Beruflich Dokumente
Kultur Dokumente
Confidential
Essentials of Project and
Construction Management
Land is Life
In association with
Hill International, Inc.
1
THE PROJECT
Session 1
2
The Project
4
The Project Life Cycle
5
The Project Life Cycle
6
The Project Life Cycle
L
e
v
e
l
o
f
E
f
f
o
r
t
7
The Project Life Cycle
Concept Phase
• Gather data • Guesstimate Resources
• Identify need • Identify Alternatives
• Establish • Present proposal
– goals, objective • Obtain Approval for next
– basic economics, phase
feasibility
– stake holders
– risk level
– strategy
– potential team
8
The Project Life Cycle
Development Phase
• Appoint Key Team • Establish
Members • master plan
• Conduct Studies • budget, cash flow
• Develop Scope • WBS
Baseline • policies and
• end product(s) procedures
• quality standards • Assess risks
• resources • confirm justification
• activities • Present project brief
• Obtain approval to
proceed
9
The Project Life Cycle
Implementation Phase
• Set Up • Procure Goods and Services
• Organization • Execute Work Packages
• Communications • Direct/Monitor/Forecast/Co
• Motivate Team ntrol:
• Detail Technical Req.'s • Scope
• Establish • Quality
• Work packages • Time
• Information • Cost
Control Systems • Resolve Problems
10
The Project Life Cycle
Termination Phase
• Finalize Products
• Review and Accept
• Final Settlements
• Transfer Product Responsibility
• Evaluate Project
• Document Results
• Release/Redirect resources
• Reassign Project Team
11
The Project Organization
12
The Project Organization
13
The Project Organization
T h e P r o j e c t - B a s e d O r g a n iz a t io n
T h e B ig C h e e s e
P r o je c t 1 P r o je c t 2 P r o je c t 3
O il R e fin e r y O ffic e B u ild in g H o te l
D e s ig n D e s ig n D e s ig n
E n g in e e r in g E n g in e e r in g E n g in e e r in g
P ro c u re m e n t P ro c u re m e n t P ro c u re m e n t
C o n s t r u c t io n C o n s t r u c t io n C o n s t r u c t io n
14
The Project Organization
15
The Project Organization
16
The Project Organization
T h e F u n c t io n a l O r g a n iz a t io n
T h e B ig C h e e s e
M a r k e t in g P r o d u c t io n A c c o u n t in g
D iv is io n D I v is io n D iv is io n
P r o je c t X P r o je c t X P r o je c t Z
P hase 1 P hase 3
P r o je c t Y
P hase 3
17
The Project Organization
18
The Project Organization
19
The Project Organization
P u r e M a t r ix O r g a n iz a t io n
T h e B ig C h e e s e
E n g in e e r in g P r o d u c t io n A c c o u n t in g
D iv is io n D iv is io n D iv is io n
R e f in e r y
P ro je c t
H o te l
P ro je c t
O f f ic e
B u i l d in g
20
The Project Organization
21
The Project Organization
22
The Project Organization
M o d if ie d M a t r ix O r g a n iz a t io n
T h e B ig C h e e s e
E n g in e e r i n g P r o d u c t io n A c c o u n t in g M a r k e t in g P ro je c t
D iv is io n D iv is io n D iv is io n X
R e f in e r y
P ro je c t
O f f ic e
B u il d in g
23
The Project Organization
The Modified Matrix Organization
• Advantages:
– Tailor-made organization
– Balance between corporate/division needs
and those of individual projects
– Central coordinator(s)/Project Manager(s)
– Ideal for multi-project organizations
– Provision for Special or small projects
24
The Project Organization
• Disadvantages:
– Better suited for managing multiple projects
– Some staffing inefficiencies
25
The Project Team
26
The Project Team
27
The Project Team
Qualities of an Effective Project Team
T y p ic a l P r o j e c t T e a m O r g a n iz a t io n C h a r t
O p e r a t io n s P la n n in g
O w n e r / C lie n t E n v ir o n m e n t a l
G o v t R e la t io n s
O th e r
P r o je c t M a n a g e r
D e s ig n / P r o je c t
E n g in e e r in g C o n t r o ls
P r o d u c t io n /
F a b r ic a t io n C ost Q u a lit y D ocum ent
S c h e d u le C o n tro l C o n tro l
C o n s t r u c t io n / C o n tra c ts /L e g a l
I n s t a lla t io n
C o m m is s io n in g
29
The Project Team
The Owner
ACTIVE PASSIVE
• Maintains Day to • Not involved in Day
Day Control to Day Affairs
• Conflict with Project • Sets Overall
Manager Direction
• Better Product ? • Lack of Control ?
