PARBATI H.E. PROJECTS

NHPC Limited

Welcomes
Delegates of
Dam of Parbati-II

Dam of Parbati-III

3rd Regional Customer Meet for Esteemed Beneficiaries

Projects under construction by NHPC in Kullu valley

PARBATI H. E. PROJECT STAGE-II ( 800 MW ) PARBATI H. E. PROJECT STAGE-III ( 520 MW )

PARBATI H. E. PROJECT STAGE-III ( 520 MW )

VIEW OF DAM AREA

SCHEMATIC DIAGRAM OF PROJECT


Lot-1 (M/s Patel-L&T Consortium) Lot-2 (M/s Jagger-Gammon JV)

Intake Tunnels

De-silting Chambers HRT


Power House GIS cum Transformer

D/s Surge Chamber

TRT

TRT Outlet

Intake

Spillway

SFT

Diversion Tunnels

SALIENT FEATURES
DIVERSION TUNNEL

- 2 Nos. 6.75 m Dia - 391 m & 440 m Length


- Rock fill 43m High 218 m Long - Orifice Type 2Nos. 7.2m Wide with 2 Radial Gates of 7.2m X14m - 2 Nos. 12.2m X 22.5m X 250m - 7.25m Dia. 7869m Long - Restricted Orifice Type 13m Dia 147m High - 2 Nos. Steel Lined 4.5m Dia 310m - Underground Machine Hall of Size 123mX22mX43.6m - 8.1m Size, 2713m Long - July.2012

DAM SPILLWAY

DESILTING CHAMBERS HEAD RACE TUNNEL SURGE SHAFT

VERTICAL PRESSURE SHAFT POWERHOUSE

TAILRACE TUNNEL COMPLETION SCHEDULE

SALIENT FEATURES
ANNUAL ENERGY GENERATION 1963 MU

Unit Tariff
(Current CERC notification and prevailing interest rate)

Rs. 2.97

CCEA CLEARED PROJECT COST


(AT MAY 2005 PRICE LEVEL)

2304.55 Cr.

CUMMULATIVE EXPENDITURE
(Up to Aug 2011- Provisional)

1539.02

CHRONOLOGY OF CLEARANCE

M.O.U (Govt. of HP & NHPC) Techno-Economic Clearance by CEA Environment Clearance by MOEF, Forest Clearances by MOEF CCEA Clearance (Govt. of India) Environment Clearance by SCST&E, Shimla (Govt. of H.P) Consent by HP SPCB

: 20 Nov.1998 : 12 Nov. 2003 : 16 Apr. 2005 : 13 Jun 2005 : 09 Nov.2005

: 26 Dec.2005 : 20 Jan. 2006

MAJOR HIGHLIGHTS
WORKS COMPLETED (DAM) 1. DT cum Spillway Tunnels including Lining 2. 3. 4. 5. 6. 7. 8. DT Intake Structure including HM gates Cut-off wall Overt lining of both Branch tunnels Excavation of HRT From Face-1,2,3 & 4 Concreting of Power Intake structure Intake Structure area concrete Spillway Control Structure Concrete

WORKS COMPLETED (POWER HOUSE) 1. 2. 3. 4. All Major Excavation Works. Barrel Concrete of Unit-1 & 2. Control Block Concrete TRT U/s Overt Concrete

MAJOR HIGHLIGHTS
WORKS UNDER PROGRESS (DAM) 1. Plunge Pool Excavation 2. HRT Concrete Lining WORKS UNDER PROGRESS (POWER HOUSE) 1. 2. 3. 4. 5. 6. 7. HRT Concrete Lining Surge Shaft Concrete Lining Pressure Shafts Concrete Lining Transformer Cavern Concreting Power House Unit-3 & 4 Concreting Surge Chamber & Draft Tube Concreting TRT D/s Concrete Lining

WORKS UNDER PROGRESS (E&M)


1. Assembling of Unit-1

Damages due to recent Cloud Burst near Adit-2

Damages due to recent unexpected rainfall

PARBATI H.E. PROJECT, STAGE - II (4x200MW)

LAYOUT PLAN PARBATI H.E. PROJECT STAGE-II (800 MW)


Diversion Tunnel Parbati River Intake structure

Head Race Tunnel Jiwa Nallah Sainj River Feeder Tunnel Adit 1 Power House

Pancha Nallah Trench Weir


Adit 2 Adit 3 Adit 4

Adit 5

PARBATI H.E. PROJECT, STAGE-II (800MW)


The Parbati Hydroelectric project Stage-II is a run off the river and interbasin transfer scheme and is spread over four valleys namely Manikaran valley, Garsa Valley, Sainj Valley and Jiwa Valley in Kullu district of Himachal Pradesh.

