Sie sind auf Seite 1von 88

Project Preparation and Administration

Bridge Module

Why are bridges part of this training?


Big cost. Long Process Design is complicated Tough Decisions

R1 Trails Project Preparation

But they are Fun!

Proud crew!

Trails do nothing more than connect the Bridges!

R1 Trails Project Preparation

Training Focus
Bridge Design Process
Decisions to be

made. How to make those decisions!

R1 Trails Project Preparation

Training Focus
Northern Region Standard Trail Bridge Plans

Intended uses Limitations, Inappropriate Uses Costs Maintenance

Wilderness Bridges Helicopter Usage Preservative Treatments If there is time NP Wilderness Bridge Project Presentation

R1 Trails Project Preparation

Authorities
All Decisions Line Office Approval of Bridge Design Director of Engineering
Unless using

Regional Standard Trail Bridge Designs Forest Engineer.

All Trail Bridges need to be designed!


R1 Trails Project Preparation

Bridge in Bob Marshall Wilderness

Authorities
Design Resources Available.
Forest Engineer
Regional Bridge Group

John Kattell David Scovell

Our job is to provide technical assistance to Forest personnel and complete and/or approve all bridge designs.

R1 Trails Project Preparation

Bridge Design Process


Function (To bridge or not? Replace or remove?) Project Scope** Who is User? ROS? TMO? Force Account/Contract?

**Contact FE and /or RO during Project Scope


Location/Survey Where is best spot? Many decisions. Preliminary Design

Project Funding and Scope finalized.

Plans, Specs, Estimates.

Final Design
Construction COR

R1 Trails Project Preparation

Project Initiation and Scope


Function
To Bridge or Not to

Bridge? Replace or remove? Preliminary Engineering needed?

Factors?
TMO & ROS User Safety Resource Protection Others?

Albino Trail Bridge Site - Gal


R1 Trails Project Preparation

Funding Feasibility Aesthetics Wilderness

Bridge Design Process


In general, more complicated than road bridges. Why?
Defining the User Location Access Wilderness Size?

R1 Trails Project Preparation

Bridge Design Process


Dome Mtn. On Ktn.
24-foot span Wilderness 6-mile from TH but

4000 ft elevation gain. Force Account Dangerous work.

R1 Trails Project Preparation

Bridge Design Process


Iron Springs on D-P
50-foot span Easy access Total cost -

Maah-Taah-Hey Trail

~$35,000 Contract

R1 Trails Project Preparation

Project Initiation and Scope


Define the User (TMO & ROS)
Pedestrians Stock ATVs Bicycles Administration vehicles Outfitters / other permittees
User affects size, design

and cost. Bridge many times limits the user!

R1 Trails Project Preparation

Project Initiation and Scope


Force Account or Contract?
decisions!) (Effects design

Design (in house or A/E) Complexity of bridge project. Availability of Forest or RO Engineers Funding Typically, R1 designs are done in house. Construction Safety Force Account capability, skill level, and availability. Complexity of bridge. Funding Pros and Cons

R1 Trails Project Preparation

Force Account or Contract?


Goat Creek on NP
Remote site required packing all materials. Simple construction NP has trained Crews. Force Account

R1 Trails Project Preparation

Force Account or Contract?


Yellow Mule on Gallatin

Bridge part of a larger trail construction project. Short distance from trailhead. Complicated construction Contract

R1 Trails Project Preparation

Force Account or Contract?


Mystic on Custer
Site at trailhead. Working over large water penstock and tracks. Needed large equipment
Contract

R1 Trails Project Preparation

Project Initiation and Scope


Summary
Function (To bridge or not to bridge)
Define Users. Force Account versus Contract

Funding. Project a go or no go?


May need some preliminary engineering

this early.

Who makes these decisions?

R1 Trails Project Preparation

Location / Survey
Location
Narrowest spot? Not necessarily Stable stream reach. Where users want it! Good trail

Survey - Varies
Simple small creek

Profile of trail and stream with few xsections. Sketches


Complex

approaches for user


(function for hikers vs stock vs snomobiles vs ATVs)

Full site survey of area. Geotechnical (drilling)


In general, experienced

bridge engineer may get by with less.