30
The Project Team
The Project Manager
31
The Project Team
Project Controls
• Critical Tools of the Project Manager
– Cost/Schedule
Control/Contracts/Legal
– Quality Control
– Document Control
• Provide the Checks and Balances for the
Project
• The “Police”
32
The Project Team
• Design/Engineering
• Construction/Installation
• Commissioning/Closeout
• Operations
• Ancillary Bodies
33
PROGRAM, PROJECT, CONSTRUCTION
MANAGEMENT AND OVERSIGHT
Session 2
34
What is Project Management?
Project Management for Design/
Construction can be defined as:
“the process of professional
management applied to the planning,
design and construction of a project
from inception to completion for the
purpose of controlling time, scope,
cost and quality.”
35
What is Project Management?
Scope Quality
Management Management
Time Cost
Management Management
36
What Is Project Management ?
CORE 1
SCOPE MANAGEMENT:
• Defining objectives
• Determine activities necessary to achieve the obje
ctives
• Monitor and control scope vs. objectives
• Quantify the resources
• Manage (inevitable) changes
37
What Is Project Management ?
CORE 2
QUALITY MANAGEMENT:
• Establish the standards of quality
required to meet the investment
objectives;
• Then manage the project to meet
these standards using Quality
Assurance and Quality Control. 38
What is Project Management ?
CORE 3
TIME MANAGEMENT:
• Plan the activities
• Schedule the activities
• Monitor and control actual
• Resolve impacts to
schedule/time
39
What is Project Management ?
CORE 4
COST MANAGEMENT:
• Define investment
• Prepare estimates
• Establish budgets
• Control actual vs. budget
40
What is Project Management ?
46
What is Project Management ?
47
What is Project Management ?
However, no matter what method you use,
every construction project requires the following:
Plan What You Want
Design What You Plan
Build the Design
O w ner
A r c h it e c t / G eneral
E n g in e e r C ontractor
S ubcontractors
49
Traditional Approach
50
Clerk of Works/ A/E Administration
Advertise Occupancy
Planning Design Construction
& Award Start-up
O w n e r
A rc h it e c t - G e n e ra l
E n g in e e r C o n tra c to r
S u b c o n tra c to r
V e n d o rs
51
Clerk of Works/ A/E Administration
52
Design/Build
Planning Design
Occupancy
Construction
Start-up
O w n e r
D e s ig n -B u ild
C on trac to r
D e s ig n e r s S u b c o n trac to r
V e n d ors
53
Design/Build
54
Project/Construction Management
Advertise Occupancy
Planning Design Construction
& Award Start-up
OR
Planning Design
Award Construction
Award Construction
Award Construction Occupancy
Start-up
55
Project/Construction Management
O wner
OR O wner
A r c h it e c t T rade Proje ct
E n g in e e r C ontractor C o n s t r u c t io n A rc h it e c t G e n e ra l C o n s t ru c t io n
M anager E n g in e e r C o n t ra c t o r M anager
T rade S u b c o n t ra c t o r
C ontractor
T rade
C ontractor
56
Project/Construction Management
57
Program Management
Project “A”
Project “B”
Project “C”
58
Program Management
O w ner
Program
M anager
A /E G .C C /M A /E G .C A /S G .C
O wner
Program
M anager
A /E G .C C/M A .E G .C
P ro je ct"C "
59
Program Management
• Management of multiple
projects
• Single Management firm
• Provides consistent standards,
controls and reporting on all
projects
• Effective management of
project interfaces
60
Project Management Oversight
(PMO)
O wner
PM O
C o n s u lt a n t
61
Project Management Oversight
(PMO)
• PMO is independent consultant to Owner
• PMO focus is top management
• PMO surveys, evaluates, reports on all aspects:
planning, design, construction
• No direct responsibility to manage project
• Can work with any other project delivery methods
