Beruflich Dokumente
Kultur Dokumente
Project Plan
Requirements
Activities
Schedule Baseline
Time-Phased Budget
Project Planning
Plan: A detailed scheme, program or method worked out beforehand for the accomplishment of an objective from Websters Dictionary Project Planning: The process of defining and putting into place beforehand the necessary systems and resources to allow the successful accomplishment of the objective within cost and schedule constraints. Project Planning is the process of defining: What?, Who?, When?, How?, How much?
Reliability 03.03
Environments 03.04
EPO 04.04
Facilities 01.05
Sci. Inves. & Ops Supt 04.05 Science Environmental Characterization 04.06
DSMS 07.05
NEPA 02.08
IV&V 03.10
V&V 5.02.03
Reliability 5.03.03
Magnetometer 5.05.03
I&T 5.02.04
Environments 5.03.04
IV&V 5.03.10
A complete narrative description of the specific work content of each element, defined with sufficient detail.
5.04.02: Structures and Mechanisms - Includes all design, testing, manufacturing of the airframe, deployment, hinging, latching, and energy absorbing mechanisms. This element also includes all control surfaces and the associated actuators, controllers, linkages, and other elements necessary to move the control surfaces. All tooling necessary for manufacturing the structures and mechanisms are included in this element. All materials testing necessary to determine and quantify structural properties for the material systems or the manufacturing methods are included in this element. All brackets, fasteners and other elements necessary for supporting, and isolating the remaining airplane subsystems and the science payload are included in this element. All pyrotechnically actuated cable cutters used for airplane deployment and deployment or release of any aerodynamic decelerator are included with this element. All aeroshell mounted or spider mounted pyrotechnically actuated fasteners or cable cutters are not included with this effort. All efforts associated with ensuring the hardware systems comply with the environment and achieve the proper level of space flight qualification are included with this effort. All efforts associated with defining, designing, manufacturing, testing, and characterizing the optical viewing windows for the Point Spectrometer and Context Camera are included with this effort. All efforts associated with defining, designing, manufacturing, testing, and characterizing the mounting for the tail mounted Video Camera are included with this effort.
WBS Dictionary
Outputs
Integrated project schedule Networks (flow) Critical path analysis Detailed schedules Milestone summaries Rec/dels
FORMULATION Pre-Phase A: Phase A: Advanced Mission & Systems Studies Definition Concept Review Phase B: Preliminary Design Project PDR Phase C: Design & Build
STEP 1 TMC
Project Assembly, Operations Post CDR Test & & Mission Launch Launch Readiness Assmnt Operation Reviews Review Readiness ORR & PLAR Review MRR ARR
Mission Briefing
Launch
Schedule Formats
Gantt or Bar Charts Milestone or Event Charts Networks (Enhanced) Gantt Charts
Bar Charts
Activity #1
Activity #2
Activity #3
Activity #4
Activity #n
Time
Displays activities or events against time. Bars represent duration of a single activity with appropriate start and stop dates. Open bars indicate work planned. Closed bars indicate work completed.
Activity #2
Activity #3
Activity #4
Activity #n
Time
Displays activity milestones against time. Lines represent duration of a single activity with appropriate start and stop milestones. Open triangles indicate milestones planned. Closed triangles indicate milestones completed.
Disadvantages
Activity inter-relationship/dependencies not shown Difficult to assess resource status vs plan Doesnt weight critical activities
Network Format
Highlights activity flow, inter-dependencies
B 3 D 3 E 4 F 1 G 2 H 1 K 3 J 2
Start
A 2
I 2
L 1
End
C 5
Critical Path: The sequence of activities with the longest cumulative duration. (ABEIJKL = 17 days) Slack: The amount of time that an activity can be delayed without extending the completion date of the entire sequence. (ACGL has 7 days of slack)
Activity #2
Activity #3
Activity #4
Activity #n Time
FY05
Phase C - Des
FY06
FY07
FY08
FY09
Phase E
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
S/C Fab S/C Phase D A/P Fab A/P Phase D CDR PDR S/C ARR Confirmation Review A/P ARR Inheritance Review A/P ATLO Start S/C ATLO Start FT-3
Build FM Build EM Build & Test FM Build FM Build FM Build FM
MRR
Launch
Science
B-2
B-3A
B-3B
B-4A
B-4B
B-5A
Build FM
STM
Carrier Spacecraft:
B-3
STL
B-1
B-2
B-4
B-5
B-6
Critical Path
Schedule Margin
Milestone
Duration (months )
2003
Se pt Oct No v De c Ja n Fe b Mar Ap r May
2004
Ju n Ju l Au g Se pt Oct No v
New Engineering
New Technology
Stardust, Genesis
CloudSAT GRACE
5
6 7
7
8 7
10
10 12
6
9 9
12
12 15
40
45 48
Moderately Complex Magellan Payload with New Odyssey Engineering Phoenix Moderately Complex Pathfinder, Deep Payload with New Impact, MER Technology Highly Complex Payload with New Engineering Highly Complex Payload with New Technology Mars Observer Voyager Galileo, Cassini, MSL
12
12
15
55
18
24
22
78
18
27
22
81
1 month/year
2 months/year
Flight Projects
ATLO Start to Implementation Start Ship to Launch Site/ to Delivery to Instrument I&T ATLO/ Start to Delivery Instrument I&T To ATLO
Definitions: Total Schedule = Planned Activities + Schedule Margin Schedule Margin = No Planned Activities, but Funded Schedule at Peak Workforce for that Mission Phase Schedule Margin Rate = Schedule Margin/(Planned Activity + Schedule Margin)
Earned value tools answer these questions by telling you what you got for the amount it cost you Earned value tools tells you what must be accomplished for the remaining dollars and the likelihood of achieving it
$
Overrun?
TIME
$
Actual Accomplishment
Earned Value
SV = Schedule Variance
TIME
TODAY