Beruflich Dokumente
Kultur Dokumente
9th Edition
Chapter 10
Risk & Refinements in Capital Budgeting
Learning Objectives
Understand the importance of explicitly recognizing risk in the analysis of capital budgeting projects. Discuss breakeven cash flow, sensitivity and scenario analysis, and simulation as behavioral approaches for dealing with risk, and the unique risks facing multinational companies. Describe the two basic risk-adjustment techniques in terms of NPV and the procedures for applying the certainty equivalent (CE) approach.
Learning Objectives
Review the use of risk-adjusted discount rates (RADRs), portfolio effects, and the practical aspects of RADRs relative to CEs. Recognize the problem caused by unequal-lived mutually exclusive projects and the use of annualized net present values (ANPVs) to resolve it. Explain the objective of capital rationing and the two basic approaches to project selection under it.
Sensitivity Analysis
Simulation
Risk-Adjustment Techniques
Certainty Equivalents
Bennett Company is currently evaluating two projects, A and B. The firms cost of capital is 10% and the initial investment and operating cash flows are shown on the following slide.
Risk-Adjustment Techniques
Certainty Equivalents
Bennett Company
Project's A and B (10% cost of Captial) Year 0 1 2 3 4 5 NPV Project A $ 14,000 14,000 14,000 14,000 14,000 $11,071 Project B (45,000) 28,000 12,000 10,000 10,000 10,000 $10,924 (42,000) $
Risk-Adjustment Techniques
Certainty Equivalents
Assume that it is determined that Project A is actually more risky than B. To adjust for this risk, you decide to apply certainty equivalents (CEs) to the cash flows, where CEs represent the percentage of the cash flows that you would be satisfied to receive for certain rather than the original (possible) cash flows.
Risk-Adjustment Techniques
Certainty Equivalents
Bennett Com any
Certainty Equivalents Applied to Project A (Risk-free rate = 6%) Cer Year $ 2 3 4 5 r ect A 42 4 4 4 4 4 9 9 8 7 6 CE Cash flow s $ $ $ $ $ $ 42 26 26 2 98 84 9434 89 8396 792 7473 $ PVIF resent Value $ 42 887 2 4 94 4 7 763 6 277 4 544
Risk-Adjustment Techniques
Certainty Equivalents
Bennett Com any
Certainty Equivalents (Risk-free rate Cert in ear Project B ( ) CE Cash flow s ( ) PVI lied to Project B ) resent Val e ( )
project A
Risk-Adjustment Techniques
Risk-Adjusted Discount Rates
Bennett Company also wishes to apply the RiskAdjusted Discount Rate (RADR) approach to determine whether to implement Project A or B. To do so, Bennett has developed the following Risk Index to assist them in their endeavor.
Risk-Adjustment Techniques
Risk-Adjusted Discount Rates
R qu R k I 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 x R tu (R DR) 6% 7% 8% 9% 10% 11% 12% 13% 14% 15% 16%
Risk-Adjustment Techniques
Risk-Adjusted Discount Rates
Project B has been assigned a Risk Index Value of 1.0 (average risk) with a RADR of 11%, and Project A has been assigned a Risk Index Value of 1.6 (above average risk) with a RADR of 14%. These rates are then applied as the discount rates to the two projects to determine NPV as shown on the following slide.
Risk-Adjustment Techniques
Risk-Adjusted Discount Rates
Bennett Company
Risk st iscount Rat (RADR = 14%) P esent ear 1 2 3 4 5 Project A (42,000) 14,000 14,000 14,000 14,000 14,000 PVIF 1.0000 .8772 .7695 .6750 .5921 .5194 $ Value (42,000) 12,281 10,773 9,450 8,289 7,271 6,063 ied to P oject A
Risk-Adjustment Techniques
Risk-Adjusted Discount Rates
CAPM project RADR
Bennett Company
Risk Adjusted Discount Rate Applied to Project B (RADR = 11%) Present Year Project B PVIF Value
E(ri ) ! rf Fi [E(rm ) rf ]
IRR
SML
IRR
rf
project IRR SML accept the project NPV>0 project IRR SML reject the project NPV<0
Risk-Adjustment Techniques
Portfolio Effects
As noted in Chapter , individual investors must hold diversified portfolios because they are not rewarded for assuming diversifiable risk. Because business firms can be viewed as portfolios of assets, it would seem that it is also important that they too hold diversified portfolios. Surprisingly, however, empirical evidence suggests that firm value is not affected by diversification. In other words, diversification is not normally rewarded and therefore is generally not necessary.
Risk-Adjustment Techniques
Portfolio Effects
It turns out that firms are not rewarded for diversification because investors can do so themselves. An investor can diversify more readily, easily, and costlessly simply by holding portfolios of stocks.
Risk-Adjustment Techniques
CE Versus RADR in Practice
In general, CEs are the theoretically preferred approach for project risk adjustment because they separately adjust for risk and time. CEs first eliminate risk from the cash flows and then discount the certain cash flows at a risk-free rate. RADRs on the other hand, have a major theoretical problem: they combine the risk and time adjustments in a single discount rate adjustment.
Risk-Adjustment Techniques
CE Versus RADR in Practice
Because of the mathematics of discounting, the RADR approach implicitly assumes that risk is an increasing function of time. However, because of the complexity in developing CEs, RADRs are more often used in practice. More specifically, firms often establish a number of risk classes, with an RADR assigned to each. Projects are then placed in the appropriate risk class and the corresponding RADR is then applied.
Capital Rationing
Firms often operate under conditions of capital rationing -- they have more acceptable independent projects than they can fund. In theory, capital rationing should not exist -- firms should accept all projects that have positive NPVs. However, research has found that management internally imposes capital expenditure constraints to avoid what it deems to be excessive levels of new financing, particularly debt. Thus, the objective of capital rationing is to select the group of projects within the firms budget that provides the highest overall NPV
Capital Rationing
Example
Gould Com any Investment Proposals k=10%
Project A B C D E F ta vestm e t 0 000 0 000 100 000 0 000 0 000 110 000 RR 1 % 0% 1 % % 1 % 11% 1 PV of Inf ow s 100 000 11 000 1 000 000 000 00 1 NPV 0 000 000 000 000 1 000 00
Capital Rationing
IRR Approach G
(R Pr ject B C E
capital constraint 0,000 B C E
l Pr
k b IRR IRR 20% 16% 15% 12% 11%
ls
I itial I v $ t e t
8%
Capital Rationing
IRR Approach
Assume the firm c st f capital i 10% an has a maximum f $250,000 available f r investment. Ranking the pr jects acc r ing t IRR, the ptimal et f pr jects f r G ul i B, , an E.
G ul Pr
I i ial Pr ject B C E IRR I estm ent , , , , , D ,
al
u ulati e , , , , , ,
Capital Rationing
IRR Approach
If w e ra tio n c a p ita l u s in g the IR R a p p ro a c h a n d m a in ta in the ra n k in gs p ro v id e d b y IR R , the to ta l P V o f in flo w s a n d N P V w o u ld b e $336,000 a n d $106,000 re s p e c tiv e ly.
Capital Rationing
NPV Approach
C B A
Ho w ever, if w e ran k them su ch that N P V is m axim ized , then w e can u se o u r en tire b u d get an d raise the P V o f in flo w s an d N P V to $357,000 an d $107,000 resp ectively.
B C E 0,000
NPV
10 ,000
IRR
Inflow s