• Good at identifying potential problems, facilitating
resolutions
• Most effective for large projects
• Most often used by Top management or funding agencies
not directly involved, e.g. Banks, Governments
62
Comparison of Delivery Methods
Traditional Clerk of Works Design- Program Project/ Project
A/E Build Construction Management
Administration Management Oversight
Principal -Owner has -Similar to -Fastest- -Applies Independent,
Advantages greatest control traditional allows fast- management experienced
-Design -A/E assists track expertise to project consultant to help
complete before Owner to -Owner deals -PM/CM is identify, solve
construction manage, which with 1 entity independent-focus problems
-Most common reduces Owners -Less is on project’s -Keeps top
system, familiar responsibility, responsibility success management
to Owners, many staff on Owner, -Brings informed,
contract forms less staff construction involved
available -Less expertise to design -Inexpensive
-Can be cheaper adversarial -Allows fast- (1%)
because less -Combines tracking and multi- -Assists all
consultants construction contracting parties to
expertise into -Gives Owner a establish effective
design wide, flexible controls,
range of services to reporting
select
-Less adversarial
-Owner has less
responsibility, less
staff
-Independent
inspection and
quality control 63
Comparison of Delivery Methods
Traditional Clerk of Design-Build Program Project
Works A.E Project/ Management
Administra Construction Oversight
tion Management
Principal -Slowest -Similar to-Less control -Owner has -May raise
Dis- -More traditionalby Owner less control potential
advantages responsibility on -Does not -Limited -Adds costs of conflict with
Owner, requires provide full
access to PM/CM Owner staff
larger staff management design team -Not always
-Price not known -A/E’s -Design often cost effective
till design interests subordinated to on smaller
complete can be construction projects
-Most adversarial- biased to -Requires
competing design careful
interests planning by
-No construction Owner
input to design -Not as many
-Difficult for firms who can
large, multi- do D.B
contractor projects
64
Planning for the
Success of the Project
Session 3
65
Planning is Essential
for a Successful Project
• Planning defines and quantifies the
measure of success
• Through planning, the project team defines
how it will organize to achieve this success
• Planning defines and develops the tools that
are needed to manage to success
• Planning defines the risks and establishes
the measures to avoid or manage the risks
66
Why Do We Need to Plan?
• Studies and case histories have shown
planning to be the single most important
factor for successful projects
• Planning is done at the very start, when we
have the most control
• Enables the project team to apply the
benefits of experience
• Anticipates problems and their solutions
67
Types of Planning
• First step of planning is to identify the
project mission:
• What is the project ?
• Who is the project for (the market) ?
• Why is the project being built ?
(short and long term projection)
68
Three Types of Planning
• Strategic planning
• Project scheduling
69
Strategic Planning
70
Operational Planning/Construction
Master Plan
• Analysis of available construction resources
within the company
• The impact of the new project
on existing work load
• Identification of the
required resources and
where to be acquired
71
Operational Planning/Construction
Master Plan (continued)
• Organize and control major work activities
to meet project goals
• Project budget/estimate
• Resource plan (people, material, systems)
• Project schedule
• Procurement plan (subcontracting, etc.)
