Substation Energisation Training Procedure

S.E.T.P. Rev.01 Oct.14th 2010

P.B.&J.C.

PLEASE NOTE; There will be a short Q&A sheet to be filled out following the presentation. They are not technical questions but do require concentration during the presentation.

Basic Rules

Every Substation being energised must be locked prior to energisation. Security must be present at all times (sign in/sign out). LOTO permit is required to enter the room. Substations will undergo complete cleaning and visual inspection prior to energisation. Only personnel carrying a special energisation badge can enter the substations while Energisation is taking place. Signage identifying that the substation is under the Energisation process must be clearly visible at all times. LOTO representative must be present during energisation.

Energisation I.D badge

SUBSTATION ENERGIZATION AND MAINTENANCE

No. 001

Energisation I.D badge cont

This card is an official Identity Document of Sky Oryx Joint Venture duly issued to monitor and ensure safety of the area, to check necessary documents needed during the operation, to report any problems that may arise at site. USEFUL TELEPHONE NUMBERS: 1. Mr. Saji Joseph (Day) 5553-2678 2. Mr. Turo Kakimoto (Night) 5550-8075 3. Mr. Yoneda (SOJV RP) 3311-7768 4. Mr. Enrique (ANEL TA) 5514-6098 5. Mr. James Creighton (SOJV TA) 7785-2363 6. Mr. Kirk Rosenbaum (Cx Manager) 5554-8928 7. Mr. Coskun (EKIN) 7720-3119 8. Mr. Jasbir (Security Manager) 3317-8943 9. Mr. Abdullah Karakaya (SOJV ELEC Manager) 5554-3596 10. Fire Truck 5554-1694

Electrical system energisation- Arc flash dangers

The following videos are to demonstrate what can happen if the procedure is not followed correctly.

The following video shows a simulation of an arc flash occurrence.

The following video is an actual arc flash event.

Energisation process

Review meeting before work commences:

The personnel from CP-13 and CP-18 who are in charge of the Energisation Process will be identified. The Lead Engineer will decide if there are too many attendees present and request those not required for the process to leave. The Lead Engineer will identify means of egress, ensure that they are clear, and indicate the paths of egress to all attendees. A brief summary of work to be performed will be given by the Lead Engineer. The person carrying out the Energisation process will confirm that he has inspected the pre-energisation check list and concurs with the results.

Energisation process cont

Review standard energisation measures;

Substations are locked and security present at all times. Pre-energisation check list complete and accepted by all parties.

The lead Engineer will ensure that all safety equipment is present before work commences.
All participants are made aware of multiple exit points prior to energisation.

Layout of a typical substation


Egress path
Entrance door LVSS room

LVSS Panels

Exit door

Transformers

Entrance/egress to substation

Entrance door to Transformer Room only.

Layout of a typical substation cont


Boundary zone, all viewers must stand on the entrance side of the boundary line while the energisation process takes place.

Photo taken from entry door. Exit door

3 Mts.

Energisation Participants

NDIA (At their discression). Fire fighter (Mandatory). OBI (Mandatory). SOJV (Mandatory). Anel (Mandatory). Schneider (Mandatory). LOTO tagging authority/responsible person (Mandatory).

Safety prerequisite

All participants must wear appropriate PPE. Energisation Team must be aware of the boundary limitations by the Lead Energisation Engineer. This must not be less than three meters from test area. Viewing participants must not encroach beyond the boundary line. Energisation engineer must wear additional PPE;

Hard hat with face protection. Hearing protection (ear defenders). Approved insulated rubber gloves. Fire retardant jacket.

Safety prerequisite cont

Fire fighting equipment;


Dry type Fire extinguisher. Fire blankets.

Trained fire fighter present. Hot Stick

Energisation procedure

Pre-energisation:

Substations are to be locked. Security personnel present at all times and limit access to personnel with LOTO permits and energisation badge. Substations undergo complete cleaning and visual inspections. Complete and submit Lock Out Tag Out Permit Form indicating energy sources and required isolation points.

Energisation procedure cont

Energisation:

The Energisation Team will be the only personnel allowed enter the substation. All personnel present must possess an energisation badge. LOTO tagging authority or responsible person must be present and verifies all locks and tags are in place. A copy of the test procedure must be present at all times. Ensure there are Energisation Warning Signs in place. CP-13 must verify energisation from the cup. Ensure all participants are wearing the required PPE for the necessary role they are taking in the process.

Energisation procedure cont


After energisation from the cup, CP-13 and CP-18 decide together which transformer to energise. Related medium voltage switchgear is turned on. CP-18 checks phase voltages and phase rotation on the LVSS panel. If all checks are ok, the main circuit breaker is turned on after the tagging authority has removed the required locks and tag.

Energisation procedure cont


During this operation all the out going feeders must be switched off and racked out. This procedure is repeated for each transformer.

Post energisation: The room is locked and is monitored by security at all times. All personnel must have a permit signed by the LOTO team before re-entry. Any personnel without a permit issued by LOTO will be refused entry, but an Energisation Badge qualifies.

Conclusion

Following Energisation, SOJV informs security that the system is live. SOJV hand back substation control to the security team.

All substation doors must be locked at all times and security staff present at all times. Security must check that people entering have the required and up to date permit approved by LOTO office

The energisation process is a very dangerous procedure and extreme caution is required.