R1 Trails Project Preparation

Location / Survey
Holter Cut on Btr. No survey done.

R1 Trails Project Preparation

Location / Survey
Little Salmon on Flathead in Bob Marshall. Full site survey completed. Needed for hydraulic analysis.

R1 Trails Project Preparation

Preliminary Design
Determine
Span

Factors
Crossing and height Flood waters, Clearance User Span, location, aesthetics Site geology See earlier slide All of the above.

Height
Width Bridge Type

Foundations
FA or Contract Cost

R1 Trails Project Preparation

Preliminary Design
Two biggest problems in R1

Bridges too short.


Abutments scour and fail Resource damage

R1 Trails Project Preparation

Preliminary Design
Bridges are too low!

R1 Trails Project Preparation

Preliminary Design
Sill-Thru Configuration Little work in water. Hydraulically efficient. (less susceptible to scour). More $ in superstructure, less in abutments. No wingwalls needed.

R1 Trails Project Preparation

Preliminary Design
Vertical Wall Configuration More work in water. Hydraulically less efficient. (more susceptible to scour). Less $ in superstructure, more in abutments. Need wingwalls

R1 Trails Project Preparation

Preliminary Design
Span Length
Field Estimate (Rule of Thumb) typical spill-thru bridge.

BH

Span Length (L)

Estimated Span Length (L) = BW + 3 x BH BW Channel bottom width BH Bridge height from channel bottom to trail tread.

R1 Trails Project Preparation

Preliminary Design
Span Length
Field estimate must be verified on paper. Do not undersize. Better to spend more on span than abutments. Evaluate existing bridge (did it function OK) Iterative process with what? Bridge height
What controls bridge height?

R1 Trails Project Preparation

Preliminary Design
What controls bridge height?
Trail height Bridge structure

depth
Rule of thumb 1/20 x span
Clearance for debris

Minimum 2 feet above high water (100 yr flood) to bottom of bridge.

Little Salmon on Flathead

R1 Trails Project Preparation

Preliminary Design
Span Length Vertical Wall abutment

BH

Span Length (L)

Span Length = Bankfull +. Must be able to pass

flood without damage to bridge or stream. Footings must be below stream bed as minimum unless on bedrock.
R1 Trails Project Preparation

Preliminary Design
Factors for Bridge Width - Users - Railing

Bridge w/o railing

R1 Trails Project Preparation

Preliminary Design
Variable widths
Single log 14 Stock w/railing 8 Snowmobile 16+ Manual guidance but can be anything.

Bridge with railing


R1 Trails Project Preparation

Preliminary Design
Bridge Types
Single Log

Timber stringer
Glu-lam stringer Truss Suspension Packable

Factors
Span Access

Aesthetics Materials

R1 Trails Project Preparation

Preliminary Design
Foundations
Spread footings Gabions Geocell Walls

Factors
Site geology Site materials Access Scour Potential

Generally we use spill-thru configuration with timber sill on gabion or geocell.

R1 Trails Project Preparation

Preliminary Design
Costs
Very difficult to estimate.
No rules of thumb. Procedure Take off and price materials (variable) Crew up labor.
$2500/day for crew of 4 with misc.tools/equipment Or use Davis Bacon rates

Estimate Equipment needed (cranes, backhoe, helicopter)

R1 Trails Project Preparation

Preliminary Design
Costs - continued
Materials Sawn Timber GL timber Bolts/hardware Concrete Reinforcing Steel Gabions Geocell Geocell fill

$1350/mfbf $2500/mfbf $3.00/lbs. $600 - $1000/cy $1.25/lb $125/cy $15/cy $25-$75/cy

R1 Trails Project Preparation

Preliminary Design
Costs - continued
Equipment Excavator Backhoe Dump Truck Crane (Light) Crane (medium) Helicopters Packing
$130/hr $80/hr $75/hr $350/hr $650/hr See later slides

$225/mule trip (180 lbs per mule)

R1 Trails Project Preparation

Preliminary Design

Typical work items to accomplish for labor.