72
Elements to Effective Planning
of Construction Projects
• Hill’s experience has shown seven (7) elements to
be necessary to construction project plans
(1) Clear Definition of Project Goals and Objectives
(2) Well Defined Project Organization
(3) Comprehensive Work Breakdown Structure (WBS)
(4) A Written Project Management Plan (PMP)
(5) Development of the Necessary Tools and Systems for
Managing the Project
(6) A Master Schedule
(7) An Effective Risk Management Program
73
Project Goals & Objectives
74
Project Goals & Objectives
(continued)
75
Project Organization
(2) Well Defined Project Organization
• Organizing the Project team early permits pro-active management and
establishes proper relationships of work and responsibilities.
• The project Organization should define the members of the project team
and outside parties affecting the project, for example:
Project Team Outside Parties
Owner - Banks and Financing
Operator - Insurers
Designers - Surety/Bonding
Contractors - Government and Regulatory
Project Manager
Consultants
76
Project Organization
• The Project Organization defines the roles
and responsibilities of the project team:
This includes:
• Scopes of Work (SOW)
• Responsibility/approval authority
• Reporting and communication matrix
• Interfaces between the project team members
77
Work Breakdown Structure
78
Work Breakdown Structure
(continued)
• Purpose of WBS:
(1) Organizes the work into detailed packages
(2) Assures that all necessary activities are
identified and organized
(3) Shows relationships of work packages
(4) Defines how the cost and schedule are to be
developed and integrated
(5) Assigns responsibility for all project work
79
Work Breakdown Structure
(continued)
80
Work Breakdown Structure
(continued)
W o r k B r e a k d o w n S tr u c tu r e E x a m p le
P r o je c t A
N e w C e n te r
AA AB AC
H o u s in g C o m p le x O f f ic e C o m p le x R e t a il C o m p le x
A AB 01 A A A01
D e s ig n D e s ig n
81
Project Management Plan
(4) A Written Project Management Plan
(PMP)
• A written document designed to cover all
project activities through project completion.
• Written by the Project Management Team
• Updated throughout project as elements of
the project change
82
Project Management Plan (continued)
Example: Table of Contents of one of Hill’s PMP Manuals:
PART 1 – Preliminary Design
1 Introduction
2 Summary
3 Objectives, Goal and Constraints
4 Assumptions/Anticipated Conditions
5 Organisation and Staffing
6 Preliminary Design Program
7 Permit Requirement
8 Project Control
9 Appendices
PART 2 – FINAL DESIGN & CONSTRUCTION PHASE
1 Assumptions/Anticipated Conditions
2 Final Design & Construction Phase
3 Scope of Professional Services
4 Project Organisation & Management
83
Tools & Systems
85
Tools & Systems(continued)
86
Tools & Systems (continued)
Quality 1) Quality Standards
2) Quality Assurance Program 3) Regulatory Requirements
e.g. CTMA 4) Quality Control and Inspection 5) Change Control
6) Non-Conformance and Corrections 7) Record-keeping
87
Tools & Systems (continued)
Communication/Documentation
1) Document Management 2) Logs and Reports e.g. -
submittals, RFIs, Change Orders 3) Management Information
System 4) Meetings 5) Procedures Manual
6) Approval and Reporting Matrices
88
Master Schedule
(6) A Master Schedule
• Summary of all major activities to achieve project
completion
• Defines overall time for project and the duration
for each major activity
• Confirms the feasibility of the overall project
duration
• Defines major milestones
• Identifies major interfaces with outside entities
89
Risk Management Program
Session 4
92
Creating and Implementing
PM/CM Tools
Successful management is like magic, it’s easy
if you have the tools. All you need are:
94
Creating and Implementing
PM/CM Tools
WBS (continued)
The WBS allows for the following:
• Estimates, costs, budget, schedule can be
established from detail level (bottom-up)
• The total program can be described as a
summation of subdivided elements/tasks
• Potential problems are detected at low level
early enough to be pro-active
95
Creating and Implementing
PM/CM Tools
W o r k B r e a k d o w n S t r u c t u r e E x a m p le
P r o je c t A
N e w C e n te r
AA AB AC
H o u s in g C o m p le x O ffic e C o m p le x S h o p p in g M a ll
AAB1 AAB2
V illa 1 V illa 2
A A B 1 0 2 -1 6 AAB101
C o n s t r u c t io n T r a t e s D E S IG N
A A B 1 0 2 S it e w o r k AAB1011 C o n c e p t D e s ig n
A A B 1 0 3 C o n c re te AAB1012 D e s ig n D e v e lo p m e n t
A A B 1 0 4 M a s o n ry AAB1013 S c h e m a t ic
A A B 1 0 5 M e t a ls AAB1014 C o n s t r u c t io n D r a w in g s
A A B 1 0 6 W o o d & P la s it ic
A A B 1 0 7 T h e r m a l& M o is t u r e P r o t e c
A A B 1 0 8 D o o r s & W in d o w s
A A B 1 0 9 F in is h e s
A A B 1 1 0 S p e c ia lit ie s
A A B 1 1 1 E q u ip m e n t
A A B 1 1 2 F u r n is h in g s
A A B 1 1 3 S p e c ia l c o n s t r u c t io n
A A B 1 1 4 C o n v e y in g S y s t e m
A A B 1 1 5 M e c h a n ic a l
A A B 1 1 6 E le c t r ic a l
96
Creating and Implementing
PM/CM Tools
Design/Scope Management
• At each level of design a validation
estimate needs to be conducted and
if higher than budget re-design
• Value engineering to be part of
design team during all design
stages
• Design to be frozen prior to
contractor award
97
Creating and Implementing
PM/CM Tools
Design/Scope Management (continued)
A common danger for cost overruns arises through“scope
creeps”and changes after the design has been frozen and
released to the contractor. These changes need to be
traceable and tightly controlled.
Changes after design is frozen must be:
• Estimated separately
• Analyzed for schedule impact
• Approved by Management
• Negotiated and settled with contractor ASAP
98
Creating and Implementing
PM/CM Tools
What is Cost Management?
Cost management is a function which
includes the processes that are required
to maintain effective financial control of
projects:
• Estimating, Budgeting and Cost control
• Scheduling, Evaluating and Monitoring
• Analyzing and Adjusting
• Reporting
99
Creating and Implementing
PM/CM Tools
Estimating
• Methods of estimating:
– Detailed bottom-up estimate
– Conceptual judgmental estimate
– Parametric historical cost parameters
– Firm Quotes from potential vendors
100
Creating and Implementing
PM/CM Tools
Estimating (continued)
The estimating effort should be continuous on
the project. Recommended levels are:
• Conceptual estimate
• Schematic Estimate
• Design Development estimate
• Construction drawing estimate
• Field Changes and Change Order Estimates
101
Creating and Implementing
PM/CM Tools
Estimating (continued)
• A contingency provision is to be included in
the various estimates, due to the percentage of
accuracy available at each level of design
• Concept/Feasibility 25%-40%
• Obtain project Funding 15%-25%
• Capital cost/budget 10%-15%
• Definitive/In field 7%-5%
102
Creating and Implementing
PM/CM Tools
Estimating (continued)
• By establishing a contingency the project
team has the ability to manage problems
and changes without alarming higher
management.
• Contingency usage monitoring is a good
indication on the performance of the project
team by Management.
103
Creating and Implementing
PM/CM Tools
Budgeting
The project budget sets a realistic projection for
material, labor, subcontractor and indirect costs on the
total project.
• A poor estimate/budget leads to an unrealistic budget
causing cost overruns and loss of control.
• The project budget is the baseline for cost control
104
Creating and Implementing
PM/CM Tools
Budgeting (continued)
At the capital stage the budget has to be
frozen and serves as baseline with costs and
future commitments.
