 Electro-static discharge (ESD)

 Wrist straps

 Modern static relays (K-SERIES, MiCOM etc.)

 Fault find to board level only

 Protect boards

8 > Commissioning & Maintenance of Protective Relays


Corrective Maintenance of
Protective Relays (1)

 Cleaning solvents
 Trichlortrifluorethane (Ozone damaging)
(Arklone, Freon, Flourisol and Supersolve)
PROZONE
 Contact lubricants and other lubricants
 Contact cleaning burnishers
 Contact pressures and settings
 Dust removal
 Relay recalibration (Why?)

9 > Commissioning & Maintenance of Protective Relays


Contents of Section 23 of ‘PRAG’ (1)
(Protective Relay Application Guide)

 Insulation tests
 Current transformer tests
 Voltage transformer tests
 Test facilities
 Secondary injection tests
 O.C. and E.F.
 Differential
 Pilot wires
 Negative phase sequence
 Directional Distance
 D.C. operated

0 > Commissioning & Maintenance of Protective Relays


Contents of Section 23 of ‘PRAG’ (2)
(Protective Relay Application Guide)

 Primary Injection Test (+ on load tests)


 O.C. and E.F. relays
 Directional
 Generator Differential
 Transformer Differential
 Restricted E.F.
 Pilot Wire
 Busbar
 Negative phase sequence

1 > Commissioning & Maintenance of Protective Relays


Contents of Section 23 of ‘PRAG’ (3)
(Protective Relay Application Guide)

 Tripping and Alarm Annunciation

 Periodic Maintenance

In addition to PRAG :-
Consult instruction manuals

2 > Commissioning & Maintenance of Protective Relays


3 > Commissioning & Maintenance of Protective Relays
4 > Commissioning & Maintenance of Protective Relays
5 > Commissioning & Maintenance of Protective Relays
6 > Commissioning & Maintenance of Protective Relays
Test Terminal Block

To
Torelay
relaycoils
coils

A B C A B C N A BC N
To CT
To CT test
test To main
To main To
Tomain
mainVTVT
windings current
current
windings
(if any) transformers
(if any) transformers

7 > Commissioning & Maintenance of Protective Relays


Test Switch and Sockets

To relay coils

A A
Current B Voltage
test B
test
sockets C C sockets
N N

Test selector switch


Make before break
on CT Circuits

To main current To main VT


transformers

8 > Commissioning & Maintenance of Protective Relays


Current Transformer
Polarity Check

P2 P1

- S2 S1 +

Push
button
switch
- +
A

Battery

9 > Commissioning & Maintenance of Protective Relays


Current Transformer
Ratio Check
A B C Test plug
insulation
A2
Temporary
short 51
circuit
51
P1
S1
51

64
P2 S2
Relay or test block
A1 contact fingers

Primary injection
test set
250V AC supply

0 > Commissioning & Maintenance of Protective Relays


Testing Current Transformer
Magnetizing Curve

A B C Test plug isolating


current transformers
from relay coils
Variable
transformer
250V 8A
A
250V
To relay AC
P1 coils supply
S1 V

S2
P2
Main circuit Step-up transformer
breaker open if required

1 > Commissioning & Maintenance of Protective Relays


Voltage Transformer
Phasing Check

A
B
C A
V1

V2 C B

VN
V
VL
V1

V2

A B C Phase rotation
meter

2 > Commissioning & Maintenance of Protective Relays


Overcurrent Test Set

Fine control A
Coarse Range
variable control
transformer reactor adjusting CT

K1 I
K2
250V
AC 51
Relay
supply coil

Start Stop
timer timer

Supply Backing Injection


switch transformer Medium transformer Relay short-
10% control control circuiting switch
reactor

Relay current I = Ammeter reading (A) x K1 K2

3 > Commissioning & Maintenance of Protective Relays


Basic Current Control Circuit
of CFBA Test-Set

A
60Hz
L1 L2
50Hz
0.1A
10X 5X 2X 1X
220/250V 0.2A

O/V Detector
AC 60Hz 0.5A Output

Circuit
Supply to
Variac V1 50Hz
50/60Hz 1A Relay
2A

5A
Supply Shorting 10A
Switch Timer
Supply T1 Injection
Contractor Start ‘Matching’
(Break to Start) C.T.

