Beruflich Dokumente
Kultur Dokumente
Actual Lake Lanao Elevation as of Feb.20, 2012 is 700.73Meters against the 699.15Meters Critical Operating Level for Agus hydro plants Mindanao Grid Total Capacity as of Mar.27, 2012
Plant Type HYDRO COAL GEOTHERMAL DIESEL Total: Installed Capacity, MW 982 210 108 397 Peaking Capability, MW 678 200 97 135
1,697
1,110
Mindanao grid demand peak forecast is at 1,347MW for CY 2012 as per DOE.
2
Pulangi [3 x 85 = 255MW] Hydro Electric Power Plant shutdown on April 09 May 09, 2012 for Preventive Maintenance. Actual dispatchable capacity for Pulangi 4 HEP as of March 21, 2012 is only 30MW.
March 10, 2012 March 11, 2012 March 12, 2012 March 13, 2012 March 14, 2012 March 15, 2012 March 16, 2012 March 17, 2012
9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm
RED ALERT RED ALERT RED ALERT RED ALERT RED ALERT RED ALERT RED ALERT RED ALERT
Contingency reserve is ZERO due to generation deficiency Contingency reserve is ZERO due to generation deficiency Contingency reserve is ZERO due to generation deficiency Contingency reserve is ZERO due to generation deficiency Contingency reserve is ZERO due to generation deficiency Contingency reserve is ZERO due to generation deficiency Contingency reserve is ZERO due to generation deficiency Contingency reserve is ZERO due to generation deficiency
9:00am - 10:00pm
9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 10:00pm 9:00am - 5:30pm 5:30pm - 10:00pm
240
240 240 240 320 240 240 200 240 240 360
RED ALERT
RED ALERT RED ALERT RED ALERT RED ALERT RED ALERT RED ALERT RED ALERT RED ALERT RED ALERT RED ALERT
9:00am - 5:30pm
5:30pm - 10:00pm
280
240 200
RED ALERT
RED ALERT RED ALERT
9:00am - 10:00pm
System Deficiency LOAD TO MAINTAIN (MW) 80 162.21 0.2 1.4 9.6 0.0 0.0 7.1 107.1 13.1 2.4 21.21 20.5 10.8 120 156.21 0.2 1.4 9.2 0.0 0.0 6.8 103.1 12.7 2.3 20.42 20.0 10.5 160 150.33 0.2 1.4 8.9 0.0 0.0 6.5 99.2 12.2 2.2 19.64 19.4 10.2 200 144.33 0.2 1.4 8.5 0.0 0.0 6.3 95.2 11.7 2.1 18.85 18.9 9.9 240 138.34 0.2 1.4 8.2 0.0 0.0 6.0 91.2 11.2 2.0 18.07 18.3 9.7 280 132.44 0.2 1.4 7.8 0.0 0.0 5.8 87.3 10.7 1.9 17.28 17.7 9.4 320 126.56 0.2 1.4 7.5 0.0 0.0 5.5 83.3 10.2 1.9 16.50 17.2 9.1 360 120.51 0.2 1.4 7.1 0.0 0.0 5.2 79.3 9.7 1.8 15.72 16.6 8.8 400 114.77 0.2 1.4 6.8 0.0 0.0 5.0 75.4 9.3 1.7 14.93 16.1 8.5
174,032 244 1,449 10,298 7,590 115,000 14,120 2,554 22,777 21,662 11,421
168.00 0.2 1.4 9.9 0.0 0.0 7.3 111.0 13.6 2.5 21.99 21.1 11.1
Prepared by:
Note: 440MW to 520MW Grid Deficiency is extrapolated based on March 2012 Matrix as provided by NGCP at w/c CD of CEPALCO is 115MW. April 2012 CD of CEPALCO is 121MW hence expectedly the Load to Maintain by CEPALCO will be improved. Extrapolation is done since NGCP did not yet provide their April 2012 Matrix
Based on CEPALCOs System Power Availability Matrix, CEPALCO will experience a power shortage at 360 MW Mindanao Grid Deficiency when its System Peak Demand reaches 130 MW CEPALCO will have a power shortage of 19.6 MW if the Grid Deficiency will reach 520 MW at a CEPALCO System Peak of 130 MW. CEPALCOs System Peak as of March 2012 is 125 MW
Butuan City and Agusan Norte Areas : 1 to 2 hours per area, only once this week Agusan Sur Areas : 1 to 3 hours per area, once this week Gingoog Areas : 2 to 3 hours per area, twice this week Iligan City : 1 to 2 hours per area, once this week Lanao Norte Areas : 1 to 2 hours per area, twice this week Lanao Sur Areas : 2 to 3 hours per area, twice this week Zamboanga Areas : 1 to 3 hours per area, once this week Bukidnon Areas : 2 to 3 hours per area, twice this week MORESCO 1 Areas : 1 to 2 hours per area, once this week Surigao Areas : 1 to 2 hours per area, twice this week CEPALCO : None
The following customers have signified their enrollment to the ILP totaling a potential of generation capacity of 23.30 MW:
o o o o o o o o o o LKKS CENTER LKKS MILLING GAISANO DEL MONTE MITIMCO ALWANA CAG. CORN RI CHEM PKI SM CITY 7.0 MW 1.0 MW 3.5 MW 2.0 MW 1.0 MW 1.0 MW 2.0 MW 1.8 MW 2.0 MW 2.0 MW
TOTAL: 23.30 MW
12
Thank You
13