Project Management

Less Common Work Items


Helicopter use.

Mobilization
Excavation Build Abutments Install Superstructure

Packing Materials
Supply Camp Install Falsework.

Build Approach walls


Build Approach fills

R1 Trails Project Preparation

Preliminary Design
Nail Lam built 15 years ago. Replace with glulam stringer bridge. On sills. Wilderness Use Helicopter to fly in stringers. Estimate based on Contract Construction Flood Creek Custer

R1 Trails Project Preparation

R1 Trails Project Preparation

Preliminary Design
Whose Responsibility / Authority for preliminary decisions?

Forest!
However, Engineering must assist! Why? Call FE and or RO during Project Scope for assistance with alternatives and options. Meet with Rec staff and Ranger to discuss preliminary design options and alternatives.

R1 Trails Project Preparation

Preliminary Design
At this point
Re-evaluate Project Scope! Re-evaluate Funding!

Why?
Many times each site has several

alternatives being evaluated. Must select Final Design Alternative.

R1 Trails Project Preparation

Final Design, PS&E


Typically done by Engineering Plans (as a minimum)
Title Sheet (signatures) Bridge Layout (Plan and Elevation) On site plan from survey. Abutment/foundation details Superstructure details Miscellaneous details

R1 Trails Project Preparation

Final Design, PS&E


Specifications
FP-03, Standard Specifications for

Construction of Roads and Bridges on federal Highway Projects. Special Project Specifications as needed.

R1 Trails Project Preparation

Final Design, PS&E


Estimates
Estimated Construction Costs Update of preliminary estimate Estimated Schedule for Construction

R1 Trails Project Preparation

Final Design, PS&E


Plans, Specs and Estimates
All 3 required. Any difference for Force Account vs

Contract?
Shouldnt be!
Authorities Regional Engineer must approve PS&E package, UNLESS Using Standard Plans, then FE has authority to approve PS&E package.

R1 Trails Project Preparation

Construction
All Trail Bridge Construction is to be administered and inspected by
Certified COR, Level III With appropriate technical endorsements. Any difference for Force Account vs

Contract?
NO!
RO will assist as needed or requested.

R1 Trails Project Preparation

Trail Bridge Standard Plans


Pre-designed and detailed drawings for:
Typical Trail
Iron Springs on Maay-Daay-Hey Trail

Bridge Superstructures Typical simple substructures (sills).

R1 Trails Project Preparation

Trail Bridge Standard Plans


Intended Uses
Simple, single spans Spans less than 60 feet Adapted for each site. FE can approve.

Limitations
At discretion of FE only.
Not for complex bridges. Not for difficult

abutments. Still requires, survey, hydraulic analysis, soils, etc.

R1 Trails Project Preparation

Trail Bridge Standard Plans


Typical Superstructures:
Solid Sawn Timber Stringer

Drawing #
R1920 R1921 R1922 R1923 R1924 R1925 R1926 R1927

Log Stringer
Glu-lam timber stringer Glu-lam longitudinal slab

Single log
Nail-lam longitudinal slab Prefabricated steel truss Packable spliced stringer

R1 Trails Project Preparation

Trail Bridge Standard Plans


Typical abutment details
Various types of sills used

Drawing #
R1930-34

Will need to be customized for each site.

R1 Trails Project Preparation

Trail Bridge Standard Plans


Sawn Timber Stringer
Spans 10 to 40 feet

Any width
Stringers 3x10 to 8x24 ROS - ??? Economical if you have

used stringers. But stringer quality large than 4x10 gets iffy. Costs increase significantly with larger stringers.

R1 Trails Project Preparation

Trail Bridge Standard Plans Sawn Stringer

R1 Trails Project Preparation

Trail Bridge Standard Plans


Log Stringer
Spans 10 to 45 feet.