Thermal Overload / Overvoltage


Protection

4 > Commissioning & Maintenance of Protective Relays


Sensitivity Check on
Biased Differential Relay

B B
OP

Test plug
fingers

To main current
Overcurrent transformers
test set

250V
A.C. supply
OP Relay operating coil
B Relay bias coil

5 > Commissioning & Maintenance of Protective Relays


Testing Bias Characteristics
(Using Overcurrent Test Set)

B B
OP
I1+I2 I1 I2
Test plug
fingers
A1 A2

R
To main current
transformers
Overcurrent
test set

250V A.C.
supply

6 > Commissioning & Maintenance of Protective Relays


Testing Relay Bias Characteristic
(Using Resistances)

B B
OP
I1+I2 I1 I2
Test plug
fingers

A1 A2

R1 To main current R2
transformers

250V A.C. A1 and A2 Ammeters


supply OP Relay operating coil
B Relay bias coil

7 > Commissioning & Maintenance of Protective Relays


Sensitivity Test

Feeder isolated
A
B
C

Test Relay
plug contact
Overcurrent 250V fingers
A.C. supply
test set

B B
OP OP

Pilots

8 > Commissioning & Maintenance of Protective Relays


Testing Sensitivity of Negative
Phase Sequence Relay

A
To main
current B
Relay
transformers C 46
250V coil
A.C.
supply N
Overcurrent
test set
Test plug Filter
in test block network

9 > Commissioning & Maintenance of Protective Relays


Test Equipment for Directional Relays

Supply switch
A
440V
B
3 phase
C
4 wire supply
N
Variable Choke
transformer
for current Relay
67
control current coil

Range adjusting CT
440/110V
phase shifting A PA
transformer

PA Relay
V 67
voltage coil

Variable transformer
for voltage control
To other voltage coils V Voltmeter
of relay under test A Ammeter
(if required) PA Phase angle meter

0 > Commissioning & Maintenance of Protective Relays


Primary Injection Test Set

A
250V A.C.
supply

Variable transformer 40A


Injection transformer
250/10 + 10 + 10V
10kVA

1 > Commissioning & Maintenance of Protective Relays


Primary Check on
Main Current Transformers

Temporary three-
phase short circuit
A
Primary 51
injection
test set B
250V 51
A.C. supply
C
51

51 Overcurrent relay
64 Earth fault relay A 64
A Ammeter

2 > Commissioning & Maintenance of Protective Relays


Sensitivity Test on Earth Fault Relay

250V
A.C. Primary injection
supply test set

A
51
B
51
C
51

64

3 > Commissioning & Maintenance of Protective Relays


Load Test on Directional
Overcurrent Relays

Direction of power flow


A B C for relay operation Load current

A PA
A PA V

A Ammeter B
V Voltmeter
PA Phase angle C
meter Directional overcurrent relays
4 > Commissioning & Maintenance of Protective Relays
Test Plug Link Connections to
Reverse Current seen by Relay

To relay

20 19 18 17 16 15 14 13 12 11

1 2 3 4 5 6 7 8 9 10
Test plug

To main VT and CT
5 > Commissioning & Maintenance of Protective Relays
Load Test on Directional Earth Fault Relay

ABC P1 P2 Loadcurrent
Load
current
S1 S2

V1
Temporary
IA short circuit V2
connections

A Insulating strips in
51 relay or test block V V
51 51 PA
P contact fingers V
A L N
P
PA
A
AA Ammeter
Ammeter
VV Voltmeter
Voltmeter Directional earth
PA
PA Phase
Phaseangle
anglemeter
meter fault relay

6 > Commissioning & Maintenance of Protective Relays


Testing Sensitivity of Generator Differential
Protection Using Primary Injection Test

87 Generator differential relay


Primary injection
250V A.C. supply V Voltmeter
test set A Ammeter

A Isolating links
Generator
A
B
C

87 87 87
V

7 > Commissioning & Maintenance of Protective Relays


Testing Sensitivity of Generator Differential Protection
Using Generator to Supply Primary Current

Temporary
short circuit
Isolating
Generator links
A
B
C

87 87 87
V

87 Generator differential relay


V Voltmeter
8 > Commissioning & Maintenance of Protective Relays
Checking Stability of Generator
Differential Protection

Temporary
Isolating short circuit
Generator links
A
B
C

A A A

87 87 87

Shorts across relay/


stabilising resistors 87 Generator differential relay
A Ammeter

9 > Commissioning & Maintenance of Protective Relays


Earth Fault Sensitivity Check on Transformer
Differential Protection

Temporary
short circuit

A A
B
Primary
injection
test set
C
250V
A.C.
supply Bias coils

Operating 87 87 87
coils

0 > Commissioning & Maintenance of Protective Relays


Phase Fault Sensitivity Check on Transformer
Differential Protection

Temporary
A short circuit
A
Primary
injection
B
test set
C
250V
A.C.
supply
Bias coils