• Budget breakdown in accordance with the
WBS
• Contingency usage is tracked and managed
105
Creating and Implementing
PM/CM Tools
Schedule
In construction projects there are usually two
schedules:
• Owners schedule - macro schedule stressing the
strategic planning goals including design
• Contractors schedule - fully detailed operational
schedule covering all the construction work
activities within the owner’s end date
106
Creating and Implementing
PM/CM Tools
Schedule (continued)
Two scheduling methods
• Bar Charts
• Logic-diagram-based schedules
Both have advantages and disadvantages
and are sometimes interchangeable
107
Creating and Implementing
PM/CM Tools
Schedule (continued)
Bar charts
• Advantages:
– Inexpensive and simple to prepare
– Easy to read and update
• Disadvantages:
– Inability to show enough detail to cover all Activities on
large projects
– Do not show the interrelation of activities
108
Creating and Implementing
PM/CM Tools
Schedule (continued)
Logic-diagram-based schedules
• Advantages
– Reveals interdependence of activities
– Calculates project completion dates
– Enables “what if” analyses
– Highlights critical activities
– Evaluates performance
109
Creating and Implementing
PM/CM Tools
Schedule (continued)
110
Creating and Implementing
PM/CM Tools
Schedule (continued)
• Contractor schedule can be used to
electronically update the Owner’s schedule
based on approved completion for each
period
• The ability to cost load the schedule and
produce earned value analysis
• Allows management of project float
111
Creating and Implementing
PM/CM Tools
Quality Control
• Conformance to requirements
• Doing it right the first time
• Fitness for the purpose
112
Creating and Implementing
PM/CM Tools
113
Creating and Implementing
PM/CM Tools
Quality Control Plan - Quality Assurance
• QA procedures
• Quality Systems Verification
• Identify& analyze issue
• Audits/observation
• Rework reporting
• Corrective action
• Training
114
Creating and Implementing
PM/CM Tools
Document Control
Integrated system based on the WBS for all
documents of the project.
• Organized filling facilitates team to work
• Engineering drawing tracking
• Correspondence tracking
• One stop shop for historical data
117
Creating and Implementing
PM/CM Tools
Session 5
120
The Project Manager
121
The Project Manager
Project Functional
Organization Organization
124
The Project Manager
• Skills of the Ideal Project Manager (2)
– Communication
• Listening
• Understanding
• Persuasion
– Planning/Organizing
• Flexibility
• Common Sense
• Positive Approach
• Goal-Setting
125
The Project Manager
• Skills of the Ideal Project Manager (3)
– Problem Solving Skills
• Analyzing and Problem Solving
• Negotiating
• Conflict Management
• Removing Obstacles
• Creativity
– Technical Skills
• Expertise/Experience/Credibility
• Current Knowledge
• Technical Problem Solving
126
The Project Manager
128
The Project Manager
• Responsibilities of the Project Manager (2)
– Lead the Project in:
• Acquiring Resources
• Selecting Team Members
• Developing user requirements
• Defining Scope and Quality
• Defining Budgets
• Determining Schedules
– Maintain control to assure the project is completed in
accordance with the requirements set forth
129
The Project Manager
• Responsibilities of the Project Manager (3)
– Report project status on a regular basis
– Ensure the completeness and adequacy of project
records and documentation
– Ensure that appropriate QA/QC procedures are set in
place and applied
– Specify testing requirements and ensure appropriate
tests are carried out so that the project meets design
requirements
– Maintain successful ongoing operations and
maintenance
130
The Project Manager
• Must be an Effective
Communicator
– Most of the working hours of a
Project Manager will be spent in
some type of communicator activity
– Conferences, meetings, writing,
memoranda, issuing and reading
reports, communicating with team
members, communicating with
management, talking to
customers/clients, talking with
contractors, subcontractors, and
suppliers
131
Reviving A Troubled Project
Session 6
132
Reviving a Troubled Project
I. WARNING SIGNS
133
Advanced Tools and
Techniques in Construction
Management
134
Value Engineering
135
Value Engineering
VE Potential Cost Savings
136
Value Engineering
Schematic
Potential
Design
for
Savings
from Design
Value Development
Engineering Contract
Documents
Construction
Time
137
Partnering
138
Partnering
• New term based on old concept
• Established 1988 by Army Corps of Engineers
• Each of the contractual parties respects the rights
and responsibilities of the other(s)
• Recognizes that every contract has an implied
good faith covenant
• Does not change the terms of the signed contract
139
Partnering
Army Corps of Engineers’ Definition
– ...“the creation of a relationship between Owner and Contractor that
promotes achievement of mutual and beneficial goals.”