Any width.
Diameter from 8 to

22 ROS ??? Costs are higher Than other types for similar spans. More difficult to build and maintain.

R1 Trails Project Preparation

Trail Bridge Standard Plans Log Stringer

R1 Trails Project Preparation

Trail Bridge Standard Plans


Glu-laminated Stringer
Spans 25 to 60 feet.

Any width.
Stringers 3.125 x 15 to

8.75 x 39. Requires diaphragms. ROS - ???? Most ecomomical for spans 40 feet or longer. Easy construction but requires larger equipment. Low maintenance.

R1 Trails Project Preparation

Trail Bridge Standard Plans GL Stringer

R1 Trails Project Preparation

Trail Bridge Standard Plans


GL Longitudinal Slab
Spans 10 to 35 feet.

Best for widths < 8.


Come in panels, max

4 width. ROS - ??? Very ecomomical Easy to build. Low maintenance Handrail more difficult to attach.

R1 Trails Project Preparation

Trail Bridge Standard Plans GL Longitudinal Slab

R1 Trails Project Preparation

Trail Bridge Standard Plans


Single Log Stringer
User is hiker only.
Spans 10 to 45 feet. Diameters 16 to 24 ROS ???. Handrail is hard to

attach and align. Handrail may be maintenance problem.

R1 Trails Project Preparation

Trail Bridge Standard Plans Single Log

R1 Trails Project Preparation

Trail Bridge Standard Plans


Nail-Lam Longitudinal Slab
Spans 12 to 30 feet.

Best for widths < 8.


Materials 2x6 to 2x14. ROS - ??? Labor intensive. Materials less expensive but

labor is higher. Good for sites short distance from trailhead but not accessible for equipment Moderate maintenance. Handrail difficult to attach.

R1 Trails Project Preparation

Trail Bridge Standard Plans Nail Laminated Slab

R1 Trails Project Preparation

Trail Bridge Standard Plans


Prefabricated Steel Truss
Spans > 60 (Standard

Plans limited to 100) Any width. ROS ??? Requires heavy equipment. Too heavy for economical use of helicopters. Requires manufacturer design and shop drawings. Low maintenance.

R1 Trails Project Preparation

Trail Bridge Standard Plans Prefabricated Truss

R1 Trails Project Preparation

Trail Bridge Standard Plans


Packable Bridge
Span 36 feet or less.

Any width.
ROS - ??? Alternative to

helicopter use. Expensive materials. Labor intensive. More difficult to build. Increased maintenance.
R1 Trails Project Preparation

Trail Bridge Standard Plans Packable Bridge

R1 Trails Project Preparation

Trail Bridge Standard Plans


Abutment Details
Sill designs - Spill-thru

Keep away from stream

edge. Not applicable if scour issues. Do not stack sills to gain height. Place on geocell, gabion, or concrete pad. Need to be site adapted.

R1 Trails Project Preparation

Timber Cribbing & Rock Gabions

Sill on Gabion Sill on Timber crib on geocell

R1 Trails Project Preparation

Others Trail Bridge Types


Timber Truss
Spans 50 to 100+

feet. Any width ROS ??? Labor intensive. Difficult to build Moderate maintenance. Can be built with semi- primitive tools or heavy equipment.
R1 Trails Project Preparation

Others Trail Bridge Types Timber Truss

R1 Trails Project Preparation

Others Trail Bridge Types


Suspension Bridges
Spans > 100 feet
Up to 8 feet. ROS ???

Very difficult to

build. Very high maintenance. Very high cost

R1 Trails Project Preparation

General Guidance
Trail Types
Hiking
Mountain Biking Pack and Saddle
Cross Country Skiing

Clear width
4
4
5 w/o rail 6 w/rail

Rail Height
42
54 54 42 Site specific

6 6

Snowmobile

Motorcycle
ATV
R1 Trails Project Preparation

42
50

42
27

General Guidance
Railing Are they needed?
Proposed manual direction says:
In general, rails shall be required for all trail and pedestrian bridges. However, railings may be eliminated and potentially curbs substituted for rails when an appropriate analysis as described below has been completed:
An analysis has identified and evaluated the potential users and determined that the potential hazards along the trail are the same or greater than that of a bridge without a rail. The analysis shall include the possibility of using a rail on only one side of the bridge. In general, rural and urban ROS settings are likely to have small children and less experienced users. Thus, a railing is warranted in most instances. In backcountry or wilderness settings, where users are normally more experienced, rails may not be needed.