Operating 87 87 87
coils

1 > Commissioning & Maintenance of Protective Relays


Stability Check on Transformer
Differential Protection

Generator Temporary short circuit

~
Bias coils
A

87 87 87
Operating coils
Instantaneous current distribution for three-phase short
circuit with phase A current at maximum

2 > Commissioning & Maintenance of Protective Relays


Sensitivity Check of Restricted
Earth Fault Protection

250V A.C.
supply A

Primary
injection
test set A
B
C

64 Earth Fault Relay 64


A Ammeter
V Voltmeter V
3 > Commissioning & Maintenance of Protective Relays
Stability Check of Restricted Earth
Fault Protection

250V A.C. supply


A Temporary short circuit
Primary
injection
test set
A
B
C

64 Earth Fault Relay


A 64
A Ammeter
4 > Commissioning & Maintenance of Protective Relays
Sensitivity Check of Negative
Phase Sequence Relay

A B C
Temporary
short circuit
Filter
network 46

Primary injection
test set

250V 46 Negative phase sequence relay


A.C. supply A Ammeter
5 > Commissioning & Maintenance of Protective Relays
Test Plug Link Connections for
Load Current Test
To relay
filter network

20 19 18 17 16 15 14 13 12 11

1 2 3 4 5 6 7 8 9 10

A B C N
6 > Commissioning & Maintenance of Protective Relays
Earth Fault Sensitivity Check
of Pilot Wire Relay

A A

B
C
Primary
injection
test set

B 250V A.C. supply


OP
Pilots to remote
end relay

B Relay bias coil OP Relay operating coil A Ammeter


7 > Commissioning & Maintenance of Protective Relays
Phase Fault Sensitivity Check
of Pilot Wire Relay
A B C

OP

B Relay bias coil


OP Relay operating coil
A Ammeter

Primary
injection Pilots to remote
test set
end relay
250V A.C. supply
8 > Commissioning & Maintenance of Protective Relays
Load Current Distribution

A B C A B C
Feeder

Instantaneous current
distribution of three-phase
balanced load with
phase A current at B B
maximum OP OP

Pilots

9 > Commissioning & Maintenance of Protective Relays


Short-Circuiting Connections
on Test Plug for Load Test

To relay summation CT
Short circuiting connections
on rear of test plug

20 19 18 17 16 15 14 13 12 11

1 2 3 4 5 6 7 8 9 10

A A B C N
To main current
transformers
0 > Commissioning & Maintenance of Protective Relays
Ratio Check of Current Transformers
of Reference Circuit

A1

250V A.C.
supply

Primary injection A2
test set Test
links

A
B Zone
C bus wires
N
A1 and A2 Ammeters
87 Busbar Protection relay
95 Supervision relay 95X
95X Bus wires short-circuiting 95 87 87 87
relay

1 > Commissioning & Maintenance of Protective Relays


Polarity Check of Reference
Circuit Current Transformers
A Ammeter A B C
Temporary short circuit
87 Busbar Protection
relay A
95 Supervision relay
95X Bus wires short-
circuiting relay

Test
links
A
250V A.C.
supply A
B Zone
Primary injection C bus wires
N
test set
95X

95 87 87 87

2 > Commissioning & Maintenance of Protective Relays


CT Inter-Group Ratio and Polarity Check in
Busbar Protection Scheme
Reference circuit Test circuit

Temporary
short circuit Test
links
A
A A A A
A 1 1 1 1
250V A.C. supply

Primary injection

B
C
N
Zone
test set

A1 Ammeter for ratio check A2 bus


A2 Ammeter for polarity A2
check A2 wires
87 Busbar protection relay 95X
95 Supervision relay 95 87 87 87
95X Bus wires short-
circuiting relay

3 > Commissioning & Maintenance of Protective Relays


Sensitivity Check of Busbar
Protection Scheme
A B C

250V A.C.
supply
Primary injection Test
test set links

A
B Zone
C bus wire
N
95X

V 95 87 87 87

4 > Commissioning & Maintenance of Protective Relays


Stability Test

A
B
C

Test Test
plug Overcurrent plug
test set

250V
A.C. supply
B B
OP OP

Pilots

5 > Commissioning & Maintenance of Protective Relays

Das könnte Ihnen auch gefallen