Construction Industry Institute Definition
– ...”a long term commitment between two or more organizations for the
purpose of achieving specific business objectives by maximizing the
effectiveness of each participant’s resources. The relationship is based
upon trust, dedication to common goals and understanding each other’s
individual expectations and values. Expected benefits include
improved efficiencies and cost effectiveness, increased opportunity for
innovation and continuous improvement of quality products and
services.
• Eliminate “Us” vs.. “Them” attitude.
140
Partnering
Keys to Success
• Concept
• Begin early in process
• Establish mutual recognizance
• Select Independent facilitator
• Commitment from Corporate Management
• Continuously evaluate
• Properly allocate risk
141
Partnering Workshop
Partnering Workshop
• Signed Charter to Guide the Partnership
• Written Mission Statement and Objectives
• Specific Program to Measure Objectives
• Action Plan for Key Problems
• Establish Dispute Resolution Process
• Address Individual Roles and Concerns
• Team Evaluation Process with Facilitator
142
Partnering
Goals of Partnering
• On Time Completion
• Completion within Owner and Contractor budgets
• Deliver required quality or better
• Establish realistic, achievable schedule
• Reduce paperwork
• Avoid litigation or arbitration
• Eliminate lost/unproductive time
• Eliminate accidents
143
Partnering
Benefits of Partnering
• Owner
– Reduced Exposure to Litigation
– Better Quality
– Lower Risk of Cost Overruns and Delays
• Contractor
– Reduced Exposure to Litigation
– Increased Productivity
– Lower Risk of Cost Overruns and Delays
144
Partnering
145
FOR EXAMPLE
- 추진방향
The Conductor of
the Project Orchestra 구분 내용 비고
- 기성 관리
품질관리
- 공사비 분석
시공 관리 안전관리
- 추가공사 분석
- 민원사항 파악 준공지원
The Project
- 운영체계
구 분 내용
용역 기간 용역착수일로부터 사업완료 시 까지
발주단계 – 시공사 입찰 및 선정
용역 범위 시공단계 – 프로젝트관리 , 사업비검토 , 공정관리 , 품질관리 ,
계약관리 , 안전 및 환경관리 ,
클레임 예방 및 분쟁방지 , 시공사 관리
준공단계 – 입주관리 , 하자관리 , 시설물 운영관리 점검 (O&M)
Advanced Tools and Techniques
in Construction Management
지반검토 ( 현지지질정보 검토 및 반영 / 적용 )
설계도서에 대한 엔지니어링 검토
VE 활성화 방안 연구
1) 자재 검토 및 품질시험 확인
2) 시공계획서 및 시공상세도 접수 검토 승인
품질관리 3) 설계도서 이행 확인
1) 설계변경 내역 검토 및 확정
2) 기성검사 및 확인
시공단계 원가관리 3) 준공정산
1) 공정표 검토 및 조정
2) 주간공정회의 실시
공정관리 3) 지연공정의 만회대책 수립
4) 준공일정 관리
입주관리 1) 준공예비검사 실시
준공단계 2) 사용승인신청서 제출확인