R1 Trails Project Preparation

General Guidance
Pettibone to left, Goat to below on NP. Selway wilderness.

R1 Trails Project Preparation

General Guidance
Dome Mtn. Kootenai. Cabinet Wilderness
No Handrail!

R1 Trails Project Preparation

General Guidance
Type Sawn Stgr. Log Stgr. GL Stgr. GL Slab Single Log NL Slab Steel Truss Packable Tbr. Truss Suspension ROS Spans 10 to 40 10 to 45 25 to 60 10 to 35 10 to 45 12 to 30 > 60 < 36 > 60 > 100 Equipment Light Light/Med Medium Light Primitive/Light Primitive/Light Heavy Primitive/Light Light/Heavy Medium Maint. Low Low Low Low Low Moderate Low Moderate Moderate High Cost Low/Med Low/Med Low/Med Low Low Medium High High High High

R1 Trails Project Preparation

Wilderness Trail Bridges


Unique
What is

appropriate? What can you build? Is a bridge needed? Bob Marshall Wilderness

R1 Trails Project Preparation

Wilderness Trail Bridges


Design Process Add conceptual design before Project Scope Need alternatives
Bridge Type Construction methods Materials

Conceptual Design

Project Scope

Costs
Location/Survey

R1 Trails Project Preparation

Wilderness Trail Bridges


Minimum Tool analysis. Use of helicopters Force Account or Contract. Logistics!!

Wilderness bridges are the most complicated and expensive. Need special attention.

R1 Trails Project Preparation

Helicopter Usage
Helicopter contracts
Type I (Heavy) Sky cranes, etc Can pick up to 25,000 lbs. On call contract $9000/hour Must come out of West Coast. Mob costs prohibitive. Type II (Medium) 5000 to 12,000 lbs. On call contract $4500/hour Several in Montana, but not readily available.
R1 Trails Project Preparation

Helicopter Usage
Helicopter contracts
Type III ( Light) Can pick up to 5000lbs. On call contract $1800/hour For up to 3000 lbs, readily available.
Need to plan ahead and try to coordinate

with other work in the area to lower costs.

R1 Trails Project Preparation

Helicopter Usage
Helicopter Use - best value?
Small helicopter More trips More on-site labor (fly one stringer at a time) Big Helicopter Less trips. Less on site labor (fly in entire bridge superstructure)

R1 Trails Project Preparation

Preservative Treatments
What is life expectancy of permanent bridge? Life of untreated material? 15 to 20 years Life of treated material? 50 + years

R1 Trails Project Preparation

Preservative Treatments
Treated vs Untreated.
Manual Direction fpr

permanent structures
design life of 50 yrs
However, exceptions are

made. Who decides?


Forest
Treated material is

strongly recommended. Papoose Creek on Clwt NF

R1 Trails Project Preparation

Preservative Treatments
Protect the integrity of Treatment.
Cutting ends, drilling

holes, all ruins treatment.

Blue Sky Bridge on Ktn NF

Field treatments have limited success. To apply field treatments, person needs training and certification. Hassle!

R1 Trails Project Preparation

Preservative Treatment
Any laws against Treatment?
Only 1 by EPA
Can not use CCA in

members in direct contact with peoples skin. No others.

However, do we want oily treatment on handrails?

R1 Trails Project Preparation

Preservative Treatment
Options
Substructure,

stringers, deck, curbs


Penta, Copper Naphthenate

Handrail Treated many choices Untreated redwood or Red Cedar


Iron Springs - DPGL

Changing constantly

R1 Trails Project Preparation

Das könnte Ihnen auch gefallen