Chronology of Events
Date of Signing of MOU/PIA: DPR of Parbati Stage-II cleared TEC accorded Environmental Clearance RR Plan Approved Date of Signing of Implementation Agreement (IA) Schedule Commissioning as per IA Date of start of construction date Proposed Commissioning Date Project taken over from HPSEB on 20.11.1998 Oct-2000 Jan-2001 June-2001 Feb-2002 Sept-2002 (as per CCEA) Sept-2009 (as per CCEA) Sept-2002 Aug-2014

SALIENT FEATURES

DAM SPILLWAY DIVERSION TUNNEL DESILTING CHAMBERS

83.7m high Concrete Gravity across river Parbati 3 Nos. Orifice type, 6m x 9m Radial Gates 7.5 Dia., 275m long 3 Nos., 15m X 16m X 170m

HEAD RACE TUNNEL


SURGE SHAFT PRESSURE SHAFT POWERHOUSE

6m Dia., 31.5 km long (22.5 km by DBM & 9.05 km by TBM)


17m Dia., 130m depth 2 Nos., 3.5m Dia Steel lined 2150m & 2133m length (1546m Inclined) Surface, Size 123m x 47m x 44m

UNITS
RATED HEAD ANNUAL ENERGY GENR. ESTIMATED COST

4 Nos. of 200 MW each, Pelton Turbine


789m (Gross Head 867m) 3108 MU Rs. 3919.59 Crs.

TARIFF

Rs. 3.54 per KWH

PARBATI H.E. PROJECT STAGE-II (800MW)


UNIQUE HIGHLIGHTS
1. Two inclined pressure shafts of 1546M length each at an inclination of 300 successfully bored for the first time in the world by using Tunnel Boring Machine and completed in record time of 16 months. Concreting & Grouting in the inclined pressure shafts, behind the steel liners had been done up to a height of 800 meter by using Schwing pump for the first time in World. Total length of Head Race Tunnel is 31.52 km which is the longest hydro tunnel in India being constructed. In the Dam area, the weak zone of the hill (Fossil Valley) grouted successfully up to a depth of 120 m in two stages with ultra fine cement of high Blaine value imported from Japan, for the first time in India.

2.

3.

4.

PARBATI H.E. PROJECT STAGE-II (800MW)


STATUS OF WORKS
ITEMS
Dam & Intake Concreting HRT Excavation HRT Lining Surge Shaft Excavation Surge Shaft Lining Pressure Shaft Excavation Pressure Shaft Steel Lining and Concreting

UNIT
cum km km m m m m

TOTAL
1.96Lakhs 31.525 31.525 130 130 2 x 1546 2 x 1545

COMPLETED
1.78Lakhs (90.8%) 26.61 (84%) 15.586 (49.4%) Completed (100%) 50.9 (39.15%) Completed (100%) Completed (100%)

PARBATI H.E. PROJECT STAGE-II (800MW)


STATUS OF WORKS ITEMS
Power House SubStructure Concreting Power House SuperStructure Concreting

UNIT TOTAL
cum cum 28416 25000

EXECUTED
28416 (100%) 3398 (13.6%)

PARBATI H.E. PROJECT STAGE-II (800MW)

DAM CONCRETING

PARBATI H.E. PROJECT STAGE-II (800MW)

INTAKE STRUCTURE CONCRETING

PARBATI H.E. PROJECT STAGE-II (800MW)

CONCRETING IN DESILTING CHAMBER

Status of Head Race Tunnel (Excavation)


Total 31.525 Km
6251m 13099m 2038m 7375m 2434m 215m

PARBATI H.E. PROJECT STAGE-II (800MW)

F-0

F-1

F-2

F-3

F-4

F-6

F-7

F-8

F-9 F-10 F-11 Adit-IV Adit-V

Inlet Adit

Adit-I

Adit-II

Adit-III

LEGEND
COMPLETED
(Drawing not to scale)

26610m 4915 m

BALANCE

PARBATI H.E. PROJECT STAGE-II (800MW)

POWER HOUSE CONCRETING WORK

PARBATI H.E. PROJECT STAGE-II (800MW)

POWER HOUSE CONCRETING WORK

INCLINED PRESSURE SHAFTS


Inclined Pressure Shaft 2 Nos., Steel Lined 3.5m Dia. Each bifurcating into two Nos. 3m Dia. Penstocks near Power House

Inclined Pressure Shaft (Right) Total Length- 1545 m Excavation Completed- 1545 m (100 %) Lining Completed (100%).

Inclined Pressure Shaft (Left) Total Length- 1545 m Excavation Completed- 1545 m (100 %) Lining Completed -1545 m (100%)

300

300

PARBATI H.E. PROJECT STAGE-II (800MW)


Problems Encountered During Execution of Project A. Head Race Tunnel : Severe Rock Bursting due to high superincumbent cover (upto 1.6 km) Heavy sudden ingress of water of the order of 8000 lpm with 7000 cum discharge of silt encountered in the tunnel which had buried and damaged the TBM. TBM refurbished and the fault zone treatment being taken up in consultation with international experts.

PARBATI H.E. PROJECT STAGE-II (800MW)

Submergence of TBM due to sudden heavy ingress of water

PARBATI H.E. PROJECT STAGE-II (800MW)

Submergence of TBM due to sudden heavy ingress of water

PARBATI H.E. PROJECT STAGE-II (800MW)


Problems Encountered During Execution of Project B. Powerhouse : Occurrence of three major slides of Power House Back slope during Apr04, Jun06 and Feb07. C. Dam : Ban on Aggregates: Hon'ble High Court H.P had imposed ban on 03.08.07 on procurement of aggregate from any mining source in Distt. Kullu for all mega projects, which was lifted in March 2008. The work of Dam and other concreting was stopped during this period of 7 months.