하자관리 3) 인수인계서 작성 및 입회 (O&M Manual 작성지원 )
Design/ Build
설계 계약관리수행 지침
• 계약일반조건 / 계약특수조건 / 제반 계약 서류
• 기획설계 , 계획설계 , 기본설계 , 실시설계 등 단계별 설계에 대한 지침의 작성 및 운영을 검토
• 설계도서의 작성 , 제출 및 승인절차 , 진도율 관리 , 기성지급기준을 명확하게 관리
• 설계자 오류로 발생한 시공단계의 클레임에 대한 책임 및 처리 방안에 대한 설계자의 책임 강화
설계 도서 성과품 관리
시공사 선정 목표
• 기본방향 : 공사의 특성에 따른 경험과 공정성 , 투명성이 확보된 시공자 선정을 기본으로 함
• 선정심사기준
시공경험 평가 항목 및 배정 비교
기술능력 평가 항목 및 배정 비교
경영상태 평가 항목 및 배정 비교 ( 부도 / 부실 / 벌점 / 재해율 등 )
신인도 평가 항목 및 배정 비교 ( 신기술 / ISO/ 협력업체관리 / 환경관리 등 )
시공사 선정 입찰지원
분리발주 및 직발주 도입
• 전문성을 필요로 하는 공종을 분리 발주하여 관리함으로써 공사비 절감 및 효율성 증대
( 토목 / 철골 및 외부 판넬 / 건축 / 전기 etc)
• 발주자의 직접 계약으로 보다 책임감 있는 업체 선정 / 계약
• 건설사업관리자의 효율적인 업체관리로 양질의 성과물 확보
• 경제자유구역내 Procurement 무관세 사항 파악
Creating and Implementing
PM/CM Tools
– Design/Scope Management
– Cost management
– Schedule
– Quality control
– Document control
– Field management control
Creating and Implement PM/CM Tools
PM/ CM 윤리
OPEN DOOR POLICY
• Communication failure can
전문가윤리
neutralize all tools, no
matter how well they are [Professional Ethic]
established 공학윤리
• Common reasons are: (Engineering Ethic)
negative mode, not
기업가윤리
accepting other peoples
ideas, impatient, assuming ( 앙티프러션 )
others have the same 장인정신
information, reacting
(Workmanship]
without analyzing the facts
THE KEY FACTOR
THE TECHNICAL ‘BIG FIVE’
1. Risk Management
2. Project Procedures
3. Project Control Systems
4. Quality Management
5. HSE Management
THE COMMERCIAL ‘BIG TWO’
• RISK MANAGEMENT
• PROJECT PROCEDURES
PROJECT TEAM
Golf Course
Designer
Architecture
PROGRAM
CONTRACTS & ADMIN PCS Golf Course & Sitework Resort&Auxiliary Facilities
MANAGEMENT
MANAGER MANAGER CONST.MANAGER CONST.MANAGER
ANALIST
Hill Korea / 상주 Hill Korea / 상주 Hill Korea / 상주 Hill Korea / 상주
Hill Korea / 비상주
• Projects:
- UAE: 60story x 9buildings Mixed-use Development (Hotel, Residental,
Office towers)(US$2.5 billion) / 복합 콤플렉스 개발 PM
- USA: 700 unit Condominium Towers, two 40 story tower (US$ 300 Million) /
콘도미니엄 PM
International Cruise Terminal, San Francisco / 국제 크루즈 터미널 PM
Two 5-star Hotel and Golf Resorts, 717 Acres (US$ 120 Million) /
5 성급 호텔 및 리조트 PM
Mega scale Power Center (Shopping Malls) / 쇼핑몰
New Town Development / 신도시 개발
165
Prepared By Hill Korea CM ㈜
미국 Hill International Inc 합작법인
대표이사 차준석 / 공학박사 ( 건설경
영 /CM)
Tel : 02-849-5660
Mobile : 010-9251-9365
E-Mail : jsa 2100 @naver.com