CONSTRUCTION OF 1 x

1000 MT MSV AT
JABALPUR (M.P.),
HPCL

1
Construction Of 1x1000 MT MSV at HPCL,
Jabalpur(M.P.)

KICK OFF MEETING


Date:- 05.11.2020

Client: Hindustan Petroleum Corporation Limited (HPCL)


TPIA : IRC Engineering Services Pvt. Ltd.
Contractor: Ishan Equipments Pvt. Ltd. (IEPL)

2
INDEX

• Project Synopsis
• HSSE
• Communication Protocols
• Brief Scope of work
• Site Organization chart
• Project Quality Plan
• 1st Month Activities.
• L-1 Schedule
• Machinery Mobilization Plan
• Assistance Required from HPCL
• Submittals 3
PROJECT SYNOPSIS

•Project Name: Construction Of 1 X 1000 MT MSV at Jabalpur, M.P.

• LOA Ref No.: CPO/2020-21/SKR/SM dated on 24.09.2020

•Owner : Hindustan Petroleum Corporation Limited (HPCL)

•Contractor : Ishan Equipments Private Limited (IEPL)

• Job Value: Rs. 15,68,22,039/- (Incl. GST)

•Completion Period : 12 Months from the Date of LOA

4
HSSE PLAN

1. The Project Team shall comply with all HSSE requirements as per the
Company & HPCL HSSE standards. HSSE Manual, plan, policy & procedures
which is implemented at all of our Project sites & they shall also comply it
with our company HSSE Standards.

2. All personnel of IEPL and its sub-contractors would be requisite HSSE


training, Induction, TBT, MTBT, HSSE Meeting at Work Places to achieve
the target safely.

3. HSSE Audit shall be held by HSSE Head/Management from HO/site at


regular interval in co-ordination with site team.

4. All HSSE requirements as per tender and company policy will be


adhered at site.

5
HSSE MANAGEMENT SYSTEM
1. Work Procedure and Risk Assessment for job activity.
2. HSSE induction to new and transferred employees about HSSE Management System and
details of site works with induction slide.
3. Tool Box Talk on daily basis by job performer.
4. Objectives and Targets with action program and responsibility for achievement of target.
5. HSSE training related job activity as per training matrix.
6. Internal Inspection / Audit as per project schedule and monthly schedule through
approved check lists.
7. Daily observation to identify UA/UC and its control measures by job performer.
8. Permit to work system (PTW system).
9. Weekly, monthly meeting to discuss about HSSE issues for control measures.
10. Formation of safety committee.
11. Incident/ accident/ near-miss/ near-hit report and investigation.
12. Monthly HSSE statistics report.
13. Third Party Test Certificates of lifting gears, equipments.
6
14. First-aid facilities with emergency vehicle.
HSSE ACHIVEMENTS

Appreciation Certificates from EIL & BPCL

7
COMMUNICATION PROTOCOL

Contact Person
IEPL TPI
Project Head-Head Office
Mr. Partha Mukherjee
Ph: +91-7043217643
e-mail: pm@ishanequipments.com
Project Manager-Head Office
Mr. Rajan Parmar
Ph: +91-7990935493
e-mail: epc1@ishanequipments.com
Project Design –Head Office
Mr. Pratik Shah
Ph: +91-9662053706
e-mail: engineering@ishanequipments.com
Site –RCM
Mr. Sanjeev kumar
Ph: +91-9024740410

8
BRIEF SCOPE OF WORK

Description UOM QTY


Major Scope of Work for Construction of one MSV at Jabalpur

Design/Detail Engineering of 1x 1000 MT Mounded Bullet & PESO approval. LS 1

Civil work includes ground improvement(If any), RCC raft and retaining wall, LS 1
Sand Filling, etc
Fabrication ,Erection of 1 x 1000 MT mounded bullet, including require NDT, LS 1
PWHT, HydroTesting.
Design, Engineering, supply, installation, testing and commissioning of LS 1
'Cathodic Protection system of mounded storage vessels.
Providing complete protective coating including supply & application
including transportation of materials, surface preparation application of PU LS 1
coating For 1X1000MT Mounded Storage vessels.
Supply and fixing of fire screen SQM 1440

Supply and Erection of Instrumentations as per SOR Items LS 1


ORGANIZATION CHART
Design & Engineering Project Manager Asst. Project Manager

Pratik Shah Rajan Parmar Pranit Joshi

RCM
Sanjeev Kumar

HSSE Engineer E & I Engineer


QA & QC Enginner HR & ADMIN
Civil Engineer Mechanical Engineer

Bablu Kumar TBA


TBA TBA TBA TBA
Ankit Singh

10
QUALITY PLAN

• ITP / QAP for all works.


• Fabrication and Erection Procedures of Mounded Storage of Vessels.
• WPS approval.
• PQR as per Specification.
• Daily Progress Report.

11
QUALITY POLICY

 We, at Ishan Equipments Pvt. Ltd., are committed to achieve full


customer satisfaction and enhancing fundamental value system of
our organization.

 We dedicate ourselves for continual improvement in all the field of


our business. We are committed to this objective by producing
quality products, services & systems, designed to meet the
expectations of our customers, complying with relevant codes,
standards, specification, statutory obligations and thereby foster
solid long terms partnership with them.

 We pursue quality improvement by periodic up-gradation of the


knowledge and skill of our personnel and through adoption of
contemporary technological advancements in our work culture.

12
1st MONTH ACTIVITY

Sr. Description Duration


No.
7 days from site handing
1 Mobilization of Site Staffs over
15 days from site handing
2 Mobilization of Equipment / Machineries
over
Submission of Documents & Procedure 15 days from site handing
3
(QAP/ITP/WPS) over
4 Establishment of Site office & Fabrication Yard. 15 days from site handover

5 WPS & PQR Qualification. 15 days from conducting the


test
Submission of DCI, MCI and Design & Drawings to TPI/ Already submitted and
6 BPCL/ PESO/ CCOE approved
30 days from conducting the
7 Mixed Design
mix design
8 Site Construction Activities/ Excavation of Mound 15 days After Site Handover

13
MACHINERY MOBILIZATION PLAN

Sr. Designation Nos. Mobilization Plan


No.
1 Crane Higher Capacity 1 From 4th Month
2 Ferana-F 15/ Hydra 1 From 2nd Month
3 Plate Rolling Machine 1 From 2nd Month
4 Welding Rectifier - 600A 8 From 2nd Month
5 SAW Welding M/c. 2 From 3rd Month
6 DG Set-125 KVA 2 From 2nd Month
7 Mother Oven (100 Kgs.) 2 From 2nd Month
8 DG Set-65 KVA 1 From 2nd Month
9 Idler Set (60/ 30 MT ) 2 From 3rd Month
10 JCB 1 From 1st Month
11 Pocklain 1 From 1st Month
12 Vibro Roller 1 From 2nd Month

14
 All Equipment/machinery shall be deployed at site well in time as per schedule.
SUBMITTALS

• QAP , ITP & Format.


• Construction Schedule (submitted after handing over of site).
• Manpower and Machinery Mobilization plan.
• Existing WPS & PQR.
• Application for issuance of Form III/ VII.

15
ASSISTANCE REQUIRED FROM CLIENT

• Availability of plate materials at site.


• Handing over of site for commencement of civil work
• Form III/ VII for Labour Licence.
• PESO approved site layout drawings
• Soil investigation report /Revised.
• TPIA approval on Design, Drawings and QC documents for civil and fire screen.
• Approval on PU coating without adding the primer/primer less PU coating.
• Change LOI dates from issuing date to site handover date.

16
THANK YOU